HomeMy WebLinkAboutUnit 2August 16, 1974
Mr. R. A. Bluem, G.E.
Vice President Engineering
,.
General Development Corp
1111 South E3ayeho3caP Drive
i
Miamei# Florida 33131
Dear Boba
I have sent you three letters advising that the ditches of
Unit #1 - phases I, II, and III, have been accepteed. It is
my understanding that Phases Iii and V aro nearing completion.
Before we will accept Phases IV and V, we desire confirmation
from you that Unit J2 plans are in our hands for approval so
there will be no great delay in the handling of Unit #2.
DFor your information, 1 was advised the other day that sweles
had been cleaned out in an am ohms Allied Construction
Company had built two houses an Berber Street. I received a
complaint from one of our people living in that area as to
why wales were dug out for new houses in which there is no
one living at the present times, but for years nothing has been
done about the drainage system in Unit d2.
In checking with your people, I find that your Land Developinant
Department took it upon themswelvees, at the request of Allied
Construction Company, to provide this drainage. However, when
you follow the drainage that was provided, it does not drain
any place. Also, I think that before any such drainage is
provided in an area that has needed it for years, the City
should have been advised of the steps being taken.
<e would appreciate your advice as to when on will receive plans
for Unit #2.
Very truly yours,
F. Eugene Cragg
alayor
FEC%e3c