February 2, 2010
Mr. Joe Griffin
Airport Manager
City of Sebastian
202 Airport Drive East
Sebastian, Florida 32958
Subject: Sebastian Municipal Airport—Runway 4-22 Improvements
Bid Tabulation, Review and Recommendation
Dear Mr. Griffin:
On Thursday January 28, 2010 I received a letter from West Construction, (via Chris Caprio)
(attached). West Construction claims they are substantially complete with the Runway 4-22
Improvements project. On the same day I have verified the project meets substantial completion.
The punchlist inspection was conducted on January 28, 2010. Punchlist items include the following:
I. GENERAL: clean up of runway shall include removal of dirt/debris found on and along
sides of runway 4-22.
2. Remove silt fence and discard from project
3. At runway #4 fill concrete at cut joint on 3 lights.
4. At taxi way A, remove and replace radius section of yellow line at lead in for cleaner
radius line.
5. West Construction shall water grassing at least once a week for the next week or so to
achieve establishment of seed and sod.
6. Brass identification tags are required on each of the lights but John did not think they
were necessary. Therefore, they will not be installed.
7. The taxiway lead-in stripe onto taxiway E needs to be removed.
At this point the only outstanding items that remain are:
+ The as -built drawings
+ AIP survey
+ Other closeout documents
In accordance with the contract, we will have a final inspection to outline any outstanding items. The
final inspection will be held Thursday February 4, 2010 at 9:00 am.
Please let me know if there are any comments or questions.
ATLANTA ■ BATON ROUGE ■ CHARLOTTE ■ COLUMBIA ■ GREENSBORO ■ JACKSONVILLE ■ KENNESAW ■ KNOXVILLE ■ LITTLE ROCK
McLEAN 0 MOBILE ■ NASHVILLE ■ OCEAN SPRINGS 0 ORLANDO ■ RALEIGH ■ SARASOTA ■ TALLAHASSEE 0 TAMPA 0 WEST PALM BEACH
Mr. Joe Griffin, Page 2
If you have any questions or if we can be of further assistance, please do not hesitate to contact me.
Sincerely,
THE LPA GROUP INCORPORATED
Robert K. Hambrecht, P.E.
Project Manager