HomeMy WebLinkAbout2009 LPA Group - Engineer's Report.,
.,
�+ 100% ENGINEER'S REPORT
FOR
RUNWAY 4-22 IMPROVEMENTS
AT
SEBASTIAN MUNICPAL AIRPORT
SEBASTIAN, FLORIDA
a"
m
..
.N
MUNI-1PAL AIRPORT
CITY OF SEBASTIAN
AUGUST 2009
..THE F
LPA
GROUP
AVIATION CONSULTANTS
^
^
TABLE OF CONTENTS
^
ENGINEER'S REPORT
For
^
RUNWAY 4-22 IMPROVEMENTS
At
^
SEBASTIAN MUNICIPAL AIRPORT
SEBASTIAN, FLORIDA
.,
Introduction.........................................................................................................................1
SiteInformation.................................................................................................................. 1
ProjectDescription.............................................................................................................. 2
.,
Design Criteria.................................................................................................................... 2
Vertical Alignment And Transverse Grades....................................................................... 2
Condition Of Existing Pavement........................................................................................ 2
..,
Electrical.............................................................................................................................2
Drainage Design And Permitting........................................................................................ 3
PavementMarkings............................................................................................................ 3
.,
Construction Phasing..........................................................................................................4
ConstructionTime.............................................................................................................. 4
Modifications to Standards................................................................................................. 4
^
Availability of Contractors................................................................................................. 4
Safetyand Security Plan..................................................................................................... 4
Construction Cost Estimate................................................................................................. 6
^
Contract Time..................................................................................................................... 6
Appendix A — Engineer's Estimate
^ Appendix B — Geotechnical Report
Appendix C — Taxiway Dimensional Standards from FAA AC 150/5300-13
^
M
M
ENGINEER'S REPORT
SEBASTIAN MUNICIPAL AIRPORT
Sebastian, FL
FAA AIP PROJECT No. TBD
FDOT PROJECT No. TBD
CITY PROJECT No. TBD
RUNWAY 4-22 IMPROVEMENTS
INTRODUCTION
.. This design report has been prepared as a supplement to the project documents for the
Runway 4-22 Improvements project at the Sebastian Municipal Airport. The City of
Sebastian intends to remove asphalt pavement from the shoulders and useable width of
., Runway 4-22 for the entire 4,000' length in order to standardize the runway. The runway
will also be remarked for visual approaches on both ends.
The purpose of this report is to
define the design parameters,
evaluate and present design
recommendations, identify
potential conflicts, outline
construction considerations, and
.. estimate costs.
LPA has acquired and reviewed information on existing site conditions. KSM
Engineering and Testing completed a geotechnical investigation on August 6`h, 2009. A
copy of the geotechnical investigation can be found in Appendix B of this report.
Preliminary field data collection was completed, and base maps have been prepared and
field checked for accuracy. A field visit was performed by LPA on August 6` , 2009 to
evaluate the site conditions, and record visual and geotechnical findings.
SITE INFORMATION
The Sebastian Municipal Airport is located in Indian River County, Florida. The Airport
is located only 1 mile West of Sebastian. Two active runways serve the Airport: Runway
4-22 and Runway 8-26.
+ Runway 4-22: Length: 4,024 feet
Width: 150 feet
Approaches: Visual both ends
+ Runway 8-26: Length: 3,200 feet
Width: 75 feet
Approaches: Visual both ends
Page 1 of 6
August2009
PROJECT DESCRIPTION
The overall project consists of one base bid and one additive bid. All materials and work
are in accordance with FAA approved standards.
Runway 4-22 serves primarily general aviation, and is the longest runway at the Airport.
The runway is currently 100' wide with 25' paved shoulders. This project consists of
_ removing pavement from the shoulders and the useable width of Runway 4-22 for the
entire 4,024' length, narrowing the runway width to 75', remarking the runway for visual
approaches, and relocating edge lighting.
DESIGN CRITERIA
The design criteria for this project have been based on applicable FAA Advisory
Circulars, existing site conditions, and professional judgment. The proposed runway's
geometry has been designed to accommodate aircraft in Design Group II, Approach
Category A&B.
TRANSVERSE GRADES
The existing site is relatively flat, with
no significant elevation variances.
The existing transverse pavement
grade is below the maximum 1.5% as
stated in AC 150/5300-13.
Constructed grass shoulders will be
below FAA standards for shoulder
cross slope. The pavement being
removed from the runway and shoulders is currently at a 0.5% average cross slope.
Cross slope beyond the pavement is at or below FAA standards for runway shoulders. To
meet FAA cross slope standards, a major grading and drainage plan would be required.
CONDITION OF EXISTING PAVEMENT
The existing 75' width of pavement along Runway
4-22 is in good condition. There does not appear to
be any significant cracking throughout this area. The
shoulder pavement and runway pavement outside of
75' is in poor condition. There are several medium
to high severity fatigue (alligator) cracks throughout
the pavement area.
ELECTRICAL
The narrowing of Runway 4-22 from 100' to 75' will require the adjustment of the
existing medium intensity runway lighting system to meet the FAA Advisory Circular
150/5340-30D requirements. Per the FAA Advisory Circular, the edge lighting system
may be located with an offset of 2' to 10' from the delineated edge of full strength
Page 2 of 6 August 2009
M
M
M
M
M
The existing edge light base cans will
pavement. Sebastian Municipal Airport has
elected to relocate the existing edge light system
to be 2'6" from the edge of pavement.
The existing edge lighting system was replaced
in 2001 with base can mounted edge lights and a
new conduit and conductor system. The existing
light fixtures are in good condition and will be
relocated while the existing edge light base cans,
wiring and conduit systems will remain in place.
have new L-867 steel covers installed and be
converted to junction cans. New edge light base cans will be installed 2'6" inches from
the edge of pavement, and the existing fixtures will be relocated to the new locations.
The existing L-867 base cans will be core drilled and the existing conduit and circuit
conductors intercepted and extended to the relocated edge lighting system.
The existing flush mounted edge light base cans will be abandoned in place and the
fixtures will be relocated to the new runway light positions. New L-868 steel covers will
be installed and the existing conduit system will be intercepted outside of the full strength
., pavement by a new L-867 junction can. New conduit and conductors will be installed in
the relocated fixture location.
M
..
M
DRAINAGE DESIGN AND PERMITTING
There will be no addition of impervious area constructed as a part of this project. The
existing drainage design and facilities will be maintained to accommodate for the changes
to the impervious area. Where pavement is removed, the areas will be replaced with
topsoil and sod.
PAVEMENT MARKINGS
All pavement markings will be placed to conform
to the updated FAA Advisory Circular 150/5340-
1J, "Standards for Airport Markings," using paint
meeting requirements of Federal Specification TT-
P -1952D. All white and yellow markings will be
retro reflective, using glass beads per Federal
Specification TT -B-1325, Type Ill. Marking shall
only be performed when the existing surface is dry
and clean, and when the weather is not excessively
windy or foggy. The Engineer will determine the
suitability of these conditions. The existing markings that are substandard will be
removed using a microsurfacing process that will not damage the pavement but remove
95% of the existing markings.
Page 3 of 6 August 2009
no
CONSTRUCTION PHASING
The continued operation of the Airport is of the utmost importance. Therefore, the
project has been broken up into four phases. Intermediate closures of taxiways and
runways will be required depending on the phase. Phases and sections have been
oriented to provide the least amount of interruption to aircraft operations.
+ Phase 1: 30 Calendar Days
+ Phase 2 60 Calendar Days
Procurement of Materials.
Construction. RW 4-22 Closed.
• Phase 3: 10 Calendar Days Night Construction. Airport Closed.
• Phase 4: 30 Calendar Days Project Closeout.
CONSTRUCTION TIME
The work described by the contract documents and shown on the plans shall be
completed and ready for use within allotted consecutive calendar days after the notice to
proceed. There are a total of four phases. Additional days can be added to the phases for
inclement weather, wet pavement, or other wind conditions not ideal for paint
application. The total construction time for the overall project is 130 Calendar days.
Each phase has a $200 per day liquidated damages amount. Liquidated damages shall be
deducted from the money due the Contractor or his surety for failure to complete work
within the contract time specified. As liquidated damages, the Contractor shall pay the
owner the sum specified for each consecutive calendar day that expires after the time
.,
specified. Liquidated damages will be assessed if the Contractor exceeds the total
number of calendar days specified for the project. In addition, liquidated damages will
also be assessed if the Contractor exceeds the calendar days specified for each phase.
MODIFICATIONS TO STANDARDS
As stated earlier, runway shoulder slopes will not meet FAA minimum standards.
AVAILABILITY OF CONTRACTORS
Contractors will be advised of this construction project through advertisements by the
City of Sebastian. Construction plans will be made available to all interested bidders
upon proper request. Numerous local and out -of- state Contractors are available to bid on
this construction project. Proper certification through the City, as well as strict DBE
participation, is required. Additionally, all construction equipment needed for the
successful completion of this project may be found locally.
SAFETY AND SECURITY PLAN
Aviation safety and Airport security are the primary considerations during Airport
construction. Construction activities shall be planned and scheduled to minimize
disruption of normal aircraft, ground and air traffic.
Page 4 of 6 August 2009
r�
M
go
W
M
This plan shall be used to address specific safety measures which FAA employees,
grantees (Airport Owners), and Contractors shall adhere to during construction activities
on airports to provide a reasonable level of safety for aircraft operations, inclement
weather, security and local rules.
1. The Project Engineer and/or Airport
Responsible Representative have established
haul routes and they are shown in the plans.
The Contractor will insure compliance with all
haul routes. The overall control of the Airport
will remain with the City of Sebastian
(Airport Responsible Representative and/or
Project Engineer).
2. Daily Clean Up before securing will be
the responsibility of the Contractor's
personnel. The Contractor will provide trash containers with heavy lids and will locate
them off the Runways and Taxiways, so debris will not be blown onto Airport Grounds
or the Aircraft Operations Area. No accumulation of mud rocks, sand, gravel, plastic or
paper will be allowed on the taxiways or runways and will immediately be removed
before Aircraft traffic is allowed to resume. A large broom will be required to assist in
cleaning the area of any debris. This daily clean up also applies to the Airport Grounds.
Authority personnel shall inspect the Airport each weekday morning at 7:00 AM. If
discrepancies exist, they will be addressed at that time.
3. Construction barricades shall be constructed as shown on the Phasing Plan sheet
conforming to AC 150/5370-2E. Depending on the sequence of construction, these may
be used more than once. Barricades will placed and removed at the beginning and end of
each work day.
4. The Contractor's Superintendent or Designated Employee shall have a portable
radio and shall monitor air traffic and ground frequencies at all times during construction
and when construction is adjacent to an active
taxiway or runway. The employee with the
radio shall make sure that the aircraft has right-
of-way.
5. Contractor's personnel are restricted to
the construction area and shall keep off the
taxiway and runways except when necessary for
construction. Most often the portion of a
taxiway or runway will be closed during this
construction. One gate will be assigned for
Contractor's access. The Contractor is responsible for all personnel passing through this
gate and also for keeping it locked when not in use.
Page 5 of 6 August 2009
M
6. A detailed sequence of construction is shown in the plans on the Phasing Plan
sheets. If the Contractor has an alternate sequence plan that would improve the method
shown, it must be submitted and approved by the City of Sebastian and FAA.
CONSTRUCTION COST ESTIMATE
Appendix A contains the engineer's opinion of order of magnitude construction cost
estimate for the listed base bid for this project.
CONTRACT TIME
., The bidding will begin August 17'h, 2009 and end September 7'h, 2009.
Construction is expected to begin in October 2009.
LJ
M
M
L1
M
A
Page 6 of 6 August 2009
OR
.,
m
w
an
..
m
Im
an
F,
APPENDIX A
ENGINEER'S ESTIMATE
MUNICIPMTCistir
Project Runway 422 improvements
Sulxni 100". Design
CM Project No.: Unknown
IPA Protect No: FAH41202
Sebastian Munsipal Airport
City 01 SebaSisn
EnBkaels Estirete
OR uv ���
... CO nstalm
Estimate Data: Aug -O6
Estimator JC
Checked: BR, BH
Bid hem
hem No.
hem0esk iptbn Una
Quantity Unit Pries
Wooden
Base Bid
1
01000
Mobilization
LS
1
$35,8W.W
535,80000
2
5-150.1.3
Erosion Control
LS
1
55000.00
55,000.00
3
P-180.5.1-1
6' Depth Pavement Milling
SY
32,900
S4.W
5131,600.00
4
P-180.5.1-2
1.5' Depth Pavement Milling
SY
200
siLoo
52,00000
5
5-190.6.1
Pavement Marking Removal
SF
1,800
$4.00
$7,200.00
6
P-401-8.1
Bituminous Pavement
TON
20
$200.00
$4,000.00
7
P-603-5.1
Tack Coat (0.1 GaUSY)
GAL
20
$5.00
$100.00
8
P-610.5.1
Structural Portland Cement Concrete (with Woven Who, Fabric)
CY
40
$300.00
$12,000.03
9
P-620.5.1-1
Reflective Pavement Markings(White)
SF
5,800
S2.W
$11'Bol
10
T-904-5.1
Sodding (Bermuda)
SY
32,900
$1.75
557,575.00
11
T-905-5.1
Topsoil
SY
32,900
$200
$65,600.00
Hand excavate minimum 8" Wide x 26' Deep in earth, Includes all labor, hand excavation, backfill
12
L-108-5.1
and sod resloration, complete in place.
LF
100
$8.00
5500.00
Hand excavate minimum 18" Wide x 36" Deep in earth, Includes all labor, hand excavation, backfill
13
L-108-5.2
and sot restoration, complete in place.
LF
100
$1300
51,300.00
314- x 20' Ground Rod Connected to Counterpoise every 507. Includes all labor, installation.
14
L-108-5.3
ground rod, splice kits, testing, backfill. Connections, exothermic weld. and etc. complete in place.
EA
7
5150.00
$1,050.00
3/4' x 10' Addftional Ground Rod Sections. Includes all labor, excavation, installation, ground rod,
15
L-1085.4
splice kits, ceding, backfill, Connections, exothermic weld and etc. complete in place.
EA
2
575.00
$10000
#6 Bare AWG Solid Counterpoise Conductor Installed above Conduit. Includes all labor,
16
L-108-5.5
excavation, Installation, splice kits, testing, backfill, connections, exothermic weld and etc. complete
LF
1,500
$150
$2250.00
n place.
#8, SKV, L-824 Conductor Installed In new and existing CondulU Ductbank/Manhole system.
Includes all labor, Installation, testing. Identification, removal and disposal of existing conductors,
17
L-108-5.6
pull string, pulling compound. cleaning and dewatering ofconduil systems, splice kits, and etc. for a
LF
4,000
E7.75
$7,030.03
complete working system In place.
1-2" Schedule 40 PVC conduit direct burled in earth/compacted subgrads complete In place.
18
L-110.5.1
Includes excavation, labor, Conduit, Connectors, warning tape, pull string, sod restoration, backfill
LF
1100
$8,00
$$,$0000
and etc. Complete in place.
1-2" Schedule 40 PVC concrete encased Conduit installed in existing Poll strength pavement
complete in place. Includes saw cutting of pavement. excavation, Concrete, Conduit, connectors,
19
L-110.5.2
warning tape, pull string, labor backfill, asphalt and pavement repair and etc. complete in place.
LF
400
§30.00
512,0001x1
Intercept existing Conduit system in earth/existing pavement, Connect to new Conduit system and
extend circuit conductors accordingly. Includes hand excavation, saw cut of pavement, backfill,
shoulder repair, Concrete, conductor removal and replacemen6 Connection to existing circuit
20
L-1145.3
conductors, cleaning and dewatering of conduits, Connecta kits, pull string, connection of
EA
12
$25000
$J,000.W
Counterpoise, identification, conduit, Couplings, labor and etc. complete In pine.
L-86716" diameter )unction can with Cover Installed in earth/naw shoulder pavement. Includes
installation, excavation, base can, Concrete, L-867 cover, connector kits, rock, ground lugs,
21
L-115-5.1
exothermic weld ground rode, safety ground, testing, stainless steal bolts, anti -seize Compound
EA
4
$1,500,00
S81000100
backfill, Identification, sad restoration and etc. complete in place.
Adjust existing L-86812' diameter function Can in existing full strength pavement. Includes coring of
pavement. L-868 Cover, extension rings, spacers, dam rings, P-606. P605, circuit identification,
22
L-115-5.2
connector kils,anti-selling Compound, Concrete, pavement repair, excavation, labor and etc.
EA
1
§200000
§200000
complete in place
Intercept existing L-867 light base can to eaMfaxoting pavement, connect to new Conduit system
23
L-115-5.3
and extend circuit accordingly. Includes saw cutting. hand excavation. Cora drill and repair can,
EA
45
$350.00
$15,7500
backfill. Concrete. pavement repair, labor and etc. Complete in place.
New L-861 Runway Elevated Edge Light and base can installed in earth/new shoulder pavement.
Includes excavation. fixture. L-867 base can. Concrete, stainless steel hardware. anlFseizing
24
L-1255.1
compound, backfill, Identification. splice kits, base plate, ground red, safety ground, ground lug.
EA
2
$120000
$2,400.00
exothermic weld, transformer, Connector kits, testing, rock, labor and ate. Complete in plata
Relocate existing L-861 Runway elevated edge Light with new base Can Instatted In
earth/compacted subgrade,compiete. Includes excavation, core drill, new L-867 base can, concrete,
25
L-125-5.2
stainless steel hardware, anti -seizing compound backfill, identification, splice kits, ground rod,
EA
41
$750.00
$30,750.00
safety ground, ground lug, exothermic weld, new transformer, new lamps, clean lens, connector
kits, testing, labor and etc. complete In place
dli
tor=
PER
MEN
rat
1Ra
No
IIIIIIIII
SO
A
PER
m
m
MUNICIPAL AIRPORT
Pmjecb Runway 422 Improvements
Sulunillel: 100% Design
CM Project No.: Unknown
1PAPmk M, FAH119aa9
Sebastian Municipal Airport
City of Sebastian
Engineefs Fslimale
URA
GROUP �B
lxaxsromsaeaIP Aa
Estri Date. Aug -09
Estmi lar JC
Checked. BR, RN
Additive Bid 1
Relocate existing Runway Flush edge Light and new base can Installed In existing full
1
5-190-6.1
Pavement Marling Removal
strength/shoulder pavement. Includes 2 piece 12' diameter L-868 base can, coring of pavement,
300
S4,00
512DD.00
2
P-520.5.1-1
Refiedive Pavement Markings (White)
extension rings, spacers, new lamps, dam rings, P-606, P605, circuit identification, connector kits,
21,100
52.00
$42200.00
3
26
L-125-5.3
rebar, grounding, new transformers, stainless steel hardware, anti-seliing compound, exothermic
EA
5
83,000.00
$15 110
P-520-5.1-3
Norl-reflective Pavement Markings (Black)
weld, safety ground, ground lug, ground rod, testing, concrete, pavement repair, excavation, labor
1,600
52.00
$3200.00
and etc. complete in place
$
85320000
Provide new L-867 cover on existing 12' diameter base can, complete. Includes labor, sawculting
of existing asphalt, removal of fixtures, new L-867 cover, connections, splice kits, disconnection of
27
L-125-5.4
existing circuit. relocation of fixture, reconnection of existing circuit, connector kits, temporary
EA
37
8300.00
$11,100.00
wiring, and etc. complete In place.
Provide new L-868 cover on existing 12' diameter L-868 base can In existing shoulder, complete.
Includes labor, sawcu8ing of existing asphalLfixture removal, L-868 cover, connections, splice kits,
26
L-125-5.5
disconnection of existing circuit. relocation of fixture, drilling and tapping of damaged bolts,
EA
4
S10o w
81,600.00
reconnection of existing circuit, temporary wiring, and etc. complete In place.
Provide new L-868 cover on existing 12' diameter L-868 base can In existing full strength
pavement, complete. Includes labor, coring of existing pavement, L-868 cover, fixture removal,
29
L-125-5.6
connections, splice kits, relocation of future, new spacer rings, P-605, drilling and lapping of
EA
2
570000
81,100.00
damaged bolts, new bolts, disconnection of existing circuit, relocation of fixture, reconnection of
existing circuit, temporary wiring, and atc. complete in place.
Removal of existing base can installed in earth, complete. Includes excavation, disposal of base
30
L-125-5]
can and relocation of edge light, backfill, sod restoration, Iabw and etc.
EA
12
530000
83,800.00
Identification of Cables, Ductbanks and Lighting Fixtures per FAA Specifications. Includes concrete
31
L-125-5.8
dud markers, tags, labor, lasting, and etc. complete in place.
LS
1
$2,00080
52,000 W
Provide and maintain temporary wiring and conduits for lighting beyond construction area during
construction. Includes jumpers, conduits, conductors, connector kits, splice kits, sandbags,
32
L-125-5.9
anchors, identification, equipment, dewatering, testing. labor and etc. for a complete working
LS
1
82,500.00
82,500.00
system In place.
Intercept existing circuit conductors In existing base can, complete. Includes conductor removal and
33
L-125-510
replacement, connector kits, transformer, splice kits, drilling and tapping of threaded bolt hole, new
EA
85
5200.00
817,000.00
stainless steel hardware, testing, identification. labor and etc. for a complete working system in
place.
Relocate existing L-861 Runway elevated edge Light with new base can installed in existing
pavement,complete. Includes excavation, core drill, new L-867 base can, concrete, stainless steel
34
L-125.5.17
hardware, anti -seizing compound, backfill, Ide bficalion, splice kits, ground rod, pavement repair.
FA
8
5900.00
51200,001
safety ground, ground lug, exothermic mid. new transformer, new lamps. clean lens, connector
kits, testing, labor and etc. complete in place
TOTAL BASE BID AMOUNT= 5 $48722500
Additive Bid 1
1
5-190-6.1
Pavement Marling Removal
SF
300
S4,00
512DD.00
2
P-520.5.1-1
Refiedive Pavement Markings (White)
SF
21,100
52.00
$42200.00
3
P-620-5.1-2
Refiective Pavement Markings (yellow)
SF
3.300
5200
88,800.00
4
P-520-5.1-3
Norl-reflective Pavement Markings (Black)
SF
1,600
52.00
$3200.00
TOTALADDRMEI AMOUNT=
$
85320000
2orl
m
.,
m
APPENDIX B
m
GEOTECHNICAL REPORT
m
m
.o
pq
dW
IN
on
OR
m
KSM
KELLER, SCHLEICHER & MacWILLIAM ENGINEERING AND TESTING, INC.
MARTIN (772) 337.7755 P.O. BOX 78-1377, SEBASTIAN, FL 32978-1377 SEBASTIAN (772) 589-0712
PALM BEACH (561) 846-7445 wwwAamenalneering.net MELBOURNE (321) 768-8488
FAX (681) 645-8876 E -Mail: KSM@KSMENGINEERING.NET ST. LUCIE (772) 229-9093
C.A.: 5693 FAX (772) 589.6469
August 10, 2009
Rob Hambrecht, P.E.
The LPA Group, Inc.
615 Crescent Executive
Suite 200
Lake Mary, Florida 32746-2146
Re: Pavement Cores
Sebastian Municipal Airport
Runway 4-22 Improvements
Sebastian, Florida
KSM Project #: 900928
— Dear Mr. Hambrecht:
As requested, ten (10) pavement cores were constructed in the asphalt runway at the
— referenced site. The pavement cores were performed in the locations as recommended
on the attached Location Plan provided to our office
.. In general, the pavement consists of an asphalt surface with a base material consisting
of gray and brown sand with some clay and shell, except at pavement core 07 where
we found a 4" thick rock base material and then stabilized subgrade material consisting
.� of gray and brown sand with some clay and shell. Please see the attached pavement
logs.
M
—
If you have any question, please feel free to calf me.
XQP�
Rn . K r, P'
Jtlli E. eller, P.E, nn�� Ql
RGK:ao C? ^v /
Ronald G. Keller, P.E.:372931 SI Lic. No.: 860 / Julie E. Keller, RE.: 68366
r
KSM
KELLER, SCHLEICHER & MaoWILLIAM ENGINEERING AND TESTING, INC.
MARTIN (772) 337-7755 PO, BOX 78-1377, SEBASTIAN, FL 32978-1377 SEBASTIAN (772) 589-0712
PALM BEACH (561) 845.7445 www.ksmengineering.net MELBOURNE (321) 768-6486
FAX (561) 645-8876 E -Mail: KSM®KSMENG1NEERING.NET ST. LUCIE (772) 229-8093
FAX (772) 569-9469
Sebastian Municipal Airport page 1
., Runway 4-22 Improvements
Sebastian, Florida
KSM Project #: 900928
M
LA
r
r
r
r
r
Pavement Core #1, See Attached Location Plan
11/1,
Asphalt
3" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #Z, See Attached Location Plan
1 '/4" Asphalt
8" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #3, See Attached Location Plan
1 '/" Asphalt
8" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #4, See Attached Location Plan
1 '/ Asphalt
8 %:" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #5, See Attached Location Pian
1 %" Asphalt
B. Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #6, See Attached Location Plan
1518" Asphalt
8" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24'
Ronald G. Keller, RE.: 37293 / Si Lie. No-: 860 / Julie E. Keller, P.E.: 88366
—
—
M
�1
—
—
KSM
KELLER, SCHLEICHER & MaCWILLIAM ENGINEERING AND TESTING, INC.
MARTIN (772) 337-7765 P.O.BOX 78-1377, SEBASTIAN, FL 32978-1377 SE
FAX
BASTIAN (772) 589-0712
AM 6)845-B w.
61}845-7445 wwksmengineenng.nm MELBOURNE(321)768-8468
FAXX(561) 845-6876 E -Mail: KSMQKSMENGiNEERING.NET S7 LUCIE (772) 229-9093
GA.: 6693 FAX (772) 589-6469
Sebastian Municipal Airport Page 2
Runway 4-22 Improvements
Sebastian, Florida
KSM Project#: 900928
Pavement Core #7, See Attached Location Plan
2 %" Asphalt
4" Cemented Coquina Rock
10" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #8, See Attached Location Plan
1 '/2" Asphalt
7'/Z' Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #9, See Attached Location Plan
1 9 Asphalt
5 %2" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Pavement Core #10, See Attached Location Plan
2" Asphalt
6" Gray and Brown Sand with Some Clay and Shell
Then Gray Sand to a depth of 24"
Ronald G. Keller, RE_ 37293/SI Lic. No.:860 / Julie E. Keller, P.E.:08366
.,1 l_ .
J.
Ao♦
=�Y�♦ •\ .-�\. i'y,'/. eC .' _' .i/ ..F 'cif-� -'r Li Kg 9s '
Iii 2
�� �^ r"�"°,fin' •�♦ �\'��.d` `•�', � ; ' ,�{ e�i'� I
Af
iz
..�- _♦./'t'�, °%•G. \ I. .iii
% _.:��`,*�`:a• , is
,.
TtWAY 4 z�z
L EGEN D
.0. PAVEMENT CORE LOClA7.10M
��D C Ai 1 oN PLAN
r
om
om
w
w
m
APPENDIX C
RUNWAY DIMENSIONAL STANDARDS
FROM
FAA ADVISORY CIRCULAR 150/5300-13
W
M
OR
so
M
..
1/3/08
AC 150/5300-13 CHG 12
Table 3-1. Runway design standards for aircraft approach category A & B visual runways and runways with not
lower than 3/4 -statute mile (1,200 m) approach visibility minimums
(Refer also to Appendix 16 for the establishment of new approaches)
ITEM
DIM
1/
AIRPLANE DESIGN GROUP
12/
I
1 II
I III
IV
Runway Length
A
4/
Refer to
paragraph 301
-
Runway Width
B
60 ft
60 ft
75 ft
100 ft
150 ft
the runway end as provided by nate 4 above.
l8m
18m
23m
30m
45m
Runway Shoulder Width
10 ft
10 ft
loft
20 ft
25 it
3m
3m
3m
6m
7.5 to
Runway Blast Pad Width
80 ft
80 ft
95 ft
140 ft
200 ft
24 m
24 to
29 m
42 m
60 m
Runway Blast Pad Length
60 ft
loo ft
150 ft
200 ft
200 ft
18m
30m
45m
60m
60 to
Runway Safety Area Width
C
120 ft
120 ft
150 it
300 ft
500 ft
36m
36m
45 m
90M
150 m
Runway Safety Area
240 ft
240 ft
300 ft
600 ft
600 ft
Length Prior to Landing
Threshold 3/, 4/
72m
72m
90M
180 m
180 to
Runway Safety Area Length
P
240 ft
240 ft
300 ft
600 ft
1,000 ft
Beyond RW End 3/, 4/
72 m
72m
90M
180 to
300 m
Obstacle Free Zone Width
- Refer to
paragraph 306
-
and Length
Runway Object Free Area
Q
250 R
400 ft
500 ft
10011
11011
Width
75 m
120 m
150 m
240 m
240 m
Runway Object Free Area
R
240 ft
240 ft
300 ft
600 ft
1,000 ft
Length Beyond RW End 5/
72 m
72m
90 m
Isom
300 m
1/
Letters correspond to the dimensions on figures 2-1 and 2-3. Use this table only when both ends of the runway
provide not lower than''%-smmte mile approach visibility minimums.
2/
These dimensional standards pertain to facilities for small airplanes exclusively.
3/
The runway safety area (RSA) length begins at each runway end when a stopway is not provided. When a stopway
is provided, the length begins at the stopway end.
4/
The standard RSA length beyond the runway end may be reduced to the standard RSA length prior to landing
..
threshold if a standard Engineered Materials Arresting System (EMAS) is provided. To qualify for this reduction,
the EMAS installation must provide the ability to stop the critical aircraft exiting the end of the runway at 70 (mots,
and the runway must provide either instrument or visual vertical guidance for approaches in the opposite direction.
See AC 150/5220-22.
5/
The runway object free area length beyond the end of the runway never exceeds the standard RSA length beyond
the runway end as provided by nate 4 above.
Chap 3
25