Loading...
HomeMy WebLinkAbout2009 LPA Group E-MailPage 1 of 1 Joseph Griffin From: Burton, Arthur H. [AHBurton@lpagroup.com] Sent: Thursday, December 31, 2009 4:24 PM To: Hambrecht, Rob Cc: Joseph Griffin Subject: Concrete issue/Rnwy 4-2 Rob: As of 4:10 PM this date the following action is being taken at Sebastian Muni to resolve the concrete failure: • Joe Griffin is standing by at the airport to close Runway 8-26 upon the arrival of West Construction Co crews (ETA 6:00 PM). • West will remove the two cans and concrete located on Runway 8-26 and fill to within 6" of finished grade w/limerock base. • Base will be compacted and 6" cold mix asphalt patch applied and compacted to finished grade +,- %". • Joe Griffin will re -open Runway for operations as soon as he has completed FOD check tonight. • Runway 8-26 will remain open throughout the weekend, barring further problems. • E.S. from KSM will be arriving on site approximately 6:30 PM tonight as QA to insure contractor performance of above initiatives. • West Construction will provide early next week a plan for the permanent repair as soon as practical. • I will be in close contact with all parties affected to insure adequacy of permanent repairs. Regards, heloll WARNING: All e-mail sent to or from The LPA Group corporate e-mail system is subject to archiving, monitoring and/or review by LPA personnel. This message is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged, confidential or otherwise legally exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all copies of this message. 1/2/2010 Page 1 of 2 Joseph Griffin From: Burton, Arthur H. [AHBurton@lpagroup.com] Sent: Thursday, December 31, 2009 3:52 PM To: Christopher Caprio Cc: Hambrecht, Rob; Joseph Griffin; Robert Binford; frank Subject: RE: Sebastian Rny 4-22/flush mounted runway edge lights in intersection Chris: I will forward the QA test results to you as soon as I receive them. Your immediate remediation plan is approved and the necessary co-ordination with the Airport Manager, Joe Griffin, is underway to close the runway for tonight's work. Thank you for your timely response and co-operation in this serious matter. Regards, Henri From: Christopher Caprio[mailto:CCaprio@westconstructioninc.net] Sent: Thursday, December 31, 2009 3:41 PM To: Burton, Arthur H. Cc: Hambrecht, Rob; Joseph Griffin; Robert Binford; frank Subject: RE: Sebastian Rny 4-22/flush mounted runway edge lights in intersection Henry This email is in response to your correspondence below. We have been in communication today to resolve this issue with your firm LPA and also with H.L. Pruitt our subcontractor responsible for the concrete and detail for the area in question since we were notified by your firm. The resolution for the correction is as follows: H.L.Pruitt will install rock base material compacted and finish with 6" of compacted cold patch asphalt. This remedial work Will take place tonight and the crew is mobilizing as we correspond. The replacement measures will be scheduled early next week And we will be contacting the approved mix bag material supplier for the investigation as to why the material did not perform as per manufacturer product data, then we can evaluate if this material is to be used for the finish product or an alternate mix be recommended. Please provide a report from your inspector and testing QC firm that was onsite when this pour took place, I will Need this information for our evaluation on the material, since he was present and advising also on the application. I greatly appreciate your cooperation to resolve this issue and completing this project successfully. Respectfully From: Burton, Arthur H. [mailto:AHBurton@lpagroup.com] Sent: Thursday, December 31, 2009 3:26 PM To: Christopher Caprio Cc: Hambrecht, Rob; Joseph Griffin Subject: Sebastian Rny 4-22/flush mounted runway edge lights in intersection Chris: 1/2/2010 Page 2 of 2 This email is in reference to your concrete pour of Wednesday, December 30, 2009, at 8:00 P.M. at the Sebastian Municipal Airport. As you know, the requirement for the concrete around the runway edge lights (Rnwy 4-22) crossing the open runway (Rnwy 8-26) was that it must reach a compressive strength of 2500 psi in 5 hours to allow safe operation of the active runway. As of 12:00 P.M. today (16 hours after the pour), the sample concrete cylinders have yielded very low compressive strengths with the highest break being 1090 psi. This is far below the strength necessary to safely support the wheel loading of the heaviest aircraft currently based at Sebastian. In addition, not knowing the type itinerant aircraft that may use the airport this weekend, we have recommended to the Airport Manager that Runway 8-26 be closed until such time as sufficient compressive strength can be demonstrated or a remedial action is performed. Closing Runway 8-26 will result in the closing of the entire airfield. You may anticipate that the airport will seek to recover lost revenues due to this unexpected closure. Please bear in mind that as a consequence of the failure of the concrete to meet the required structural strength, cracking, shifting, and spalling may produce depressions and/or FOD on the runway and should be monitored closely. I request at this time that you send us a plan for correction of this deficiency as soon as possible. Regards, /eoi i-A001415n Henri Burton Construction Manager The LPA Group, Inc. 1320 Executive Center Dr., STE 100, Atkins Bldg. Tallahassee, FL 32301 Office: (850) 205-0460 Fax: (850) 205-0461 WARNING: All e-mail sent to or from The LPA Group corporate e-mail system is subject to archiving, monitoring and/or review by LPA personnel. This message is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged, confidential or otherwise legally exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all copies of this message. WARNING: All e-mail sent to or from The LPA Group corporate e-mail system is subject to archiving, monitoring and/or review by LPA personnel. This message is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged, confidential or otherwise legally exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all copies of this message. 1/2/2010 Page 1 of 1 Joseph Griffin From: Christopher Caprio[CCaprio@westconstructioninc.net] Sent: Monday, January 04, 2010 11:39 AM To: Burton, Arthur H.; Hambrecht, Rob; Joseph Griffin Subject: FW: initial findings for calcs/headings FYI From: L Delisa [mailto:ldelisa@gssfla.com] Sent: Monday, January 04, 201011:15 AM To: Christopher Caprio Cc: 'Joshua Drum' Subject: Good Morning Chris, The talcs are done and based upon the onsite airports compass rows, the new headings are as follows: Existing Runway 4-22 will become 5-23 Existing Runway 8-26 will become 9-27. Geodetic Survey Services, Inc. Leslie De Lisa (329) 724-6659 x22 (321) 984-1277 fax Idelisa@gssfla.com 1/4/2010 Page 1 of 2 Joseph Griffin From: Hambrecht, Rob [RHambrecht@lpagroup.com] Sent: Monday, January 04, 2010 12:57 PM To: Christopher Caprio; Burton, Arthur H.; Joseph Griffin Subject: RE: initial findings for talcs/headings Ok, thanks. See you then. From: Christopher Caprio [mailto:CCaprio@westconstructioninc.net] Sent: Monday, January 04, 2010 12:56 PM To: Hambrecht, Rob; Burton, Arthur H.; Joseph Griffin Subject: RE: initial findings for calcs/headings Thursday 2pm at Joe's office. Surveyor will be present. From: Hambrecht, Rob[mailto:RHambrecht@lpagroup.com] Sent: Monday, January 04, 2010 11:53 AM To: Christopher Caprio; Burton, Arthur H.; Joseph Griffin Subject: RE: initial findings for calcs/headings Chris, Can you setup a meeting for this project to discuss the outstanding issues. Also please make sure the surveyor can be at the meeting? Wednesday, Thursday or Friday works for me. Joe, what day/ time works best for you? I'm thinking the sooner the better. Thanks Rob From: Christopher Caprio [mailto:CCaprio@westconstructioninc.net] Sent: Monday, January 04, 2010 11:39 AM To: Burton, Arthur H.; Hambrecht, Rob; Joseph Griffin Subject: FW: initial findings for calcs/headings FYI From: L Delisa [mailto:ldelisa@gssfla.com] Sent: Monday, January 04, 2010 11:15 AM To: Christopher Caprio Cc: 'Joshua Drum' Subject: Good Morning Chris, The calcs are done and based upon the onsite airports compass rows, the new headings are as follows: Existing Runway 4-22 will become 5-23 Existing Runway 8-26 will become 9-27. 1/4/2010 Page 2 of 2 1f .d= Geodetic Survey Services, Inc. Leslie De Lisa (321) 724-6659 x22 (329) 984-1277 fax ldelisa�7a,gssfla. com WARNING: All e-mail sent to or from The LPA Group corporate e-mail system is subject to archiving, monitoring and/or review by LPA personnel. This message is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged, confidential or otherwise legally exempt from disclosure. if you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all copies of this message. WARNING: All e-mail sent to or from The LPA Group corporate e-mail system is subject to archiving, monitoring and/or review by LPA personnel. This message is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged, confidential or otherwise legally exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all copies of this message. 1/4/2010 Page 1 of 2 Joseph Griffin From: Christopher Caprio[CCapdo@westconstructioninc.net] Sent: Monday, January 04, 201012:56 PM To: Hambrecht, Rob; Burton, Arthur H.; Joseph Griffin Subject: RE: initial findings for calcs/headings Thursday 2pm at Joe's office. Surveyor will be present. From: Hambrecht, Rob[mailto:RHambrecht@lpagroup.com] Sent: Monday, January 04, 2010 11:53 AM To: Christopher Caprio; Burton, Arthur H.; Joseph Griffin Subject: RE: initial findings for calcs/headings Ch ris, Can you setup a meeting for this project to discuss the outstanding issues. Also please make sure the surveyor can be at the meeting? Wednesday, Thursday or Friday works for me. Joe, what day/ time works best for you? I'm thinking the sooner the better. Thanks Rob From: Christopher Caprio [mailto:CCaprio@westconstructioninc.net] Sent: Monday, January 04, 2010 11:39 AM To: Burton, Arthur H.; Hambrecht, Rob; Joseph Griffin Subject: FW: initial findings for calcs/headings FYI From: L Delisa [mailto:ldelisa@gssfla.com] Sent: Monday, January 04, 2010 11:15 AM To: Christopher Caprio Cc: 'Joshua Drum' Subject: Good Morning Chris, The calcs are done and based upon the onsite airports compass rows, the new headings are as follows: Existing Runway 4-22 will become 5-23 Existing Runway 8-26 will become 9-27. u 'Tr Y Geodetic Survey Services, Inc. Leslie De Lisa (321) 724-6659 x22 (321) 984-1277 fax ldelisa@zs.yfla.com 1/4/2010