C H E S S E R' S G A P
PRELIMINARY PLAN FOR
A COMMERCIAL PLANNED
UNIT DEVELOPMENT
FOR
SEBASTIAN GENERAL PARTNERSHIP B.F.T.
PREPARED BY:
MOSBY & ASSOCIATES, INC.
1507 - 20TH STREET
VERO BEACH, FLORIDA 32960
August 1990
SECTION 20A-4.13 PRELIMINARY DEVELOPMENT PLAN
r_nrnmTnM
The proposed Chesser's Gap Commercial Planned Unit Development
is located on a tract of land lying approximately 3.5 miles west
of U.S. #1 and the Florida East Coast Railroad on the south side
of C.R. 512. The site comprises 58.09 acres.
PRESENT USE
The project site is presently used for agriculture. Land surrounding
the proposed development is generally undeveloped residential land,
except the land abutting the north property line which is undeveloped
commercial.
PLANNING OBJECTIVES
It is the intent of the Sebastian General Partnership to create
a Planned Unit Development containing Commercial, Professional
and Light Industrial uses blended together in an aesthetically
pleasing format. All buildings will be designed and constructed
of the finest materials to compliment the overall project. The
entrance and overall site will be landscaped and maintained to
present a clean and beautiful experience for the public visiting
the project. Specific facilities will include a supermarket, a
general merchandise department store, an assortment of specialized
retail shops, office complexes and high-tech light industrial units.
Efforts are presently being made to include an Elks Lodge and a
County Municipal facility. If these efforts fail, then these lands
will be used as commercial.
It is the overall belief of the developers that the proposed project
will fulfill the need for a centrally located shopping facilities
for the public.
QUANTITATIVE DATA
Lot 1 Organization (Elk's Lodge)
Total Area = 2.87 Acres
Building Area = 10,880 S.F. = 8.7%
Impervious Area = 50,814 S.F. = 40.60
Open Space = 74,206 S.F. = 59.4%
-1-
QUA14TITATIVE DATA (continued)
Lot 2
Professional Office
Total Area
= 3.51
Building Area
= 22,500
S.F. =
14.7%
Impervious Area
= 86,880
S.F.
= 56.8%
Open Space
= 66,015
S.F. =
43.1%
Lot 3
Professional Office
Total Area
= 4.44 Acres
Building Area
= 30,000
S.F. =
15.5%
Impervious Area
= 96,410
S.F. =
49.8%
Open Space
= 96,995
S.F. =
50.0%
Lot 4
Light 1ndustr:ial
Total Area
= 17.10 Acres
Building Area
= 77,000
S.F. =
10.4%
Impervious Area
= 346,595
S.F.
= 46.5%
Open Space
= 398,280
S.F.
= 53.4%
Lot 5
Professional Office
Total Area
= 4.36 Acres
Building Area
= 25,600
S.F.
= 13.5%
Impervious Area
= 77,546
S.F.
= 40.8%
Open Space
= 112,374
S.F.
= 59.2%
Lot 6
Commercial/Retail
Total Area
= 12.39 Acres
Building Area
= 102,000
S.F.
= 18.2%
Impervious Area
= 411,070
S.F.
= 73.2%
Open Space
= 150,420
S.F.
= 26.7%
Lot 7
Commercial/Retail
Total Area
= 5.63 Acres
Building Area
= 37,400
S.F.
= 15.2%
Impervious Area
= 176,156
S.F.
= 71.8%
Open Space
= 69,089
S.F.
= 28.2%
Tract A Commercial
Total Area = 1.53 Acres
Building Area = 26,650 S.F. = 40.0%
Impervious Area = 53,320 S.F. = 80.0%
Open Space = 13,330 S.F. = 20.0%
-2-
QUANTITATIVE DATA (continued)
Tract B Commercial
Total Area
Building Area
Impervious Area
Open Area
Tract C Commercial
1.24 Acres
21,600 S.F. = 40.0%
43,210 S.F. = 80.0%
10,803 S.F. = 20.0%
Total Area = 0.82 Acres
Building Area = 14,280 S.F. = 40.0%
Impervious Area = 28,570 S.F. = 80.0%
Open Area = 7,144 S.F. = 20.0%
Fleming Street Extension
Total Area
Impervious Area
Open Area
= 3.68 Acres
= 1.12 Acres
= 2.56 Acres
TOTAL SITE SUMMARY
Total Site Area
= 58.09
Acres
Total Site Area Less Fleming Street
Extension
= 54.41
Acres
Gross Site (Floor to Area Ratio)FAR
= 0.15
Acres
Net Site (Floor to Area Ratio) FAR
= 0.16
Acres
Total Building Area
= 8.44
Acres
Total Open Space
= 22.89
Acres
Total Impervious Area
= 35.20
Acres
Maximum Building Height
= 35
Feet
Gross Residential Density
= 0
DEVELOPMENT SCHEDULE
Development is expected to begin in January 1991, and be completed
in 1996. The project will be constructed in three (3) phases,
which will be a continuing, evolving process of cooperation between
the City of Sebastian and the Sebastian General Partnership B.F.T.
The project will be broken down as follows:
-3-
Phase I January 1991 to January 1992
This phase will be the construction of the proposed Fleming Street
Thoroughfare Extension. In addition, this phase may include the
development of the proposed supermarket and some retail shops.
The landscaping, overall drainage system, utilities and traffic
improvements will be completed during this phase.
Phase II January 1991 to June 1994
This phase includes the development of a portion of the proposed
Professional Office/ Commercial area as well as a portion of Light
Industrial area.
Phase III June 1994 to January 1996
This phase will include the development of the remaining Professional
Office/Commercial and Light Industrial areas.
ENVIRONMENTAL IMPACT STATEMENT
No wetland areas exist on the project site.
Lakes are to be utilized for stormwater retention. These lakes
will be interconnected and protected against direct discharge of
surface runoff by utilizing natural drainage concepts. Approximately
fourty percent (400) of the gross site is to be used as grassed
areas for runoff. These stormwater managerial practices will have
a beneficial impact on the water resources in the area, including
the opportunity for groundwater recharge.
Landscape buffers will be established to provide both noise and
sight buffers. Mounds of earth with tree and shrub plantings will
be utilized. The existing vegetation along the east, west and
south property lines will be maintained as much as practicable.
Whenever possible, existing trees within the project will be main-
tained.
PRELIMINARY DRAINAGE PLAN
The drainage system presently consists of a roadside ditch along
C.R. 512, and a major drainage ditch along the west property line.
The ditch along C.R. 512 discharges into other collector ditches
which discharge ultimately into the Indian River. The existing
topography of the land is such that nearly all of the rainfall
results in ponding and eventually runoff into the adjacent ditches.
The detention time is minimal, thereby reducing the advantage of
recharge of the surficial aquifer.
-4-
PRELIMINARY DRAINAGE PLAN (continued)
The proposed drainage system consists of a complex network of
centralized lakes, swales and underground pipes. Best managerial
practices include grassed swales, berms around lakes and establish-
ment of littoral zone vegetation.
The design of the stormwater management system will be such that
the runoff from a twenty-five (25) year storm will be retained
on-site with provisions for an overflow, thus providing a detention
time that will allow the collected stormwater to be used to recharge
the surficial aquifer and to make provisions for use of the storm -
water for non -potable irrigation water, if desired.
PUBLIC FACILITY IMPACT STATEMENT
A. Wastewater Generation
The wastewater system for Chesser's Gap is to be tied in to
the North County Wastewater System which is presently under
construction. Indian River County has already installed at
the project's north west corner of the property.
The following is the estimated quantity of wastewater generation:
Retail 175,400 ft2 Total Bldg. Area x 0.1 GPD/ft2 =
17,540 GPD
Professional Office 105,100 ft2 Total Bldg. Area x 0.2 GPD/ft2 =
21,020 GPD
Light Industrial 77,000 ft2 Total Bldg. Area x 0.2 GPD/ft2 =
15,400 GPD
Organizational 10,800 ft2 Total Bldg. Area x 0.3 GPD/ft2 =
3,240 GPD
Total Estimated Wastewater
= 57,200 GPD
As you can see from the above calculation, the estimated waste-
water flow is based on square footage of the buildings which
is a conservative approach to the calculation of the waste-
water flows.
B. Water Required
The planned potable water source for this project is from General
Development Utilities. The amount of potable water required
is estimated at 57,200 GPD.
It should be noted that the above estimated potable water re-
quired does not include water for irrigation nor building fire
systems. It is intended to use non -potable water for these
purposes.
-5-
C. Recreation Facilities
The Green Areas around the professional office area adjacent
to the lakes will be equipped with facilities such as benches
and tables for the employees of these buildings.
D. Estimated Number of School Age Children
There are no developmental units planned for the project, there-
fore, no generation of school age children.
E. Estimated Property Taxes .
The estimated property taxes are as follows:
Phase I A moderate increase to the tax revenue is
expected to result from Phase I. No sales
tax revenue is expected from Phase I.
Phase II A significant tax revenue increase is ex-
pected as a result of Phase II. Taxable
values are expected to exceed $10,000,000.00
and bring in tax revenue in excess of
$1,000,000.00. Sales tax revenue is ex-
pected to top $500,000.00.
Phase III This phase will see the completion of the
project with total taxable values exceeding
$30,000,000.00 with tax revenues above
$10,000,000.00 and sales taxes over
$16,000,000.00.
TRAFFIC INFORMATION
A detailed traffic impact analysis was performed by Motorist Design
Data Movement, Inc. of Merritt Island. It is recommended that
a traffic signal at the C.R. 512 and Fleming Street intersection
be installed. Also that an east bound deceleration lane for right
hand turns into the project, a west bound left turn lane into the
project and a dual exit lane be constructed.
A copy of the report has been submitted to the City.
SUMMARY
One positive impact that the proposed project will have is that
it will provide centralization of commercial, professional and
light industrial services for citizens of Sebastian.
The project will be developed in such a fashion that the City leaders
and citizens will be proud to have such a development within their
City.