HomeMy WebLinkAbout1992 Charles Ankrom Forecast!9-11 ourde, rcklech, Conjullunl3 &Pianner9
CHARLES F. ANKROM INC.
June 4, 1992
TO: CITY OF SEBASTIAN
SEBASTIAN, FLORIDA
FROM: CHARLES F. ANKROM,
GOLF COURSE ARCHITECT AND CONSULTANT
ATTN: MR. JIM DELARME, MANAGER
SEBASTIAN MUNICIPAL GOLF COURSE
AND:
GOVERNING OFFICIALS, CITY OF SEBASTIAN.
Enclosed is our projections for construction cost to expand the
existing 18 hole golf course to 36 holes or 27 holes. Documented
and detailed projections are included for a new 18 hole course,
and/or a new 9 hole course addition.
The average cost projections forecast to develop an 18 hole
regulation golf course with multiple tees is $2,899,600.
The average cost projections forecast to develop a 9 hole
regulation golf course with multiple tees is $1,568,800. This is
about 54% of the cost of an 18 hole course (expect a range of 53%
to 55%).
The cost projections establish a value to budget for 1992-1993
dollars, with a modest contingency.
The analysis of total cost is divided into three sections:
Section A: The typical estimated cost for actual site
construction by a qualified golf course contractor.
Section B: All items of site engineering, permitting,
topographic maps, environmental issues, and site
structures.
Section C: Professional fees and the Owner's grow -in phase to
prepare the course for opening.
These cost projections exclude items such as:
1. Clubhouse expansion.
2. Parking lot expansion.
3. Maintenance shop expansion.
4. Additional maintenance equipment.
5.'' Soft cost such as advertising and promotion, new scorecards,
signage, and other professional services (structural
architect, legal, consultants, bonding cost, etc).
P.O. BOX 898 STUART, PL. 34095-0898 • (407) 283-1440 9 MEMBER: A.S.G.C.A.
n
Typical comparable cost of recent public golf course
developments, or forecast for new projects in planning.
A) From P.G.A. consultants files, assuming typical identical
cost categories.
1. Palm Beach Gardens Municipal (18 holes, recently opened):
+ $3,302,232.
2. Sandridge Municipal Golf Course projections (18 holes,
recently started construction): + $2,892,602.
3. Palm Beach County, Okeeheelee Park (27 holes, to be
constructed):
+ $4,145,380, plus the fees of the Golf Course Architect,
Civil Engineering, Environmental Consultants, and soil
testing (at 8%, this would equal $331,630).
Note: These cost may not include other soft cost such as
topographic and aerial maps.
B) From our files and estimates we have:
1. The Habitat, Brevard County (18 holes, opened October
1991): This was a $4,300,000 bond issue. About $2,500,000
was spent on identical categories.
2. The new Cocoa Beach Municipal Golf Course Facilities was
constructed with a budget of $4,382,642. Of this amount,
approximately $2,554,000 was spent on the golf course,
plus some irrigation equipment cost from another budget.
The improvements to the golf course included 18 new golf
holes, plus the retaining of one existing nine of the
original golf course for a total 27 hole facility.
John Rossi of the PGA Golf Services is preparing a feasibility
study which includes other cost necessary to complete your golf
course expansion program. Please contact my office should there
be any questions on this report, and the construction cost
estimates provided.
Very Truly Yours,
Charles F. Ankrom
President
PROJECTIONS:
18 ROLE GOLF COURSE EXPANSION PROGRAM
"SEBASTIAN MUNICIPAL GOLF COURSE"
COST PROJECTIONS AND ESTIMATES FOR EXPANSION
18 HOLE ADDITION: REGULATION LENGTH COURSE
GOLF COURSE CONSTRUCTION COST ANALYSIS
Section A: 18 Hole Golf Course Construction
Cost Projection, Category Analysis
TtPm No_
Description
1. Mobilization: The estimated cost
for contractors to mobilize staff,
operators, supervisors, construction
equipment, and field construction
trailers.
2. Site Staking: Additional field
staking to isolate clearing control
dimensions, and additional stakes
to establish key features positions
All measurements establish from
centerline survey control line.
3. Clearing: The cost projections to
clear the site of all features,
lakes, and including the clubhouse
& maintenance shop sites. Clearing
analysis projected at $500 to $700
per acre light clearing of ground
vegetation, $700 to $900 per acre
moderate growth, and $1,000 to
$1,700 for areas of dense trees.
4. Topsoil Stockpile: This phase is
to strip and temporarily stockpile
quality topsoils from lake and
surface excavation cuts. To be re-
used after grading of artwork
features. Quantities can vary from
50,000 to 60,000 cu. yds. at
$.90 to $1.15 per cu. yd.
Projected
Range of Cost Average Cost
$151000-$30,000 $22,500
71500-12,000 91500
952000-1352000 115,000
452000-69,000 55,000
Item No.
Description
Projected
Range of Cost Average Cost
5.
Construction Earthwork: The
371,200-562,500 466,800
heavy equipment excavation of earth-
work and artwork shaping soils from
all new designed lakes, swales,
and environmental wetland features,
or any sub -grade cuts. A range of
275,000 to 375,000 cu. yds. is
projected to develop the tees,
greens, mounds and playing features
of the course. Soils will also be
developed to elevate fairways in
low areas, or sections of the course
with high water tables. Cost may
range from $1.35 to $1.50 per cu. yd.
Cost to include pre -rough grade
shaping.
6.
Artwork Shaping: The cost for art-
957000-1252000 1102000
wort shaping of all tees, greens and
fairway earthwork features by skilled
and experienced operators using
dozers and specialty equipment.
7.
Greens Construction Specifications:
270,000-378,000 3242000
To include superior U.S.G.A. type
blended topsoils, and with a minimum
sub -base of tile & gravel lines, to
full U.S.G.A. sub -base specifications.
This category may have a range of
cost options, and varies with the
size of greens. Assume 6,000 sq. ft.
greens average.
8.
"Surface" Drainage Features: To
202000-35,000 279500
include the use of hig impact
plastic catch basins, polyethylene
drainage pipe, and tile & gravel
turf drains. Necessary to drain all
sand traps, grassy pockets or design
depressions, and potential wet areas
of the course.
9.
Interior Culvert Pi e:An allowance
35,000-50,000 42,500
for lake interconnecting culverts,
culvert cart/equipment crossings,
and all interior major drainage
equipment or features, including
endwalls, and all outfall control
structures.
rIMN
Item No. Description
10. Topsoiling of Features: Using top-
soils previously stockpiled, and
other developed topsoils, to plate
all mounds, green slopes, tees and
any area needing topsoils for turf -
grass development. A cost range of
1.00 to 1.25 per cu. yd.,
including hauling and spreading.
11. Soil Amendments: An allowance for
the purchase o peat and silica sand
to improve teeing surfaces. The cost
to include purchases, application,
and blending. Note: greens topsoils
amendment included in green
specifications.
12. Irri ation System: The install-
ation of a fully automatic
irrigation system and turbine pump
station. A computer operated system
may run from $25,000 to $60,000
1"1) additional cost.
Range of Cost
502000-752000
102000-202000
Projected
Average Cost
62,500
15,000
500,000-625,000 5632000
13.
Final Surface Grading & Floating:
352000-502000 402000
The use of tractor, floats, small
equipment, and hand labor to smooth
and level all areas in preparation
for grassing.
14.
Fume ation: The fumigation and
72500-102200 82800
stere ization of greens putting
surfaces using Methyl Bromide. This
eliminates any weed seeds, soil
insects, and nematodes.
15.
Grassing and Sodding: The planting
95,000-1102000 1022000
o Ti dwar Bermuda on greens,
"Tifway 419" on all tees, fairways
and irrigation rough, and possibly
Argentine Bahiagrass in "off" areas
of rough. Include sod around all
trap edges and key areas subject
to erosions.
16.
Pre -Plant Fertilizer & Lime:
142000-202000 172000
The cost to apply a quality pre -
plant (before grassing) fertilizer,
and Dolomite Lime to increase low
PH soils. This is a requirement to
provide immediate nutrients to new
roots of all sprigs & seedlings.
Projected
Item No. Description
Range of Cost Average Cost
17.
Treescape: An initial allowance to add
109000-20,000 159000
tree plantings in areas or locations
where native forest trees are lack-
ing. To recommend the use of native
species for low maintenance and a
more natural site aesthetic appear-
ance.
18.
Special Features: This category to
15,000-35,000 252000
include all tim er bulkhead retaining
walls, timber bridges, any rock
walls, or special features. Note:
this category cannot be accurately
forecast without a Design Master Plan.
19.
Golf Cart Paths: All sites require
110,000-145,000 127,500
the installation of golf cart paths.
Both asphalt and concrete are used.
Current prices are more favorable
for concrete, which also lasts
longer and has less maintenance.
101
Assume a minimum of routing from
green through the next tee, full
length on Par 3's, and circulation
to the clubhouse site. Assume partial
length for budgets. (not full length.)
20.
Construction Contingency, Section A:
1002000-150,000 125,000
An allowance to cover any unknown
site construction or miscellaneous
items, and cost increases not forecast.
21.
Environmental Issues: The cost of any
10,000-189000 14,000
required environmental plantings or
berms, or new wetland development
criteria. Note: Accurate cost for
this item cannot be projected until
the actual design and permitting
process.
TOTAL
COST SECTION A:
Total
projected average cost:
$2,287,600
ENO
Section B: Engineering, Architectural and
Requirements, Topographic Maps,
and Outfalls Structures.
Item No. Description
1. Road Improvements: To include entry
road cost, and required improvements
to public roads.
2. Utilities: The projected cost
to eve'op underground electric
to the pump station, and misc. cost.
3. On-site Restrooms and Shelters:
Normally 3 to 4 shelters are
required, with up to 2 combination
shelter/restrooms. Assume 2
shelter/restrooms at $18,000 ea.
and one shelter at $12,000 ea.,
plus $4,000 Architects fee.
Environmental Cost Items, Survey
Major Drainage Criteria
4. Site Survey: The cost to survey and
to site stake all property lines;
property line corners; golf course
fairway centerlines; tee, green and
fairway target points; top of new
lake banks and any initial golf course
features requiring site survey.
5. Permitting Requirements: A
projected category to include the
processing of both engineering and
environmental construction permits
through local and county government,
Corps of Engineers, S. Florida Water
Management, and additional government
agencies typical to D.E.R., D.N.R.,
and Fish & Wildlife.
6. Soil Borings & Soil Test: To
inc ude p ysica an c emical test
of available site topsoils, and
any sand sub -soils. To include
test borings up to +20' for cut
areas of lakes to determine soil
layers to be excavated and used for
building of the golf course features.
Range of Cost
(Not Projected)
72500-12,000
+52,000
122000-152000
102000-202000
21000-42000
Projected
Average Cost
10,000
52,000
13,500
15,000
3,000
Projected
Item No. Description Range of Cost Average Cost
7. Topographic Maps: Each site requires
an accurate topographic map to one
foot contours, and fractions on high and
low points, to use for design of the
golf course, roads & facilities, and
to use for permitting purposes. The
cost shall be determined by the size
of the project. Assume aerial
topographic mapping and some ground
shots.
8. Irri ation Wells or Water Resources:
Each site requires research
evaluations to determine the sources
of irrigation water. Normally recharge
wells are required. The size of the
irrigation lake, and natural ground
water recharge, will also impact
recharge demand.
..X TAL COST SECTION B:
Total projected average cost:
182000-25,000
212000-30,000
21,500
25,500
$140,500
oECTION C: Professional Fees and Expenses, Owners Grown -in Phase:
Item No. Description
1. Golf Course Architect: The
projection to retain a highly
qualified Golf Course Architect,
a member of the "American Society
of Golf Course Architects", to
develop the site "Master Plan",
and to prepare the necessary
construction plans and
specifications. The Architect
should have experience in Florida
Public Golf Course development,
soils and turfgrasses. The fees
should also include site
inspections during construction.
2. Professional Engineer: To retain
a protessional civil engineer to
develop all site engineering plans,.
drainage criteria of storm water
management, ground water & water
resources, culverts, outfall
structures, roads & paths, the
clubhouse site plan and parking
lot, lighting requirements,
maintenance shop site plan, all
utilities, and for processing all
plans for permitting through required
governmental agencies.
3. Environmental Consultant: To retain
a professional environmental
scientist and planner for site
ecology and environmental studies,
to include both plant and animal
life, for all environmental designs
and bidding (i.e.: wetland litteral
zones, animal habitats, etc.),
construction installation, to
process all required environmental
plans, specifications, and reports
through required governmental
agencies, and to serve as a
consultant to the Owner, Architects
and Engineers.
Projected
Range of Cost Average Cost
159,000-2007000 1692000
18,000-252000
7,500-121000
22,000
10,000
Item No. Description
4. Landscape Architect: The services
o a landscape architect will be
required for design of the landscape
and tree plantings around the club-
house site and parking lot,
maintenance site (if required), for
entry treatment and signage, any
landscape lighting, all landscape
irrigation requirements, and for
any treescape/landscape design on
the golf course (roughs and off -
areas). To also process all
required plans through local
government permitting agencies.
5. Clubhouse & Structure Architect:
Not included in this report. Any
cost of this category will need to
be added.)
6. Professional Expenses: To include
the cost of printing of
specifications, documents & blue-
prints, mylars, sepias, photo
reproduction, travel, L.D. calls
& FAX, any separate lab cost,
expenses to process all permits,
and any direct reimbursable
expenses of the job.
7. Grow -in Phase: This phase of work,
and all cost, are to be performed by
the Owner's Golf Course Maintenance
Superintendent and crew. To include
all watering practices to mature the
hybrid bermuda sprigs, sod and seed,
fertilization, chemicals to control
pests and weeds, top -dressings of
greens, tees, ruts and washouts, all
mowing practices, supervision, labor
utilities, repairs, purchase and
installation of trap sand, and any
item required to mature the turf for
play and opening of the course,
including site equipment such as flag
poles, ball washers, signage, etc.
DOTAL COST SECTION C:
Total projected average cost:
Range of Cost
(Excluded)
Projected
Average Cost
(Excluded, except for shelters
41000-7,000 52500
2401000-290,000 265,000
$471,500
PROJECTIONS:
9 HOLE GOLF COURSE EXPANSION PROGRAM
"SEBASTIAN MUNICIPAL GOLF COURSE"
COST PROJECTIONS AND ESTIMATES FOR EXPANSION
9 HOLE ADDITION: REGULATION LENGTH COURSE
GOLF COURSE CONSTRUCTION COST ANALYSIS
Section A: 9 Hole Golf Course Construction
Cost Projection, Category Analysis
Item No. Description
1. Mobilization: The estimated cost
for contractors to mobilize staff,
operators, supervisors, construction
equipment, and field construction
trailers.
2. Site Staking: Additional field
staking to isolate clearing control
dimensions, and additional stakes
to establish key features positions
All measurements establish from
centerline survey control line.
3. Clear in : The cost projections to
clear t e site of all features,
lakes, and including the clubhouse
& maintenance shop sites. Clearing
analysis projected at $500 to $700
per acre light clearing of ground
vegetation, $700 to $900 per acre
moderate growth, and $1,000 to
$1,700 for areas of dense trees.
4. Topsoil Stockpile: This phase is
to strip and temporarily stockpile
quality topsoils from lake and
surface excavation cuts. To be re-
used after grading of artwork
features. Quantities can vary from
25,000 to 30,000 cu. yds. at
$.90 to $1.15 per cu. yd.
Projected
Range of Cost Average Cost
$152000-$202000 $17,500
52000-82000
502000-65,000
22,500-342500
6,500
57,500
27,500
Item No. Description
5. Construction Earthwork: The
heavy equipment excavation of earth-
work and artwork shaping soils from
all new designed lakes, swales,
and environmental wetland features,
or any sub -grade cuts. A range of
148,000 to 178,000 cu. yds. is
projected to develop the tees,
greens, mounds and playing features
of the course. Soils will also be
developed to elevate fairways in
low areas, or sections of the course
with high water tables. Cost may
range from $1.35 to $1.50 per cu. yd.
Cost to include pre -rough grade
shaping.
Projected
Range of Cost Average Cost
200,000-2662800 2332400
6. Artwork Sha in The cost for art- 50,000-65,000 57,250
work s aping o all tees, greens and
fairway earthwork features by skilled
and experienced operators using
,,MkN dozers and specialty equipment.
7. Greens Construction Specifications:
To include superior U.S.G.A. type
blended topsoils, and with a minimum
sub -base of tile & gravel lines, to
full U.S.G.A. sub -base specifications.
This category may have a range of
cost options, and varies with the
size of greens. Assume 6,000 sq. ft.
greens average.
8. "Surface" Drainage Features: To
include the use ot high impact
plastic catch basins, polyethylene
drainage pipe, and tile & gravel
turf drains. Necessary to drain all
sand traps, grassy pockets or design
depressions, and potential wet areas
of the course.
9. Interior Culvert Pipe:An allowance
for lake interconnecting culverts,
culvert cart/equipment crossings,
and all interior major drainage
equipment or features, including
endwalls, and all outfall control
structures.
135,000-189,000 1622000
121000-172400
202000-25,000
14,700
22,500
Projected
Item No. Description Range of Cost Average Cost
10.
Topsoiling of Features: Using top-
25,000-37,500 31,250
soils previously stockpiled, and
other developed topsoils, to plate
all mounds, green slopes, tees and
any area needing topsoils for turf -
grass development. A cost range of
1.00 to 1.25 per cu. yd.,
including hauling and spreading.
11.
Soil Amendments: An allowance for
62000-92000 71500
t e purchase of peat and silica sand
to improve teeing surfaces. The cost
to include purchases, application,
and blending. Note: greens topsoils
amendment included in green
specifications.
12.
Irrigation System: The install-
2552000-335,000 295,000
ation of a fully automatic
irrigation system and turbine pump
station. A computer operated system
may run from $20,000 to $40,000
additional cost.
13.
Final Surface Grading & Floating:
20,000-252000 222500
The use o tractor, floats, small
equipment, and hand labor to smooth
and level all areas in preparation
for grassing.
14.
Fumi ation: The fumigation and
4,000-42800 41400
stern ization of greens putting
surfaces using Methyl Bromide. This
eliminates any weed seeds, soil
insects, and nematodes.
15.
Grassing and Sodding: The planting
50,000-60,000 55,000
oT_`Titdwar7 Bermuda on greens,
"Tifway 419" on all tees, fairways
and irrigation rough, and possibly
Argentine Bahiagrass in "off" areas
of rough. Include sod around all
trap edges and key areas subject
to erosions.
16.
Pre -Plant Fertilizer & Lime:
72000-10,000 81500
The cost to apply a quality pre -
plant (before grassing) fertilizer,
and Dolomite Lime to increase low
PH soils. This is a requirement to
provide immediate nutrients to new
roots of all sprigs & seedlings.
Item No. Description
Projected
Range of Cost Average Cost
17.
Treescape: An initial allowance to add
51000-10,000 72500
tree plantings in areas or locations
where native forest trees are lack-
ing. To recommend the use of native
species for low maintenance and a
more natural site aesthetic appear-
ance.
18.
Special Features: This category to
15,000-20,000 17,500
include all timber bulkhead retaining
walls, timber bridges, any rock
walls, or special features. Note:
this category cannot be accurately
forecast without a Design Master Plan.
19.
Golf Cart Paths: All sites require
552000-72,600 63,800
the installation of golf cart paths.
Both asphalt and concrete are used.
Current prices are more favorable
for concrete, which also lasts
longer and has less maintenance.
Assume a minimum of routing from
green through the next tee, full
length on Par 3's, and circulation
to the clubhouse site. Assume partial
length for budgets. (not full length.)
20.
Construction Contingency, Section A:
802000-1007000 902000
An allowance to cover any unknown
site construction or miscellaneous
items, and cost increases not forecast.
21.
Environmental Issues: The cost of any
51000-92000 71000
required environmental plantings or
berms, or new wetland development
criteria. Note: Accurate cost for
this item cannot be projected until
the actual design and permitting
process.
TOTAL COST SECTION A:
Total projected average cost: $1,2089800
Section B: Engineering, Architectural and Environmental Cost Items, Survey
Requirements, Topographic Maps, Major Drainage Criteria
and Outfalls Structures.
Projected
Item No. Description Range of Cost Average Cost
GO
1. Road Improvements: To include entry
road cost, and required improvements
to public roads.
2. Utilities: The projected cost
to deve op underground electric
to the pump station, and misc. cost.
3. On-site Restrooms and Shelters:
Normally 2 shelters are
required, with up to 1 combination
shelter/restrooms. Assume 2
shelter/restrooms at $18,000 ea.
and one shelter at $12,000 ea.,
plus $3,500 Architects fee.
4. Site Survey: The cost to survey and
to site stake all property lines;
property line corners; golf course
fairway centerlines; tee, green and
fairway target points; top of new
lake banks and any initial golf course
features requiring site survey.
5. Permitting Requirements: A
projected category to include the
processing of both engineering and
environmental construction permits
through local and county government,
Corps of Engineers, S. Florida Water
Management, and additional government
agencies typical to D.E.R., D.N.R.,
and Fish & Wildlife.
6. Soil Borings & Soil Test: To
include physical and chemical test
of available site topsoils, and
any sand sub -soils. To include
test borings up to +20' for cut
areas of lakes to determine soil
layers to be excavated and used for
building of the golf course features.
(Not Projected)
69000-102000
+33,500
69000-71500
92000-152000
12500-32000
33,500
6,750
12,000
2,250
Item No. Description
7. Topographic Maps: Each site requires
an accurate topographic map to one
foot contours, and fractions on high and
low points, to use for design of the
golf course, roads & facilities, and
to use for permitting purposes. The
cost shall be determined by the size
of the project. Assume aerial
topographic mapping and some ground
shots.
8. Irrigation Wells or Water Resources:
Each site requires research
evaluations to determine the sources
of irrigation water. Normally recharge
wells are required. The size of the
irrigation lake, and natural ground
water recharge, will also impact
recharge demand.
,,,DOTAL COST SECTION B
Total projected average cost:
Range of Cost
122000-18,000
159000-252000
Projected
Average Cost
15,000
20,000
$97,500
.,ECTION C: Professional Fees and Expenses, Owners Grown -in Phase:
Item No. Description
1. Golf Course Architect: The
projection to retain a highly
qualified Golf Course Architect,
a member of the "American Society
of Golf Course Architects", to
develop the site "Master Plan",
and to prepare the necessary
construction plans and
specifications. The Architect
should have experience in Florida
Public Golf Course development,
soils and turfgrasses. The fees
should also include site
inspections during construction.
2. Professional Engineer: To retain
a proYeTs-11-onal civil engineer to
develop all site engineering plans,.
drainage criteria of storm water
management, ground water & water
resources, culverts, outfall
structures, roads & paths, the
clubhouse site plan and parking
lot, lighting requirements,
maintenance shop site plan, all
utilities, and for processing all
plans for permitting through required
governmental agencies.
3. Environmental Consultant: To retain
a professional environmental
scientist and planner for site
ecology and environmental studies,
to include both plant and animal
life, for all environmental designs
and bidding (i.e.: wetland litteral
zones, animal habitats, etc.),
construction installation, to
process all required environmental
plans, specifications, and reports
through required governmental
agencies, and to serve as a
consultant to the Owner, Architects
and Engineers.
Projected
Range of Cost Average Cost
852000-1057000 95,000
112000-202000
67000-102000
15,500
M
Projected
Item No. Description Range of Cost Average Cost
4. Landscape Architect: The services
o a landscape architect will be
required for design of the landscape
and tree plantings around the club-
house site and parking lot,
maintenance site (if required), for
entry treatment and signage, any
landscape lighting, all landscape
irrigation requirements, and for
any treescape/landscape design on
the golf course (roughs and off -
areas). To also process all
required plans through local
government permitting agencies.
5. Clubhouse & Structure Architect:
Not included in this report. Any
cost of this category will need to
be added.)
6. Professional Expenses: To include
/001� the cost of printing of
specifications, documents & blue-
prints, mylars, sepias, photo
reproduction, travel, L.D. calls
& FAX, any separate lab cost,
expenses to process all permits,
and any direct reimbursable
expenses of the job.
7. Grow -in Phase: This phase of work,
and all cost, are to be performed by
the Owner's Golf Course Maintenance
Superintendent and crew. To Inc ude
all watering practices to mature the
hybrid bermuda sprigs, sod and seed,
fertilization, chemicals to control
pests and weeds, top -dressings of
greens, tees, ruts and washouts, all
mowing practices, supervision, labor
utilities, repairs, purchase and
installation of trap sand, and any
item required to mature the turf for
play and opening of the course,
including site equipment such as flag
poles, ball washers, signage, etc.
/"TOTAL COST SECTION C:
(Excluded)
(Excluded, except for shelter:
31000-51000 42000
1302000-1502000 1402000
Total projected average cost: $262,500