HomeMy WebLinkAbout1986 - Installation InfoL. GENE HARRIS Mayor Citti) of Sebastian POST OFFICE BOX 127 ❑ SEBASTIAN, YtORIDA TELEPHONE (305) 589f5330 October 10, 1986 TO: Mayor and City Council FROM: Hector Franco City Engineer As per your request fin attached all the paperwork done in reference to t installation of traffic light at Schumann and U.S. ghway #1. Concerning the mayor's specific question the following are the answers. Hector A. Franco City Engineer 1) FDOT operation center at Fort Lauderdale is still reviewing the project. As of today, Mr. W. Lewis's letter points out that a small change has to be made to the signal design and a permit application is needed. County Traffic Engineer, Michael Orr, will take care of this change. In addition, there will be required changes on turning lanes and a detailed cross section of the Schumann Drive -U.S. High- way #1 intersection. A roadway alteration permit needs to be filled in. The city will take care of that part. 2) All the Engineering is completed for this project except for the above minor changes. 3) So far the only money spent is the county preliminary design cost of $206.71. 4) FDOT at Fort Lauderdale has only two (2) Engineers to review all the projects coming to this district according to the information provided by them. Right now, the project is a little behind schedule. Mr. Michael Orr estimates the completion date to be around June instead of January or February 1987 (see Mr. Orr's letter dated March 13, 1986. He points out past experiences shows him the FDOT is six (6) months behind schedule in most cases. ; Finally under the Departments Equipment Procuremed program for FY86-87 the equipment was ordered from Tallahassee last month. Please call if you have additional questions. cc; Michael Orr L. Gene Harris Mayor City of Sebastian POST OFFICE BOX 127 ❑ SEBASTIAN, FLORIDA 32958-0127 TELEPHONE (305) 589-5330 October 2, 1986 TO: Hector Franco City Engineer FROM: Mayor L. Gene Harris 1 RE: Installation of Traffic Light/Schumann Drive & U.S. #1 Elizabeth H. Reid City Clerk Please provide me with the following information concerning the installation of the traffic light at the intersection of U.S. #1 and Schumann Drive: LGH/jmt What has been completed by D.O.T. up until this point? Is all engineering completed for this project? What amount of money has been spent so far? What is the estimated completion date by D.O.T. for this project? Florida BOB GRAHAM GOVERNOR Department of Transportation THOMAS E DRAWDY SECRETARY 780 Southwest 24 Street Fort Lauderdale, Florida 33315-2696 Telephone: 305-524-8621 Mr. Michael Orr, P.E. Traffic Engineer Indian River County 1840 - 25 Street Vero Beach, Florida 32960 Dear Mr. Orr: Re: Section 88010, Schumann Drive, Traffic Signal October 6, 1986 S.R. 5 (U.S. 1) at Sebastian - 0CT 4� n�N ���i4tT'Y.Y` .7ggs This is in response to your letter of September 5, 1986 with enclosed data. We have reviewed the data submitted by you and stil' maintain that two-phase operation is appropriate. Enclosed, lease find revised signal timing incorporating a two-phase operation. Upon completion of this plan modification, please submit three originally signed permit forms with three copies of the signal plans to Ms. Beth Coe, Florida Department of Transportation District Permit Office for final approval. In response to your questions concerning the proper course of action in obtaining approval for lengthening storage lanes on S.R. 5, we recommend that you contact Ms. Coe at Suncom 421-1310. Sincerely, William A. Lewis r., P.E. Assistant District Traffic Operations Engineer WAL:hg e BOARD OF COUNTY COMMISSIONERS 1840 25th Street, Veru Reach, Florida 32960 Telephone. (7051 507.8000 September 5, 1986 William Lewis, Jr. P.E. Assistant District Traffic Operations Engineer 780 S.W. 24th Street Fort Lauderdale, 33315-2696 Suncom Telephone: 424.1011 Re: Section 88010; State Road 5 at Schumann Drive, City of Sebastian; Traffic Signal Dear Mr. Lewis: Enclosed is a revised plan set for the referenced signal. Pole B and the span have been relocated and the stop bar for the westbound approach moved back to provide forty feet of distance to signal head 8. In addition, traffic counts obtained for both AM and PM peaks with their left -turn analyses are enclosed as jusitification for the State Road 5 left -turn phases. It is my understanding that the equipment for this signal will be requisitioned by your office through the Equipment Procurement Program. Please call if you have any questions. Very truly s, i ichaelL. Orr, Traffic Engineer MLO: rt cc: Hector Franco, City Engineer Floridan Department of Transportation ROR GRAHAM GOVERNOR THOMASE DRAWDY SECRETARY 780 Southwest 24 Street Fort Lauderdale, Florida 33315-2696 Telephone: (305) 524-8621 August 22, 1986 - Mr. Michael L. Orr Traffic Engineer Indian River County 1840 - 25th Street Vero Beach, Florida 32960 Dear Mr. Orr: Re: Section 88010; State Road 5 (U.S. 1) at Schumann Drive, Sebastian, Indian River County - Traffic Signal This is in response to your letter with enclosed signal plans of May 23, 1986. Please forgive our delay in responding. We have reviewed your plans and have two comments, as follows: • Pole A should be moved north in order to develop the minimum 40 feet distance from the east stop bar to signal head 8 & 2. • Traffic volumes on file in this office do not indicate a justification for more than two phases at this intersection. Mr. Toufic Khayat of this office will contact you to confirm your request for signal equipment as soon as this Fiscal Year's money is confirmed. We will provide the necessary authorization for this signal upon receipt of modified plans and the appropriate permit forms. Sincerely, 'l , William Lewis, Jr., .E. Assistant Distric Traffic. Operations Engineer WAL:hf City e f ' Sebastian L. CLINE HARRIS POST OFFICE BOX 127 ❑ SEBASTIAN, FLORIDA 32958-0127 Hector A. Franco Mayor TELEPHONE (305) 589-5330 City Enyineei July 16, 1986 TO- MAYOR HARRIS AND CITY COUNCIL FROM: HECTOR FRANCO CITY ENGINEER RE: TRAFFIC SIGNAL SC6RIMANN DRIVE Please find attached a copy of a letter I received from Michael Orr,,Traffic Engineer, Indian River County in answer to my request for an update on this project. As you can see the plans are in the hands of the FDOT now and that is the hold up. Should you have any further questions, please feel free to contact me. 4 BOARD OF COUNTY COMMISSIONERS 1840 25th Street, Vero Beach, Florida 32960 Telephone: (305) 557-8000 July 15, 1986 Hector Franco City Engineer City of Sebastian P.O. Box 127 Sebastian, Florida 32958-0127 RE: Traffic Signal, SR 5 at Schumann Drive Dear Mr. Franco: Suncom Telephone: 424-1011 Plans for the referenced traffic signal are being reviewed by the FDOT in Ft. Lauderdale. I spoke with Mr. Bill lewis, Assistant District Traffic Operations Engineer, on July 14 and was advised that their review should be complete by the end of August. In addition, funding levels for the Equipment Purchase Program during FY86-87 have not yet been finalized. Please call if you have any questions. Very trulVyours, Michael L. Orr, Traffic Engineer MLO: rt City of - Sebastian L. (,ENE HARRIS POST OFFICE BOX 127 ❑ SEBASTIAN, FLORIDA 32958-0127 Hector A. Franco Mayor TELEPHONE (305) 589.5330 City Engineer July 9, 1986 Michael Orr County Administration Building 1890 25th Street Vero Beach F1 32960 Dear Mr. Orr: Please advise the a us the Schumann Drive traffic signal and the es imated co etion date. Thank you for your assistance in•this matter. Sincerely, I\ Hect(/r A. Franco Cit Engineer C r BOARD OIC COUNTY COMMISSIONERS 1840 251h Street, Vero Beach, Florida 32960 Telephone: (305( 567-6000 May 23, 1986 Mr. E.11 Lewis Assistant District Traffic Operations Engineer 780 S.W. 24th Street Fort Lauderdale, FL. 33315-2696 RE: Section 88010, SR 5 ( U.S. 1) At Schumann Drive; City of. Sebasti.an, Indian River County TRAFFIC SIGNAL Dear Hill, Suncom Telephone 424-1011 The City of Sebastian has asked me to be their agent in constructing the referenced traffic signal. A copy of the proposed signalizat.ion design is enclosed for your review and permit application. It is requested that the material for the signal be provided through the Department's Equipment Procurement Program for FY86-87. Please forward the appropriate order forms when they are ready. Please call my office at Suncom 424-1234 if you have any questions. Very truly,yeuts, X ' Michael L. Orr, Traffic Engineer MLO: rt Enclosures cc: hector Franco, City Engineer L. GENE HARRIS Mayor City of Sebastian POST OFFICE BOX 127 ❑ SEBASTIAN, FLORIDA 32958-0127 TELEPHONE (305) 589-5330 May 16, 1986 Michael L. Orr County Traffic Engineer Indian River County 1840 25th Street Vero Beach F1 32960 RE: Traffic Signal Schumann Drive Dear Mr. Orr: Thank you for your help in the design of the traffic light for Schumann Drive. I have recommended approval of the design to the City Council and they in turn approved the design at their last meeting. Please consider this your authorization to submit the plan set to the FDOT for review and place an order for the signal equipment to be furnished by the FDOT through their FY86-87 procurement program. Should you havey furthe hesitate to conta t me. Very truly yours, Hecto�y A. Franco City ngineer HAT: lk CC: Mayor Harris tions, please do not Hector A. Franco City Engineer BOARD OF COUNTY COMMISSIONERS 1840 25th Street, Vero Beach, Florida 32960 Telephone: (305) 587-6000 May 15, 1986 Mr. Ken Roth, Councilman City of Sebastian 1225 Main Street Sebastian, F1. 32958 RE: Traffic Signal, US 1 at Schumann Drive Dear Mr. Roth: As you requested prior to Planning Committee, enclosed improvements related to the Drive. Suncom Telephone: e2e-1011 the May 13th Transportation is a cost estimate for all signalization of US1/Schumann Upon approval of the signalization plan sent to Mr. Franco on April 22, 1986, we can submit the plan set to the FDOT ' for review and place an order for the signal equipment to be furnished by the FDOT through their FY86-87 procurement program. Please call if you have any questions. Very, truly ys Michael L. Orr, Traffic Engineer MLO: rt cc: James W. Davis, P.E., Public Works Director .Hector Franco, City Engineer, City of Sebastian Cost (estimate) Item FDO'P Sebastian Traffic Signal: Controller Assembly 4,500 Concrete Poles (2) 1,600 Signal Heads (8) 1,400 Head Accessories (8) 1,600 Loop Detectors (8) 800 Loops (17) 2,500 Misc. - Grounding, Cable, Elec. Service, Span Wire, Labor, etc. 8,000 Guardrail 5,000 Improve Northbound Left -turn Lane 10,000 Modify Schumann Drive 5,000 Totals $9,900 $30,500 rOT — TRRFF( G OFE2n-n0,J5 aQ�p SoOTHwEsT 14. STl Foer 4vaDO&PALIE FLS 33 a' �- fit City of Sebastian _ BOX 127 ❑ SEBASTIAN, FLOBIDA 32958-0127 Hector A. Franco Mayor TELEPHONE (305) 589- 30 City Engineer April 28, 1986 TO: Mayor and City Council FROM: Hector A. Franco City Engineer RE: Traffic Signal US dl a Schumann Drive For your information an further action, please find attached a letter from Michael L, rr, County Traffic Engineer. The letter is pelf explandtpry, I have ,reviewed the design and can recommend the city council to approve it and authorize the City Engineering Department to follow all the -required steps in order to complete the project and get the traffic light installed. It is necessary to point out that this gxpendi,turp. i:$ included on the federal revenue sharing money. Telephone: (305) 567.8000 BOARD OF COUNTY COMMISSIONERS 1840 25th Street, Vero Beach, Florida 32960 lj r .III NEERcn _ 4��///����.'''��yyyy SunCom Telephone: 424.1011....... April 22, 1986 Mr. Hector Franco City Engineer City of Sebastian 1225 Main Street Sebastian, F1.'32958 Re: Traffic Signal, US 1 at Schumann Drive Dear Mr. Franco: Enclosed is a print of the traffic signal plans for the intersection of US 1 and Schumann Drive for your review. The next step is to submit the plans to FDOT Traffic Operations in Fort Lauderdale and subsequently order the necessary equipment through the FDOT. Please let us know if you desire assistance. Total cost for this project by Indian River County through preliminary design is $206.71. Feel free to call me at 567-8000 ext. 234 if you have any questions. very truly yo , Michael L. Orr, Traffic Engineer MLO: rt cc: Councilman Ken Roth James W. Davis, P.E., Public Works Director SUGGESTED BUDGET FEDERAL REVENUE SHARING Fiscal Year 1985/1986 REVENUE Carryover from Previous Year $ 49,253.00 Anticipated Federal Grant 83,000.00 Interest Earned 250,00 $ 132,503.00 EXPENDITURES Barber St. Fire Substation $ 46,836.00 Library Improvements 3,000.00 Handicapped Improvements 8,000.00 Lift, Pad 6 Cover for vehicle Maintenance 9,000.00 Traffic Light at Schumann s U.S. 1 25,900.00 Ballfield 25,000.00 Development of Hardee Lake Park (Parking Area) 15,000.00 Administrative Costs 167.00 $ 132,503.00 Jim Gallagher Mayor City of Sebastian POST OFFICE BOX 127 D SEBASTIAN, FLORIDA 32958.0127 Hector A. Franco TELEPHONE (305) 589-5330 City Engineer March 20, 1986 T0: Mayor Gene Harris Police Chief Nappi Public Works Director,Peltier ✓ From: Hector A. Franco City Engineer Please find attached for y94r information a copy of a letter from the Board of County Commissi0ers regarding the traffic signal at Schumann Drive and U.S. N1, Should you have any questions, please feel free to contact me. 9 BOARD OF COUNTY COMMISSIONERS 1840 250s Street, Vero Beach, h7orida 32960 1 ulnphone. 13051 567-UON March 13, 1986 Vice Mayor Kenneth Roth City of Sebastian P.O. Box 127 3(,b,asti:ln, 1'1. 32958-01 2 % Dear Mr. Roth: Suncom Tobphone. 171-1011 A proposed schedule for the Construction a traffic signal at US 1 and Schumann Drive is offered below. As approved by the Transportation Planning Committee on March 11 1986, the ['raffia Engiru:ering Department will assist in your effort to construct lite uignal un a cost 1Jn611B. Proposed Conutruction Schedule 1986-1907 March -April Design Signal May -June FDOT Review and Permit July -October Order Signal Equipment from FDOT January -February Receive Equipment and Install Signal. Please feel free to call my office if you have any questions. Very truly yours Michael L. Orr, Traffic Engineer MLO:rt rc: James W. Ddvis, P.E., Public Works Director Florida �I ill l.I1 l.I1PM Li1VL11NV11 Department of Transportation 780 SOUChWVNL 24 Street Fort Lauderdale, Florida 33315-2696 Telephone: (305) 524-8621 Honorable .1im CaILagher Ciry of Sebastial[ 11.0. bux 127 Sebastian, Florida 32958-0127 Dear Mayor Callagher: P VI N P^PPA• Murch 4, 19135 Re: Sectlou 88UlUl Sit 5 (U.S. 1) at Schumann Urivc City of Subastian, Indian River County Itlil llliS'1' 1'U It TRAFFIC SIGNAL RECEIVrr) x.16 f y This IS In response to your letter of January 15, 1985. We agree that a traliic Signal Is warranted lit this inter- section. Uniortuuatuly, FlurLda Uupartmout of 'Transportation funds are already coumtltted to other projects for the next two to three years. There is, however, an alternative method by which a signal may be acquired. That 1S, Lhrough our 1?qulpntent Procurement Urogram. Under this program the Ciry of Sebastian is responsible for the denigu and hl.aI lhlLloo of the Signal, with the Florida De- partmeht of TratibpurLaLiuu pruvidiug Lite signal equipment re- quired. If the City desires to pursue chis uptlon, we will need a letter of coumlittment to this installation. in addition it will be necessary to provide a sketch of the proposed signal design. Honorable Gallagher Murch 4, 198 Page Two 11 you have any questluns or couments, please contact this office. Sincerely, �l William A. Lewis, Jr„ P. ,E AsslsLant D1sLrlct 'traffic` Operations Engineer WAL:hu cc: Mrs. Lenora Barber Mr. Michaul Orr SIGNED '-J DATE SIGNED CFaEDIFORMJ, 4S 469 POLY PAA (50 SETS) 4P 469 SENO PARTS 1 AND 3 WITH CARBON INTACT. - PART 3 WILL BB RETURNBD WITH REPLY, DETACH AND FILE FOR FOLLOW • SUBIECT �,,.,. �� pATE SIGNED '-J DATE SIGNED CFaEDIFORMJ, 4S 469 POLY PAA (50 SETS) 4P 469 SENO PARTS 1 AND 3 WITH CARBON INTACT. - PART 3 WILL BB RETURNBD WITH REPLY, DETACH AND FILE FOR FOLLOW