CERTIFICATE OF PROJECT COMPLETION
Date Accepted:
06/02/19
Project Name & #:
Construct Shade Hangars # Al 852
Total Project Expenditures:
$ 622,471.69
Project Location:
Airport
Contractor(s):
Clyde Johnson Contracting/Dean Steel Buildings/ICE/Misc
Contract Amount(s):
$ 422,108.00/$ 149,800.00/$ 37,075.00/$ 13,488.69
Pursuant to the above captioned contract and in compliance of same, we the undersigned do hereby certify
that this project is complete.
Issuance of this certificate releases the contractor from any further responsibility as stipulated in the contract
as it relates to bond performance, payment of subcontractors, release of liens, maintenance and indemnity. All
contractual obligations as to warranty, insurance, indemnification and patents, shall remain in full effect for the
contractually stipulated period of time. In no way does the issuing of this certificate release the Contractor from
all legal obligations as stipulated in Chapter 713 of the Florida Statutes.
Therefore, having reviewed the contract and inspected the work, the undersigned to hereby accept the
segment as being complete.
5 2� W25l2of9
Project Manager
Date
1;1
(e Building O if applicab e D e
4ferl
( l ld l tXX. AxYlA (o Z 7j 4
Date
PROJECT ID A1852 Construct Shade Hanagm
4 Iaote
FY18
FY19
DATE
CHECK#
PO#
DESCRIPTION
VENDOR
AMOUNT
AMOUNT
TOTALS
11/13/17
95833
8216
Professional Services (10/1/17- 10/31/17)
Infrastructure Consulting & Engineering
5,430.00
5,430.00
12/12/17
96091
8216
Professional Services (11/01/17 - 11130117)
Infrastructure Consulting & Engineering
12,935.00
12,935.00
01/10/18
96204
8216
Professional Services (12/01117-1 2 /31/1 7)
Infrestmcture Consulting & Engineering
4,000.00
4,000.00
01/01/18
AmEx
Invdation to Bid Notice
Treasure Coast Newspapers
212.85
212.85
0129/18
VISA
Permit Application Fee
St. Johns River Water Management District
100.00
100.00
02/08/18
96415
8216
Professional Services -(01/01/18-0128/18)
Infrastructure Consulting & Engineering
2,010.00
2,010.00
03/15/18
96631
8216
Professional Services -(0129118-03/04/18)
Infrastructure Consulting & Engmeenng
2,010.00
2,010.00
0328/18
96781
Fabricate metal stanchions for solar taxiway lights
Sawgrass Welding
490.00
490.00
04/11/18
AmEx
Invitation to Bid Notice
Treasure Coast Newspapers
223.17
223.17
08/10/16
97546
8496
20% deposit - (2) steel buildings
Dean Steel Buildings
29,960.00
29,960.00
09/19/18
97725
FDEP Permit
Dept of Environmental Protection
500.00
500.00
09/19/18
97736
Utility Construction Permit
Indian River County Dept of Utility Services
150-00
150.00
10/04/18
Journal Entry
Building Permit
City of Sebastian
4,681.64
4,681.64
10/09/18
97858
FDEP Permit
Dept of Environmental Protection
150.00
150.00
12/04/18
98306
8624
(15) Storage Boxes
Tool Fetch
4,060.00
4,060.00
12/14/18
98322
8518
Shade Hangar Construction thm 12/14/18
Clyde Johnson Contracting
42,102.90
42,102.90
12/17/18
Wire Transfer
8496
(2) Steel Builtlings- Final Payment
Dean Steel Buildings
119,840.00
119,840.00
01/07/19
98446
8518
Shade Hangar Construction 12/14/18-01/07/19
Clyde Johnson Contracting
65,115.00
65,115.00
0125/19
98525
8518
Shade Hangar Construction 01/08119- 0125/19
Clyde Johnson Contacting
115,567.20
115,567.20
01/31/19
98656
8675
Striping Paint for Shade Hangar
Florida Transcor
1,380.00
1,380.00
02/11/19
VISA
(6) Fire Extinguisher Signs
Amazon
15.99
15.99
02/11/19
VISA
(6) 1011, fire extinguishers
Amazon
356.94
356.94
02/11/19
VISA
(2) 3W Blue Double Braided Nylon Rope
Amason
47990
47990
02/12/19
VISA
(5) 32 gallon heavy duty wheeled trash cans
Amazon
688.20
688.20
02/15/19
98693
8518
Shade Hangar Construction 0l/26/19-02/15119
Clyde Johnson Contracting
66,159.90
66,159.90
03/05/19
98729
8518
Shade Hangar Construction 02/16/19 - 03105119
Clyde Johnson Contracting
32,858.10
32,858.10
03/15/19
98862
8518
Shade Hangar Construction 03/06/19-03/15/19
Clyde Johnson Contracting
58,094.10
58,094.10
03/15/19
99177
8518
Shade Hangar Construction - Retainage
Clyde Johnson Contacting
42,210.80
42,210.80
06/06/19
99340
8784
Professional Services (03/05/18 -06/02/19)
Infrastructure Consulting & Engineering
10,690.00
10,690.00
0.00
58,021.02
564,450.67
622,471-69
SEBASTIAN MUNICIPAL AIRPORT
CITY OF SEBASTIAN, FLORIDA
202 AIRPORT DRIVE E.
SEBASTIAN, FLORIDA 32958
5tE13AS -
MUNICIPAL AIRPORI
CHANGE ORDER
!, ProjectTtie: Shade Hangars I Date Prepared:
Original Contract Date:
Project Design Services for the 14 shade hangar
Description: units FAA AIP No.
Consultant Infrastructure Consulting and Engineering I FDOT Fin Proj No.
Address: 5550 W Idlewild Avenue, Suite 102 III4,
Tampa, Florida 33634 Change Order#
ORIGINAL CONTRACT AMOUNT: $
AMOUNT OF PREVIOUS CHANGE ORDERS: $
COST OF THIS CHANGE ORDER: $
REVISED CONTRACT AMOUNT: $
DESCRIPTION OF CHANGE QUANTITY
Design changes to include additional bidding services, waterline and
hydrant design and permitting, foundation design, and redesign of
structure. See attached backup
Reason for Chance Order. Additional Work (see attached backup)
May 23. 2019
October 11, 2017
n/a
441615-1-94-01
001
$26.385.00
0.001
510.690 I
_ $37,075.00
UNIT PRICE TOTAL AMOUNT I
$10,690
Subiect to the conditions set forth below, an ecuitable adiustment is established as follows:
The contract once is ... The contract time to complete work is ...
notchanged.z not.
changed.
x Increased $10.690 Inc c(ecreased 0 days.
The foregoing is in accordance with your contract dated I Octo er land as listed below:
A. The aforementioned change and work affected thereby are subject to all contract stipulations and covenants.
8. The rights of the Owner are not prejudiced; and
C. All claims against the Owner which are incidental to or as a consequence of the aforementioned change are
satisfied.
Owner Representative:
Consultant Representative
FAA (ifapplicable)
FDOT (if applicable)
SIGNATURE
DISTRIBUTION: Eacn Agnatory Parry
ATTACHMENTS: EWUt W Change Orilerjustifiwtion
TITLE
Vice President 15-23-19
DATE
1
Exhibit "A"
Change Order Justification
The project was originally intended to be a structural column with tight fabric pulled between "Y" shaped
arms (see below). Cost escalation and problems with the manufacturer forced the City to re -design the
project with a rigid, structural steel covering. A breakdown of the design cost effects incurred by the ICE
are summarized below.
Additional biddinn{� services: Due to high costs associated with the Aeropon USA original bid, the City was
forced to re -bid fhe project. The original bid (17-23) opening was February 8, 2018. New bid (18-04) was
opened May 11, 2018. This required ICE to modify the plans, modify front ends, re -assembled bid docs,
attend an additional pre-bid meeting, generated minutes to meeting, and preparation of addenda.
Cost = $4.000
Added hydrant: The City building official required a hydrant be placed within 400' of every comer of the
building structure. This required design calculations for flow and Indian River County Utilities
coordination. Changes to our plan set to incorporate a new waterline lie in to the main, plan view, and
details were needed. Also, IRCU and DEP permit applications.
Cost= 51,800
Structure chances: The original design involved a fabric covered type of structure manufactured by
Aeropon. These bids came in too high and there was uncertainty about the manufacturer to deliver. ICE
revised the Aeropon design with the re -bid (18-04)at project completion to move away from fabric
covering with cantilever support poles to a pre-engineered steel building. Details of the Aeropon design
was redrawn along with new specifications for a Dean steel building or approved equal.
Cost = $3.000
Original Design- December 2017
New Design — April 2018
E71
i
I
-
(
1
I
I
1
8MM-EVAnON-FROMwEWHIGH SIDE
I
L.
E71
Foundation calculations and olans:, Originally, the responsibility for the foundation design was to be part
of the Aeroport product. When problems with Aeropod surfaced, forcing the City to change products, the
responsibility was put on the bidder. However, this was changed due to backlash from bidders not
wanting the responsibility. ICE designed foundations for the rigid steel building that were 3' diameter by 8'
deep concrete.
Cost = 51,800
Construction Administration and Closeout: ICE was retained to perform engineering construction
administration which included:
• Review pay applications
• Engineer Site Visits
• Review of contractor submittals
• Review of testing reports
• Coordination with contractor, City, utilities, inspector
Cost =53,200
Pond/ Drainaoe Desion
From the original contract, ICE is offering a credit for a scaled back drainage design. Although culverts,
Inlets and pipes were in early phases of the design, they were removed due to cost and the site adjusted
for sheet now only. No pond design was ever performed. Therefore, we are offering a credit of the
following:
14 hours senior engineer = $2,450
4 hours designer = S 360
Cost = (52.6 t 0)
Total Change Order #1 = $10,690
SE��V
MUNICIPAL AIRPORT
WORK AUTHORIZATION FORM
Work Authorization #02 — Sebastian Municipal Airport
Shade Hangar Project Engineering and Consulting
City Project # FDOT 441615-1
The City of Sebastian hereby assigns to Infrastructure Consulting & Engineering (ICE), a
Sebastian Municipal Airport commissioned consultant, approval to perform the work outlined in
the attached Scope of Work, Exhibits 'A' and 'B' dated 9/05/2017 with respect to the Engineer
and Construct Shade Hangars project at Sebastian Municipal Airport.
Description of Assignment: See Attached Scope of Work
Basis of Completion / Period of Services:
Services shall be provided for a payment of: $26,385.00
Work will commence upon execution of this Work Authorization by the parties and continue in
accordance with Exhibit "A" provided in the Scope of Work. Services shall be completed within 120 -Days
of the execution of this Work Authorization Form.
AGREED as to scope of services, time schedule and budget this 11'" day of October, 2017.
CITY OF SEBASTIAN
A Florida Municipal Corporation
40S G la, City Manager
(seal)_
Attest:
Infrastructure Consulting & Engineering
By:
ug Hambrecht, P.E, Vice President
Approved as to Form and Content for Reliance
By the City of Sebastian only:
J nette Williams, MMC, City Clerk Cynthih V Hall, Interim City Attorney
Staff Approvals: / 1�
Administrative Services as to budget
1E
INFRASTRUCTURE
CON6LVI%0 d [601N[flM
Project Description
EXHIBIT "A"
SCOPE OF WORK
SHADE HANGARS
Sebastian Municipal Airport
number will depend on cost.
SEBASTIAN
YIr=
MUNICIPAL AIRPORT
The City of Sebastian and the Sebastian Municipal
Airport (CITY) desire shade hangars for the west
side of the airport. These hangars shall consist of
column(s) support to a roof truss system which
stretches and supports a type of polypropylene
fabric covering. Infrastructure Consulting and
Engineering will provide performance
specifications for a system meeting the airport's
desires to be competitively bid. Site work
includes re -using much of the existing base
material for the new pavements and a milling and
resurfacing of the existing where it can be re-
used. An in depth design for the grading and
drainage and permitting of the site will be
required as well as obtaining water management
permits. ICE will also administer the bidding.
The total number of shade hangars desired is 14
units; 12 units for single engine type aircraft, and
two larger units for twin engines. The actual
The budget for this project is based on an 80/20 FDOT grant for a total project amount of
$625,000.
See the conceptual layout shown in the attached sketch labeled Exhibit "C".
The current condition of the asphalt in this area is severely cracked and cannot be salvaged.
Instead, this asphalt shall be removed and the surface re-applied to the current grades. Limerock
base material will be re -used in areas of asphalt apron to be converted to grass. A new asphalt
pavement section consisting of 2" of Bituminous Material will be incorporated for the taxilane,
taxidrives, and the area under the shade structure.
Electrical improvements shall be basic and include only a general description of what shall be
required by the contractor. It is assumed the contractor shall investigate the meter housing on the
T -Hangar and provide an underground feed to the project area for installation of several roof
mounted exterior LED lights. Since this electrical work is minor, it is assumed the contractor can pull
Shade Hangars 9/5/2017 Page A-1 of A-5
his own permit and no engineering seal will be required.
Preliminary conversations with the City of Sebastian building department and Community
Development have assured us the project will not require any parking areas for vehicles. Therefore,
landscaping, access roads, and parking lot design are not included in this scope.
Other design items of consideration for this Project Scope:
• Performance specifications and guidelines for a pre-engineered shade structure.
• Site Geometric Design to meet criteria of various structure widths and lengths and aircraft
Object Free Area.
• Removal of taxiway pavement
• Apron Pavement and Taxiway Layout and Design
• Stormwater pond and site drainage
• Environmental Resource Permit from SJRWMD
• Construction Safety and Phasing Plan
The design and production of bid documents will consist of the following items:
Grading and Drainage Plans
Retention Pond Design
Earthwork calculations
Technical Specifications
FDEP/ SJRWMD Permit
Survey
Pavement Marking Quantity Calculations
FDOT coordination Coordination with CITY
Stormwater Pollution Prevention Plans (required for permit)
No site survey shall be performed. ICE will utilize points provided by the City Surveyor already in
hand.
No geotechnical investigation will be performed. Instead, ICE shall utilize information obtain in
past reports within the vicinity of the project and information based on hand digging performed
by the airport staff. Review meetings shall be held via conference call.
Compensation for the above mentioned work will be based on the Manhour and Fee Estimate
provided in Exhibit B.
Design deliverables shall be broken up into three phases Phasel — 30% Design, Phase 2- 60%
Design, and Phase 3- 100% Design. Phases 4 shall include bidding services.
Phase 1-30%Design
Phase 1 services will involve preliminary design and the production of 30% Plans. The design
considerations shall include:
Shade Hangars 9/5/2017 Page A-2 of A-5
• Draft hangar technical specification and requirements,
• General Coordination with Airport Staff,
• Drainage Evaluation,
• Horizontal and Vertical Geometrics,
• St. John's River Water Management District (SJRWMD) Pre -Application Meeting,
• Preliminary Cost Estimates, and
• Preliminary Construction Schedule.
The Consultant will prepare a revised Construction Cost Estimate and the Preliminary Plans, which
will include:
Cover Sheet Project Layout Plan
Typical Sections Staking and Demolition Plan
Deliverables Three (3) copies of the PreliminaryPlans in 11 x17"pdfformat will be submitted to the
CITY for distribution to airport staff`.
Phase 2 — 60% Design
The Consultant shall address any changes requested by the airport at the 30% Review Meeting in
this Phase. Upon issuance of the Notice to Proceed, the Consultant will proceed with the 60% Plans
to include the following:
• Final hangar technical specification and requirements,
• Preliminary Drainage Design,
• General Coordination,
• Preliminary Grading,
• OE/AAA submittal
• Construction Safety and Phasing Plan,
• Updated Cost Estimates, and
• SJRWMD Permit submittal
The Consultant will prepare a revised Construction Cost Estimate and the 60% Plans, which will
include:
Cover Sheet
Typical Sections
General Notes
Preliminary Grading Plans
Project Layout Plan
Safety Plan
Staking and Demolition Plan
Marking Plan
The Consultant will meet with the CITY to review the Plans and Specifications to verify that all
concerns, issues, and potential conflicts are addressed prior to proceeding with 90% Construction
Documents.
Shade Hangars 9/5/2017 Page A-3 of A-5
Deliverables.- Three (3) copies of the 60% Plans in 11 "r17"pdf format will be submitted to the CITY
for distribution to airport stab`.
Phase 3 —100% Design
The Consultant shall address any changes requested by the airport at the 60% Review Meeting in
this Phase. Upon issuance of the Notice to Proceed, the Consultant will proceed with the 100%
Plans to include the following:
• Front End Documents,
• Technical Specifications,
• Responses to SJRWMD Permit Application,
• Final Grading Plans,
• Construction notes, and
• Final Cost Estimates/ Bid Schedule.
The Consultant will prepare a final Construction Cost Estimate and the 100% Plans, which will
include:
Cover Sheet
Typical Sections
General Notes
Profile Sheets
Drainage Details
Erosion Control Plans
Project Layout Plan
Construction Safety and Phasing Plan
Staking and Demolition Plan
Grading and Drainage Plans
Signing and Marking Plans
Miscellaneous Details
The Consultant will meet with the CITY to review the Plans and Specifications to verify that all
concerns, issues, and potential conflicts are addressed prior to proceeding with Final Construction
Documents.
Deliverables Three (3) copies of the 100% Plans in 11 `x17"pd( format, a set of specifications and
front end documents will be submitted to the CITY for distribution to airport staff. Two sets of
signed and sealed plans will be submitted for CITYrecords. A copy will also be sent to the FAA, and
FDOT for their files
Phase 4—Bidding Services
The Consultant shall perform general coordination with the City and Bidders and will:
o Maintain project FTP site. Distribute plans and specifications to potential bidders.
o Pre -Bid Conference (by telephone);
o Prepare and distribute addenda as necessary;
o Assist the CITY in tabulating and evaluating bids; and
Shade Hangars 9/5/2017 Page A-4 of A-5
o Assist the CITY for the re -bid of the project if the CITY rejects the bids for any reason. This
work will be performed as an additional service requiring a negotiated contract; and
o Assist in the contract award and preparation of construction contract documents.
Other Provisions
a) The CITY will pay all costs associated with any permit application and/or impact fees.
b) No construction services are included at this time.
c) No attendance at the pre-bid conference will be included at this time.
Schedule.•
(rota/ design duration= 95 days, contingent on owners review time)
Shade Hangars 9/5/2017 Page A-5 of A-5
2017 2018
Work
Phase Major Activities
Notice to Proceed
!!!tom!!!!!!!
(rota/ design duration= 95 days, contingent on owners review time)
Shade Hangars 9/5/2017 Page A-5 of A-5
EXHIBITSE�t
Manhour anddFeea Estimate
Shade Hangar1E
—
Sebastian Municipal Airport MUNICIPAL AIRPORT
INFRASTRUCTURE Summary
CO`+N.41gGa(Mtr(Fdvf.
PHASE PHASE2 PHASE3 PHASE4 TOTAL
TOTAL HOURS 39 107 32 35 213
TASK COST $4,515.00 $13,300.00 $3,725.00 $4,020.00 $25,560.00
Reproduction
$200.00
30% Plans
60% Plans
100% Plans
Bidding
$75.00
CLASSIFICATION
RATES
HOURS
HOURS
HOURS
HOURS
HOURS
$825.00
Principal
$225.00
0
0
1
0
1
Project Manager
$175.00
2
1
1
4
8
Senior Engineer
$175.00
9
48
9
_
72
Engineer
$150.00
7
0
3
18
Designer
$90.00
3
25
2
31
Technician
$75.00
14
33
12
64
Administrative Assist.
$55.00
4
0
4
11
19
TOTAL HOURS 39 107 32 35 213
TASK COST $4,515.00 $13,300.00 $3,725.00 $4,020.00 $25,560.00
Reproduction
$200.00
$200.00
$200.00
$600.00
Postage
$75.00
$75.00
$75.00
$225.00
TOTAL EXPENSES
$275.00
$275.00
5275.00
$825.00
ITOTAL COSTS $4,790.00 $13,575.00 $4,000.00 $4,020.00 $26,385.001
Lump Sum Lump
Page B-1 of B-5
0.019101:9
Sebastian Municipal Airport
Shade Hangar
Phase 1 - 30% Design Plans
MANHOUR AND FEE ESTIMATE
Project Senior Administrative Total
Item/Task Description Principal Manager Engineer Engineer Designer Technician Assistant Hours
-_Coordination with Airport Sta_ff_--"--- --------- -------------------------- ---------------2
Coordination with Subconsultants 2 1 3
Horizontal Desyn _________ ______? 3 ? ?
-- -orizo------------------------------------------------ -------------- ----- ------
---Construction-Cost Estimate 1 2 2 _ 5
------------------------------------------------------------------------------------------------------------- ---
-
Prepare
------------------------------- --------------------------------- ------------- --------_------------------ -----------------
—
---Lbk§L9eet------------------------------- —------ —------ —---------------------------- --- --- — ------- ------'------- 1—'---------------------__1
_—?sect tapout Plan------------------------------ — -------- — ------- --------------- 2--- -------- — ------ ------- Z--
-------------------------------------------------------
__Jyb,_rcq/Sgctio2__________—_—__________________________________—_________________________123______
----aki!i9_a2q_De7jolitio�=1a2-------------------------- ---?- -------------- --------------- 4 -------
Assemble Preliminary Shade Hangar performance
----------------------------- -------------------------- -------------
4 4 2 10
Quality Control Review 1 1
Plot 30% 11'x17 plans (3 Copies) 1 1
Total Hours: 0 2 9 7 3 14 4 39
Page B-2 of B-5
EXHIBIT "B°
Sebastian Municipal Airport
SrVI:[4s1:L1.193;14 7dbFIN ly
Shade Hangar
Phase 2 - 60% Design Plans
Item/rask Description
Project Senior
Principal Manager Engineer
Technical
Engineer Designer Technician Assistant
Total
Hours
Coordination with Airport
1
6
1
-"—'-""coon Safety --"-'-'---9 -------------------------------------------------------------------__'--__--______—'-'—""-'--"'------------'-----------------
Construction Safety and Phasin Plan
3
6 4
13
Final Drainage Design
2 -----------------------
2
Draina a Desi n
5---
12
8 9
--"—
1
---_ ---""'-'—'-'-------------------------------'--'---
Pond Design
___-- —_ '__--"'-"__'
14
_-_— ___ - ---------------29
______—_ "---
4
----
18
Geometry
_ Finalize Pavement Geometry
-------------------------------------
2
Stormwater Permitting
Prepare and Submit SJRWMD Permit Application
Prepare 60% Plans
--General Notes _------ ____
Stakin and Demolition Plan
Typical Section
----------------------------------------
PreliminarV Gradinq Plans
4
Total Hours: 0 1 48 0 25 33 0 107
Page B-3 of B-5
2
2
18
3
6
27
11
---------------------------------------------------------------------
--------------------------------------
2 -----------------------
2
--"—
1
2
2
Total Hours: 0 1 48 0 25 33 0 107
Page B-3 of B-5
EXHIBIT "B"
Sebastian Municipal Airport
Shade Hangar
Phase 3 -100% Design Plans
MANHOUR AND FEE ESTIMATE
Project Senior Technical Total
Item/Task Description Principal Manager Engineer Engineer Designer Technician Assistant Hours
Coordination with Airport
1 1
2
-------'------------------------------------------------------------------------------------------------------------------------____—"""—__'_---------
Final Front End Documents
1
2 3
Final Technical Seecifications
2
Prepare and submit OE/AAA
--------
1 2 4
__?___________4___
7
Prepare 100% Plans
Gradin and
2
1 2
5
-Drainage -Plans
----- -----------------
_ -
--------------------------------------
----DrainageDetails - -----------------------------------1
Erosion Control Plans
--------------------------------
-----------1 -----------------
1 2
-------� -
3 "'-
-n-gP---la---ns-_'—_""------------""---_------------------------------------------------
—G'Mark in
1 '-----_-------------------------------------1
1 ----------
2
Miscellaneous Details
1
1
2
--"------------'----' ---------------'—"—"--------------------------------------------------------------------------------------
QualitY Review 1—_
1
Plot 100% 11"xU" Plans
1
_ - —
1
Total Hours: 1 1 9 3 2 12 4 32
Page B4 of B-5
EXHIBIT "B"
Sebastian Municipal Airport
Shade Hangar
Phase 4 - Bidding Services
Project Senior Technical
Item/Task Description Principal Manager Engineer Engineer Designer Technician Assistant Totals
Total hours: 0 4 6 8 1 5 11 35
Page B-5 of B-5