HomeMy WebLinkAbout1994 07 20 - Permit CorrespondenceRe: Sebastian Sport Complex, Permit #42-061-0332NG,,,
Section 24, Township 31, Range 38
Indian River County
(Please reference Permit number on all submittals.)
Dear Mr. Koford:
On July 19, 1994, District staff re -inspected the above -referenced
permitted project. Based upon this inspection, the following
discrepancies have yet to be resolved with the stormwater system:
Northeast Retention Area:
1. A four (4) inch.PVC pipe is located in the west berm
connecting the retention area to the Rosebush Lane Swale.
2. Standing water, algae and cattail growth are in the
retention area, an indication of a recovery problem.
Northwest Retention Area;
1. A breech is located within the east berm connecting
the retention area to the Rosebush Lane swale.
2. Wetland type vegetation is growing in the retention
area, an indication of a recovery problem.
3. The type "C11 inlet with a 15 inch C.A.P is not
constructed in the east end of the retention area.
Within 30 days of receipt of this letter the following must be
completed to resolve the above referenced discrepancies:
1. Remove the PVC pipe from the west berm of the
Northeast Retention area.
Patricia T. Harden, CHAIRMAN Lenore N. McCullagh. VICE CHAIRMAN Jesse J. Panish, III, TREASURER William Segal. SECRETARY
SANFORD ORANGE PARK TITUSVILLE MAITLAND
Reid Hughes Dan Roach Denise M. Prescod Joe E. Hill James H. Williams
DAYTONA BEACH FERNANDINA BEACH JACKSONVILLE LEESBURG OCALA
Henry Dean, Executive Director
ST. JOHNS FIVER
John R. Wehle, Assistant Executive Director
Charles T. Myers III, Deputy Assistant Executive Dlrector
WATER
POST OFFICE BOX 1429 PALATKA, FLORIDA 32178-1429
MANAGEMENT TELEPHONE 904/329-4500 SLINCOM 904/860-4500
DISTRICT
FAX(EXECU71VE/LEGAL) 3294125 (PERMITTING)3294315 (ADWNISTRATION/FINANCE)32945M
FIELD STATIONS
818 E. South St.M 7775 Baymeadorre Way PERMITTING: OPERATIONS:
Orlando, Roil& 32801 Suke 102 305 Eaet Drive 2133 N. Wickham Road
907/9974300 JacksonvlM, Florida 32256 Meboume, Ficdda 32904 Mebourne, Fbrida 329359109
July
20, 1994
904/730-9270 407/9844940 40]254-1792
CERTIFIED
NUMBER: Z 757
311 749
AA
T
City
of Sebastian
JUL 1394
ATTN:
Mr. Joel Koford,
City Manager ReCeit/Pr;
1225
Main Street
City Manage,;
Sebastian,
FL 32958
Office
Re: Sebastian Sport Complex, Permit #42-061-0332NG,,,
Section 24, Township 31, Range 38
Indian River County
(Please reference Permit number on all submittals.)
Dear Mr. Koford:
On July 19, 1994, District staff re -inspected the above -referenced
permitted project. Based upon this inspection, the following
discrepancies have yet to be resolved with the stormwater system:
Northeast Retention Area:
1. A four (4) inch.PVC pipe is located in the west berm
connecting the retention area to the Rosebush Lane Swale.
2. Standing water, algae and cattail growth are in the
retention area, an indication of a recovery problem.
Northwest Retention Area;
1. A breech is located within the east berm connecting
the retention area to the Rosebush Lane swale.
2. Wetland type vegetation is growing in the retention
area, an indication of a recovery problem.
3. The type "C11 inlet with a 15 inch C.A.P is not
constructed in the east end of the retention area.
Within 30 days of receipt of this letter the following must be
completed to resolve the above referenced discrepancies:
1. Remove the PVC pipe from the west berm of the
Northeast Retention area.
Patricia T. Harden, CHAIRMAN Lenore N. McCullagh. VICE CHAIRMAN Jesse J. Panish, III, TREASURER William Segal. SECRETARY
SANFORD ORANGE PARK TITUSVILLE MAITLAND
Reid Hughes Dan Roach Denise M. Prescod Joe E. Hill James H. Williams
DAYTONA BEACH FERNANDINA BEACH JACKSONVILLE LEESBURG OCALA
2. Fill in the breech in the berm of the Northwest
Retention area and construct the type "C" inlet with
the 15 inch C.A.P. as depicted on the permitted plans
dated July 18, 1993.
3. Determine the cause of the recovery problem within
both retention areas and submit a corrective proposal
to the Melbourne office for a permit determination.
4. Notify the Melbourne
work is completed so that
be arranged.
Office when the corrective
a follow-up inspection may
Please find attached correspondence to Mr. Dan Eckis and from Mr.
Randy Mosby pertaining to this project.
Also be reminded that the operation phase of the permit shall not
become effective until a Florida Registered Professional Engineer
certifies that all facilities have been constructed in accordance
with the design approved by the District. Within 30 days after
completion of construction of the surface water management system,
the permittee shall submit the certification of completion or one
(1) set of plans which reflect the system as actually constructed
and notify the District that the facilities are ready for
inspection and approval.
If you have any questions, please contact Janice Unger or Eddie
Carr at 407/984-4940.
Si cerely,
nice V. Unger /
Compliance Manager
Department of Resource Mgmt
EC:ec
CC: John Juilianna
PDS
Attachments: 3
4�'C61'111-14
Eddie Carr
Field Representative
Department of Resource Mgmt