Loading...
HomeMy WebLinkAboutCO#4CITY OF SEBASTIAN CHANGE ORDER CHANGE ORDER A CONTRACTORNAME: L.R. Tanner Construction Corp PROJECT NAME: Police Evidence Bonding CONTACT NAME: Dan Acosta — City Representative CONTRACT DATE: Notice to Proceed: May 19, 2017 By the signature affixed below, both the City and the Contractor agree to the changes as stipulated herein. Upon proper execution of this document, the Contractor is hereby notified to commence work. All changes stated below are hereby incorporated and made a part of the Contract identified above, and all the terms and conditions of said Contract are enjoined and in full force while executing the change(s) stipulated as follows: DESCRIPTION: A) CONTRACT PRICE PRIOR TO THIS CHANGE S 371.475.72 NET INCREASE (DECREASE) RESULTING FROM THIS CHANGE S 9,690.98 NEW CONTRACT PRICE INCLUDING UDING THIS CHANGE ORDER S _381.166.60 B) CONTRACT TME PRIOR TO THIS CHANGE (NUMBER OF DAYS) 257 NET INCREASE (DECREASE) RESULTING FROM THIS CHANGE (NUMBER OF DAYS) 22 NEW COMPLETION DATE INCLUDING THIS CHANGE Febnrsy 21.2018 AGREED: fCONJ COF SEB TiAN:/ No-r/I�/_8' /7 �L...�. Aut dd Signature Autho a Ity M,44jer inager Authorization —cumulative amount less than 15% of contract price or 515,000 single change order. until Authorization — cumulative amount exceeds 15% of contract price or $15,000 single change order. date ) CITY OF SEBAST ,( Date: City Mani g Finance Director JeWhette Nllilams, MMC, City Clerk ------ City Attorney Procurement \ - ' CONTRACTOR'S NAME: LH. Tanner Construction Corporation Date 11/617 Job 6 17-804 ADDRESS: 2300 Avocado Ave, Melbourne, FL 32935Sebastian Poll" Evidence LIC #: CGC 1511228 Project Name Building Owner City of Sebesban Contract Rep, Dan Acosta Change Order # 4 C.R. Email Addre dacosta@etyorsebastian.org Project Address 1201 Main Street CITY Sebastian State Florida Zip 32958 B1 Additional Days Are Nature rid Na Change: Bund Ra Raceway for A/C Ductwork and AIC Stand ,� RegWred for This Change InS=Pa. Oescrbtion Ovantlty Un8 TOTAL 7/16' OSB 8 Sheet 5324.00 10' PT 2x4 6 Each $121.50 3/4' PT Plywood 1 Sheet 5701.25 1 Agree to the Above Described Scope and Price 5546.75 Date OWNER OR OWNER'S AGENT'S SIGNATURE 02 Additional Days Ars Nature or the Change: Design i Instan Air Condfti In Scopeoning .t,� .dor This Change In Scop. Description Ouanely unit TOTAL Provide Energy Cabs i Each S703S0 Layout Ductwork d Pro-Ada Shop Drawing 1 Each Install Distribution System per Shop Drawing / Each $568.50 54,416.00 Install d1d' Concrete AC Pad 1 Each $636.00 Install 3 Ton Trane l6SEFR Spin System (Model It 4TTR6036J1) 1 Each Credit for AC Mini Sprit System from Original Contract 2 Each $6.508.50 3/4' PVC Condensate Drain d Safe T Switch 1 Each •55.500.00 $467.25 20720 Finer Back Grill for AID Sbrq 1 Each $568.50 Install Fresh Air Makeup at Intake Vent at Soffit to Supply Side of DucN.ark 1 Each SM.So So Install Programmable Thermostat 1 Each 5207.38 I Agree to the Above Described Scope and Price $9,144.13 Date OWNER OR OWNER'S AGENTS SIGNATURE Total Change Order Amount: $9,690.88 Total Additional Days Required For Change Order Work: 22 Additional Days CONTRACTOR'S SIGNATURE