November 26, 1997
Mr. Martin Smithson
Interagency Program Manager
St. Johns Water Management District
1900 S. Harbor City Blvd, Suite 107
Melbourne. FL 32901
RE: Contract #95J266, Riverview Park
Shoreline Restoration Project Final Progress
Report
Dear Mr. Smithson:
We are pleased to submit this final report on the subject contract. The project
was completed on November 21, 1997 with the installation of the Fishing Observation
Pier, which was funded by the City as part of the City's Match to the SJWMD Cost
Share Agreement. The pier is a 60 foot long pier with a 24 foot X 12 foot observation
area. It was constructed according to the permitted plans by our contractor, Dockside
Builders, for $13,300. The Fishing/Observation Pier was the final portion to be
completed under the Riverview Park Shoreline Restoration Project.
Earlier phases of the project were completed in 1996. These phases included:
clearing the shoreline, installing a coquina rock breakwater over filter fabric, and
shoreline plantings. The total project was completed at a cost of $52,358.20. Please
review the attached breakdown of costs by contract item. The District's portion of the
cost share agreement that was actually expended totals $ 23,633.74. Please accept
this letter as the request for reimbursement of the District's share of the agreement.
Martin Smithson, SJWMD
November 26, 1997
The City is grateful to the District for supporting this project and we look forward
to working with your office on the Main Street Basin and Baffle Box project. If you have
any questions or concerns regarding this project, please don't hesitate to contact me. I
may be reached at 561-589-5490.
Sincerely,
Y�({tv2 S. Caj-,,P�
Martha S. Campbell, P.E.
City Engineer
enclosure