HomeMy WebLinkAboutQuarterly ReportQuarterly Report:Q2
Sebastian Municipal Airport
Construct Building 425720-1
Objectives
Provide current status of project and detail progress for this time period.
Due to the Fire Dept. review comments to add fire suppression for the hangar for permitting, the project scope was reviewed and
modified to reduce the hangar size to avoid the additional fire suppression requirement. The consultant prepared several
conceptual plans with the reduced hangar. The revision will not change the budget or contract amount only reduction of the
hangar size.
ProiectContinuation
Provide any additional information about future action items, challenges, or changes to this project:
Due to the reduction of the hangar building, City Council approved on December 10, 2014 the additional design contract services.
The consultant is working on the reduced hangar design plans which should be completed within two months. City anticipates to
advertise and award the construction of the hangar by the next quarter.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
Due to the holidays, City Council met only once in November and December 2014. The consultant was on -hold for the City
Council to approve the additional design contract for the reduced hangar building. The added design contract was approved on
December 10, 2014. The reduced hangar construction and added design cost is still within the project budget. Consultant will
invoice the City during this third quarter.
Quarterly Report:Q2
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
The Notice to Proceed was issued to the contractor on January 5, 2015. There was a delay in the construction start date due to
minor revisions needed to avoid impacting the golf course. The project was modified to add the piping of the eastside drainage
ditch as part of the project. No increase in construction cost, only a shift in the project to reduce the open swale and to add the
piping of the drainage ditch. Construction has begun on 1/5.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
City received the approved Supplemental JPA on 10/8 and issued the new NTP to the contractor. Contractor started on 1/5/15
with mobilization, erosion control, utility markings and excavation of the drainage ditch. The project is estimated to be completed
within the following quarter. The City terminated the contract with C&S on the design build of the storage building. City is
currently revising the plans to advertise in-house for construction by Feb 2015
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Quarterly Report:Q1
Sebastian Municipal Airport
Construct Building 425720-1
Objectives
Provide current status of project and detail progress for this time period.
Design consultant submitted 95% final plans to the City and other agencies for permits. Fire permit required the need for
additional cost for fire suppression which exceeds the project budget. City is redesigning the hanger size to be able to
construction a new hanger within budget.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
Complete the design and permitting of the new hangar to proceed into construction.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
City received the latest invoice from the design consultant in late Sept and will submit into the JACIP system this week.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
_ Quarterly Report:Q1
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
The Notice to Proceed was issued to the Contractor for the Airport Drive Construction however there impacts to the existing
airport/golf course project limits which required redesign and modification. In addition, there needs to be a supplemental JPA
approved by City on 10/8 for the approved FAA funds not listed. The storage building is behind in schedule and permits.
ProiectContinuation
Provide any additional information about future action items, challenges, or changes to this project:
City will approve the Supplemental JPA on 10/8 and issue new NTP for contractor to start on the Airport Drive Construction.
Estimate the construction to be completed within the following quarter. The City has terminated the contract with C&S
consultants on the Storage Building and will proceed with in-house engineering to re -advertise the construction project for Jan
2015.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Consultant Invoices were submitted.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Please upload project schedule
4. Scroll towards the bottom - you see it shows 'Select Year', in this case you'd be selecting
2014/2015
5. Select Quarter - in this case you'd be selecting October -December (Q2)
6. Answer the 3 questions and Submit, this will automatically send a notification to me.
7. I will review and you'll receive a follow up notification, letting you know if the project is in
compliance or if we're missing any documentation.
Please feel free to call me if you have any questions at (954) 777-4497.
Thank you,
Laurie McDermott
Aviation Coordinator/Office of Modal Development
Florida Department of Transportation, District 4
3400 West Commercial Blvd
Fort Lauderdale, FL 33309
Tel: (954)777-4497
Laurie. MCDermottOdot.state.f1.us
F�
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
4 Quarter for 2013
Grant Number:
AIP10
Projects:
Improve Access Road — Airport Drive
Nominal Airport Submission:
X_ Project Status Summary (one form for each project included in the grant agreement.)
_X_ Statement and Distribution of Project Costs or equivalent (cumulative)
FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
_X_ Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
_ All Change Orders, Work Authorizations/Scope Changes in addition to summary
Airport Sponsor Representative
/ , IIl�T
Title
Date
Updated November 2006
ADO Program Manager
wrt
011-V pue ZO I-V IT l$WO AD pagpOSOld
S01-ILZ
319VSn N011103 Sn01AUTI
rvVlia nuv tla7tl IVJO tlW UdLitl UHllitl
L£ZB-BB£ (ZLL)
IPIeA /louery
wmmene au,
)wfunV'ep0n my; 3NOH2=P1
i in. ONt Y 031111he HO OIdM
AI 1311 - 01 0111111133
3AlJVl N3S31d3N
PJRNF aW 10 SW)01 eq] UP# BOVepl000e
q m B i N)om Ile put pe WJDjjod UGvq Sey
q RIA -01
01
1' V"
u01132dsul ue 1241 pue )DIMI al AISn°IALO
L3NLIS 3IY°
tlltll ff lb3['
)//I
e371U0Hint ID Mnlv.ls
YBBq IOU eP4 y9lym anp 01245 IPIBpaj
041 SWBBBiOBI 1061110SM41mal 941 1,41 pup
loolud V41 l0 Guinq aw wlm aaueplooD, w
LZP-99C (ZLL)
misegaS 3o Allo
mmfw)n P.
/w
-Wne v,o: euo- 3xoxe3t31
aria ON', o31N1u< x0 03d).1
it clueweslnislp )L slsoo palllq 941 1011aq
puF a6pa1moin AW IC lsaq 041 w 1241 Apuao I
1N31d 1030 'P
03111WBnE 1tl4[3t 3l YC
11*1:10X12]11113' 13371NOH1111 103Bn1 VN915
N OI1tl01J 11H30 'ZI
&
k
k
10910id 10 00111910woo IVOISA40 to 06elusmad n
00 ,0 S
S S
$ IuaWBslnquimi j4l pB1sanbei lOnowV n
00 ,0
p01sa0bB) Alsnolna)O SlueWA,O ltoxpoj 'I
00 '0
00 ,0
QQ Q
QQ Q
(1 put L saugjo mins) QUEUE IelBpaj lelol 'S
00,0
puawasmgwl9/ !Y0011 Sluw6 uolle011geyaN'1
00'0
DIED 01 meOS le)Bpaj'In
WOZZ17L
00'0
00'0
8£ OZL'17L
IT OUR TOM U VU11) BIep 01 an0elnwns 19K, d
00,0
eW02Ul We1600 )03 Suollanpan '0
8£'OZL'17L
00'0
00'0
8£'0ZL'17L
WWIN fsduq/O Wnsimp O10Al1elnum I2wl'a
00'0
]SOD SpOOU,IB4SIW1'W
00,0
3uew01nh3 'I
00,0
ISO- lu2wanGJdW11011012 PUP U0119n11s000',,
00'0
¢na Wal poi UOIIIIOWBn'I
00'0
;U5 pup
slenpmlpw W sluawAe5uoeooWH1
00 ,0
50x1 uoyeoolay 'y
00 ,0
JUBWOOIBABp pUP1'
00 ,0
SBa) U04414Sul MlOid'I
00 ,0
aa1 ullBau' yF l,lnwaJlyO1P 18410 'F
B£'OZL't'L
8£'OZL'VL
seal p!seg uuaaul uai—M111TV P
00'10
201.14-1431, —mojonijs 'pull';
00'0
asuaaxa MEUIWIITld 'q
00'0 S
$
$
S
MOW OAne1131UIWptl 'e
1V101
of
Iql
Ie)
NBIlY0111SSV10
5 3 1114 11011 " SNOIlONnj — SWY0008d
SONnd JO Sn1tl1S II
awes :ap00 d/Z
6Z£ ld'uepsegeS WOO d/7
pue alvis 3AS
puF we2S'A3!(J
ewes jams pup 'DA
Jaails Uleh SM 1664$ pue 'PAT
awes :;WEN
uepsegeS to 1410 aweN
,[V,01 ueV, lwn//a /Vue!N0:f avV: ueYM ?3et< 0:
NOIl V21NYea°1N31d103, F
E L OZIOC/60 E loin OILO
LZt,000B-6S
11 . ner alum w ✓we eea urvoN x022
e3ennA TRIM '"a NO U3aFYnx
e3anah lNnu-ov s .740 lrD,.A3 1 e3).cian5 s
1S3003U
SINI AS 03113100 601113d
IIOd
Zl0-Ol0-S4L0-Z L-E-dIV
e9x3tr WHO;_ eE 43FwSSt
epltgld opue110 - uo0e11S1u1W py uo4eiAV lelepa,S
ON.E3nL321k3n.Y<tYI:NhY 5
t3anOh ON1n14N3w
p3Xa44L:NYNt lvdMio t
0311IW0ne S: 1a06b SIH1 HDIXM
W:x3n?ii ttkpl.YZINYLB40kh AOA30t ONWOSuwd tre3030 [
IVnW33V 0 HSVO 0
ltliletld ❑ IVN11 ❑
-Ee0L32 IT ElYF 2
-E3043t fG 3e11 i
INaep u0 tupg4nllsw ea$!
SWVB00Bd NO110OB1SNOO BOJ
Efpt< LI L
Z000'SFCO ON 1tlA0Nddtl SWO
:4 ?eta
1113W35B0 BW13N BOJ 153003N ONtl 1N0d3N AV1100
Page _1 _ of _1 _
STATEMENT AND DISTRIBUTION OF PROJECT COSTS AND CREDITS
Sebastian Municipal Airport
City of Sebastian, Florida
AIP Projects No. X26
Airport Access Road Improvements
DATE
PAYEE
DESCRIPTION OF CHECK
EXPENSES NO.
TOTALS
WorkltemOne
WorkltemTwo
WorkltemThree
WorkltemFour
WorkltemFive
7/26/13
AID
Engineering Design 85892
$41,475.00
$41,475.00
7/26/13
AID
Engineering Design 85892
$16,816.00
$16,816.00
8/30/13
AID
Engineering Design 86096
$12,156.00
$12,156.00
8/30/13
AID
Engineering Design 86096
$4,236.00
$4,236.00
9/06/13
Federal Ex.
Shipping 86172
$37.38
$37.38
Subtotal
TOTAL
$74,720.38
$74,720.38
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
1 s Quarter for 2014
Grant Number:
AIP10
Projects:
Improve Access Road — Airport Drive
Nominal Airport Submission:
_X— Project Status Summary (one form for each project included in the grant agreement.)
X_ Statement and Distribution of Project Costs or equivalent (cumulative)
X_ FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
X_ Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
All Change Orders, Work Authorizations/Scope Changes in addition to summary
irport ponsor Representative ADO Program Manager
Title
Date
Updated November 2006
Date
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
2" Quarter for 2014
Grant Number:
AIP10
Projects:
Improve Access Road —Airport Drive
Nominal Airport Submission:
X Project Status Summary (one form for each project included in the grant agreement.)
_X_ Statement and Distribution of Project Costs or equivalent (cumulative)
_X_ FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
_X_ Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
All Change Orders, Work Authorizations/Scope Changes in addition to summary
Airport Spobsor Representative
Title
Date
Updated November 2006
ADO Program Manager
Date
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
3rdQuarter for 2014
Grant Number:
AIP10
Projects:
Improve Access Road — Airport Drive
Nominal Airport Submission:
_X_ Project Status Summary (one form for each project included in the grant agreement.)
_X_ Statement and Distribution of Project Costs or equivalent (cumulative)
_X_ FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
_X_ Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
All Change Orders, Work Authorizations/Scope Changes in addition to summary
Airp Spponsor
'Representative
A'"i J ,L///C/✓fC/ '
Title T Ll
Date
Updated November 2006
ADO Program Manager
Date
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
4 Quarter for 2014
Grant Number:
AIP10
Projects:
Improve Access Road — Airport Drive
Nominal Airport Submission:
X_ Project Status Summary (one form for each project included in the grant agreement.)
XStatement and Distribution of Project Costs or equivalent (cumulative)
X__ FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
X_ Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
All Change Orders, Work Authorizations/Scope Changes in addition to summary
Airport Sponsor epresentative
�/CJZ_ l /JCIGIc/
Title
Date
Updated November 2006
ADO Program Manager
Date
OUTLAY REPORT AND REQUEST FOR REIMBURSEMENT
PAGE OF
FOR CONSTRUCTION PROGRAMS
OMB APPROVAL NO. 0348.0082
1 1 1 PAGES
I TYPE Of REQUEST
2. OASIS Of REDDEST
(See Instructions on back)
0 FINAL 0 PARTIAL
0 CASH 0 ACCRUAL
A FEDERAL SPONSORING AGENCY AND ORGANIZATIONAL ELEMENT TO
A FEDERAL GRANT OR OTHER
5 PARTIAL PAYMENT BEOUEST NO
WHICH THIS REPORT S SUBMITTED
IDENTIFYING NUMBER
Federal Aviation Administration - Orlando Florida
ASSIGNED BY FEDERAL AGENCY
AIP-3-12-0145-010-012
Full
5 EMPLOYER IDENTIFICATION
P RECIPIENTS ACCOUNT NUMBER
PERIOD COVERED BY THIS REQUEST
FROM IMmO, Ly. Yen) TO (MRFN, dq. 0.11
NUMBER
OR IDENTIFYING NUMBER
59-6000427
05/01/2014 07/30/2014
9. RECIPIENT ORGANIZATION
la PAYEE filthw nrcN re to of SenMadlermt,nen RM 31
Name: City of Sebastian
Name: Same
No. and Street:1225 Main Street
Na. and Street: Same
City. State and
City. State and
ZIP code: Sebastian, FL 329
ZIP Code: Same
11. STATUS
OF FUNDS
PROGRAMS FUNCTIONS ACTIVITIES
CLASSIFICATION
TOTAL
(a)
(b)
(c)
a. Administrative expense
S
S
S
S 0.00
0'00
I. Preliminary expense
0'00
c. Land, structures. right-of-way
11,187.36
11,187.36
d. Architectural engineering basic fees
0.00
e. Other architectural engineering fee
0.00
I. Project inspection fees
0.00
. Land development
0'00
I. Relocation expense
I. Relocation payments to indwiduals
0.00
and businesses
j. Demolition and removal
0.00
k. Construction and project improvement cast
9,720.00
9,720.00
I. Equipment
0.00
in. Miscellaneous cost
0.00
n. Total cumulative to date(sum of linesa thrum
20,907.36
0.00
0.00
20,907.36
a. Deductions for program income
0.00
F. Net cumulative to dale (line It minus line o)
20,907.36
0.00
0.00
20,907.36
q. Federal share to date
0.00
r. Rehabilitation grants (100% reimbursement)
0.00
s. Total Federal share (sum of lines q and 0
0.00
0.00
0.00
0.00
It. Federal payments previously requested
0,00
u. Amount requested for reimbursement
S
S
$
S 0.00
v. Percentage of physical completion of project
%
IN,
%
%
12. CERTIFICATION
SIGNATURE OF AUTHORIZED CERLIFYINDOFFIMAL
DATE REPORT SUBMITTED
a. RECIPIENT
certlly that m the best Grimy knowledge and
TYPED OR PRINTED NAME AND TITLE
TELEPHONE!Arei few. numOn,
belief the billed costs or disbursements are
end ulene�om
in accordance with the terms of the project
City of Sebastian
(772) 388-821
and that the reimbursement represents the
Federal share due which has not been
SIGN{rURE OF AUTHORIZED CERTIFY' D OFFICIAL
i
DATE SIGNED
previously requested and that an inspection
REPRESENTATIVE
/ ! <�.L 1
(.- J!�
has been performed and all work Is in
b.
OR PmgTEp xAMe 'o irtlE
TELEPHONE Wee rode. nusi
accordance with the terms Of the award.
CERTIFYING TO LINE ITVTYP
Nancy Veldt
me saiens'Pm
(772) 388-8231
AUTHORIZED FOR LOCAL REPRODUCTION eRAN.ARU run. Alyn., 1-11,
PREVIOUS EDITION USABLE Prescribed by OMB Circular A-102 and A-110
271-103
Page I— of —I—
STATEMENT
—
STATEMENT AND DISTRIBUTION OF PROJECT COSTS AND CREDITS
Sebastian Municipal Airport
City of Sebastian, Florida
AIP Projects No. x26
Airport Access Road Improvements
DATE
PAYEE
DESCRIPTION OF
EXPENSES
CHECK
NO.
TOTALS
WorkltemOne
WorkltemTwo
WorkltemThree
WorkltemFour
WorkltemFive
05/09/14
Mancil Const
Airport Or Const
87776
$9,720
$9,720
06/20/14
AID
Design Airport Drive
88008
$5,222.80
$5,222.80
06/20/14
AID
Design Airport Drive
88008
$5,964.56
$5,964.56
Subtotal
$20,907.36
$20,907.36
TOTAL
Frank Watanabe
From: Mark Jansen, PE <mjansen@aidinc.us>
Sent: Wednesday, December 10, 2014 7:33 AM
To: Frank Watanabe
Cc: Joseph Griffin; Michelle Stromberg; Nancy Veidt
Subject: RE: Sebastian Airport
Frank,
Here is my interpretation of the total budget. This basically shows 405k remaining for the building while maximizing
grants and matches. Let me know if you think otherwise as this is a series of formulas.
X26 Projects
Summary
12/9/2014
Budget
Building
Design
Road
Design
Road
Construction
Buildin
Construction
Total
Remaining
FAA
$600,000
1 $0
$89,215
$436,218
1 $0
$525,433
$74,567
FDOT
$600,000
$18,539
$2,348
$113,379
$202,810
$337,076
$262,924
City
$275,000
$18,539
$2,348
$51,304
$202,810
$275,000
$0
Totals
$1,475,000
$37,077
$93,910
$600,901
$405,620
$1,137,509
$337,491
Note: City portion includes 5% "Match" for design of road.
FDOT Road Grant
80%
80%/
20%
FDOT Building Grant
50%
50%/
50%
FAA Percentage
95%
AID Fees
Road Design
$87,124.48
Road Design Add 1
$6,786.00
Building Design
$37,077.28
Building Amount to
C&5
$5,000.00
-Mark
Mark C. Jansen, P.E. (FL), LEED BD+C
American Infrastructure Development, Inc.
37 N. Orange Ave., Suite 500, Orlando, Florida 32801-2459;
407.926.6611 (o), 321.695.5061 (m)
From: Frank Watanabe[mailto:FWatanabe@Cityof5ebastian.org]
Sent: Tuesday, December 9, 2014 1:48 PM
To: Mark Jansen, PE
Cc: Joseph Griffin; Michelle Stromberg; Nancy Veidt
Subject: RE: Sebastian Airport
Mark,
Thanks for the update. Please provide me with the following additional information:
• Copy of the original cost estimate by Mancil (date?)
• What is the original total budget approved?
• Are there differences in unit cost from the original to the Change Order No 1?
Thanks
Frank Watanabe
Public Works Director/City Engineer
City of Sebastian
(772)388-8228
From: Mark Jansen, PE fmailto:mjansen(daidinc.us]
Sent: Tuesday, December 09, 2014 11:46 AM
To: Frank Watanabe
Cc: Joseph Griffin; Michelle Stromberg; Nancy Veidt
Subject: Re: Sebastian Airport
Frank,
In summary, the 11/17 version showed AID's estimated unit prices to get you budget numbers. I put placeholders in there
while we were waiting for Mancil's to finalize the change order so we would generally know where we were. I apologize for
failing to do a better job explaining that. The prices have been updated in mancil's official change order. I think that may
explain
the deltas in the unit prices.
11/25 is their change order
11/17 is an estimate as described above
11/3 is also an estimate as described above
8/18 base bid cost you show below did not include piping the canal.
Keep in mind that on the 11/3 and 11/17, the yellow cells indicate "awaiting verification from Mancil's for unit price." Italic
and items starting with 1 xx are "added" items not included in original bid.
The change order bid prices are consistent with the original unit prices in the change order where applicable.
AID'S add services letter for $6,786 is attached.
Mark C. Jansen, P.E. (FL), LEED BD+C
American Infrastructure Development, Inc.
37 N. Orange Ave., Suite 500, Orlando, Florida 32801-2459;
407.926.6611 (o), 321.695.5061 (m)
From: Frank Watanabe <FWatanabe@CitvofSebastian.ore>
Sent: Monday, December 08, 2014 3:05 PM
To: Mark Jansen, PE
Cc: Joseph Griffin; Michelle Stromberg; Nancy Veidt
Subject: FW: Sebastian Airport
Mark,
Please review the attached spreadsheet from Mancil's dated 11/17 which I received from Jim and note my summary of
past cost estimates:
Date
Cost
Budget Total
1. 11/25/14
$620,148.00
$752,741.10 (Change Order No.1)
2. 11/17/14
$596,418.50
$833,496.10 Mancil's
3. 11/3/14
$603,330.00
$825,351.10 Mancil's
4. 8/18/14
$466,102.93
$831,701.10
Please let me know why the Change Order No.1 differs from the cost spreadsheet from Mancil dated 11/17?
Why does the total budget keep changing?
There are changes in unit cost items, such as:
"Remove existing pipe" from Change Order No.1 dated 11/25 to the Mancil's 11/17 (which matches 11/3)
"48" Optional pipe material" changes from $72 (demuck at $14.21) to $80 (which includes demuck)?
Here is what I have per our approved contracts:
Per our PO contracts AID= $124,201.76, Mancil's = $752,741.10 Total= $876,942.86
Add C&S contract = $512,968 + $876,942.86 = $1,389,910.86 < $1,475,000
There is still add-on for AID engineering cost ? Please email me this fee.
Once we clarify these differences and make sure total cost is sound and within budget, which I now believe we are ok, I
will issue the NTP
Thanks
Frank Watanabe
Public Works Director/City Engineer
City of Sebastian
(772)388-8228
From: Jim [mailto:iim(c)mancils.com]
Sent: Monday, December 08, 2014 10:49 AM
To: Frank Watanabe
Subject: RE: Sebastian Airport
Frank,
Please find attached bid tab of the project
Jim Barbieri
Mancil's Complete Sitework
0:(772)288-0951
From: Frank Watanabe(mailto:FWatanabe@CitvofSebastian.orgl
Sent: Wednesday, December 03, 2014 8:09 AM
To:'Rick Slone'; Mark Jansen, PE
Cc: Lm@mancils.com; Michelle Stromberg; Joseph Griffin
Subject: RE: Sebastian Airport
Rick,
Please note that we received this change order No.l. Let me review and get back with you all later this week on any
comments or questions. Please provide mean updated schedule as requested in our meeting by this week. At this
time, we have not released a "Notice to Proceed" on the construction. Since this has taken so long to obtain the change
order and not yet a schedule, I now have concerns with this project.
In addition, please copy all correspondence to Michelle Stromberg, new Airport Administrator since she will be assisting
me on this project.
Thank
Frank Watanabe
Public Works Director/City Engineer
City of Sebastian
(772)388-8228
From: Rick Slone [mailto:rsloneCalmancils.com]
Sent: Wednesday, December 03, 2014 6:55 AM
To: Frank Watanabe; Mark Jansen, PE
Cc: iim(a)mancils.com
Subject: Sebastian Airport
Good morning Mark & Frank,
I'm sending this out for Jim, He's PC is down
Please find attached Change Order # 1.
We are having issues with our server.
Please let me know you received this email.
Rick Slone
Mancil's Complete Sitework
772-288-0951(Office)
772-288-0983(Fax)
772-519-0003 (Cell)
rslone@mancils.com (Email)
OUTLAY REPORT AND REQUEST FOR REIMBURSEMENT
FOR CONSTRUCTION PROGRAMS
OMB APPROVAL NO. 0343-0002
PAGE DF
PAGES
I TYPE OF REQUEST
2. BASIS OF REQUEST
(See instructions on back)
0 FINAL 0 PARTIAL
0 CASH 0 ACCRUAL
S. FEDERAL SPONSORING AGENCY AND ORGANIZATIONAL ELEMENT TO
1 FEDERAL GRANT OR OTHER
5. PARTIAL PAYMENT REQUEST NO
WHICH THIS REPORT IS SUBMITTED
IDENTIFYING NUMBER
ASSIGNED BY FEDERAL AGENCY
S. EMPLOYER IDENTIFICATION
1 RECIPIENT 5 ACCOUNT NUMBER
PERIOD COVERED BY THIS REQUEST
NUMBER
OR IDENTIFYING XUMBER
FROM INenM, Ory, YNrl TO Ramm.. day par)
e RECIPIENT ORGANIZATION
ID, PAYEE FWAen chockis to be sent I dlf)ennt than item 91
Name:
Name:
No. and Street:
No. and Street'
City. State and
City. State and
ZIP Code:
ZIP Code:
11. STATUS
OF FUNDS
PROGRAMS FUNCTIONS ACTIVITIES
CLASSIFICATION
TOTAL
(a)
(b)
(c)
a. Administrative expense
S
S
S 0.00
I. Preliminary expense
0'00
c. Land. structures, right-of-way
0'00
d. Architectural engineering basic fees
0.00
e. Other architectural engineering fee
0'00
0.00
I. Project inspection lees
0.00
. Land development
IT Relocation expense
0.00
1. Relocation payments 10 Individuals
and businesses
0.00
j. Demolition and removal
0.00
k, Construction and project improvement cost
0.00
I. Equipment
0.00
m. Miscellaneous cast
0.00
IT Total cumulative t0 date(sum of lines a thru in
0.00
0.00
0.00
0.00
0. Deductions for program income
0.00
p. Net cumulative to date (line IT minus line o)
0.00
0.00
0.00
0.00
q. Federal share to date
0.00
r. Rehabilitation grants (100% reimbursement)
0.00
s. Total Federal share (sum of lines q and r)
0.00
0.001
0.00
0.00
I. Federal payments previously requested
0.00
u. Amount requested for reimbursement
$
S
$
S 0.00
v, Percentage 0f physical completion of project
%
%
as,
%
12. CERTIFICATION
SIGNATURE OF AUTHORIZED CERTIFYING OFFICIAL
DATE REPORT SUBMITTED
a. RECIPIENT
I certify thatto the best Of my knowledge and
TYPED OR PRINTED NAME AND TITLE
TELEPHONE Miter :006, number.
belief the billed Costs at disbursements are
and eannam.)
in accordance with the terms DI the project
and that the reimbursement represents the
Federal share due which has not been
SIGNATURE OF AUTHORIZED CERTIFYING OFFICIAL
DATE SIGNED
previously requested and that an inspection
has been performed and SII work Is in
accordance with the terms of the award.
b. REPRESENTATIVE
CERTIFYING TO LINE IIV
TYPED OR PRINTED NAME AND TITLE
TELEPHONE (Am rode. number.
and aYrenI
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM en GUY. 7-97)
PREVIOUS EDITION USABLE Prescribed by OMB Circular A-102 and A-110
271-103
11
INVOICE SUMMARY
NO. I
DEPARTMENT OF TRANSPORTATION, DISTRICT IV
ATTN: LAURIE MCDERMOTT, AVIATION COORDINATOR
IN ACCORDANCE WITH CHAPTER 332.006(6), F.S., THE JOINT PARTICIPATION AGREEMENT
DATED OCTOBER 31. 2012 BETWEEN FDOT AND THE
CITY OF SEBASTIAN
1225 MAIN STREET, SEBASTIAN, FLORIDA 32958
THE AGENCY INCURRED THE INDEBTEDNESS LISTED BELOW BETWEEN THE DATE OF
OCTOBER 31, 2012 THROUGH AUGUST 14, 2013
THIS INVOICE IS NOT FOR COSTS INCURRED ON A PREQUALIFIED JOINT PARTICIPATION AGREEMENT
TOTAL ESTIMATED PROJECT COSTS: $ 1,200,000.00
FRONT END FUNDED PROJECT: YES () NO (X) $
MAXIMUM DOT PARTICIPATION PER AGREEMENT: 50.0% $ 600,000.00
TOTAL ELIGIBLE PROJECT COST INCURRED TO DATE
FDOT PARTICIPATION IN ELIGIBLE COSTS INCURRED TO DATE
PREVIOUSLY BILLED:
THIS BILLING:
NET REQUEST FOR PAYMENT:
I CERTIFY T ATTIE AFORESAID LISTING IS TRUE AND MRI ..
M'FIN
APPROVED:
DIST. MULTI -MODAL PROG. MGR
DATE
APPROVED AS MEETING TERMS OF CONTRACT:
DISTRICT PROJECT MANAGER
DA
$ 75,215.86
$ 37,607.93
$ 0.00
$ 37,607.93
$ 37,607.93
CERTIFY UNDER PENALTIES OF P URY. TNATTIIE AGENCY HAS CONIFLL D
THE PROVISIONS OF THIS AGREEMENT
BY:�
/35l /9
FINANCE DIRECTOR J
DATE
FPN:
429695-1-94-01
DOT WPI NO.
N/A
DOT JOB NO.
N/A
CONTRACT NO.
AQT69
INSTRUCTIONS
Public reporting burden for this collection of information Is estimated to average 60 minutes per response, including time for reviewing instructions,
searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments
regarding the burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Office of
Management and Budget, Paperwork Reduction Project (0348-0004), Washington, DC 20503.
PLEASE 00 NOT RETURN YOUR COMPLETED FORM TO THE OFFICE OF MANAGEMENT AND BUDGET,
SENO IT TO THE ADDRESS PROVIDED BY THE SPONSORING AGENCY.
Please type or print legibly. Items 3, 4, 5, 8, 9. 10, 11sand 1 l are sell explanatory; specific instructions for other items areas
follows:
Item Entry
1 Mark the appropriate box. If the request is final, the amounts
billed should represent the final cast of the project.
2 Shaw whether amounts are computed an an accrued
expenditure or cash disbursement basis.
6 Enter the Employer Identification Number (EIN) assigned
by the U.S. Internal Revenue Service or F1 CE (institution)
code if requested by the Federal agency.
7 This space is reserved for an account number or other
identifying number that may be assigned by the recipient.
11 The purpose of vertical columns (a) through (c) is to
provide space for separate cost breakdowns when a large
project has been planned and budgeted by program,
function or activity. If additional columns are needed, use
as many additional forms as needed and Indicate page
number In space provided in upper right; however. the
summary totals of all programs. functions, or activities
should be shown in the *total' column on the first page.
All amounts are reported on a cumulative basis.
lie Enter amounts expended for such Items as travel, legal
fees, rental of vehicles and any other administrative
expenses. Include the amount of interest expense when
authorized by program legislation. Also show the amount
of interest expense on a separate sheet.
11b Enter amounts pertaining to the work of locating and
designing, making surveys and maps, sinking test holes,
and all other work required prior to actual construction.
11c Enter all amounts directly associated with the acquisition
of land, existing structures and related right-of-way.
11d Enter basic fees for services of architectural engineers.
11e Enter other architectural engineering services. Do not
include any amounts shown on line J.
fit Enter inspection and audit fees of construction and related
programs.
11g Enter all amounts associated with the development of
land where the primary purpose of the grant is land
improvement, The amount pertaining to land development
normally associated with major construction should be
excluded from this category and entered on line k.
11h Enter the dollar amounts used to provide relocation
advisory assistance and net costs of replacement housing
(last resort). Do not include amounts needed for
relocation administrative expenses; these amounts should
be included in amounts shown on line a.
ill Enter the amount of relocation payments made by the
recipient to displaced persons, farms, business concerns,
and nonprofit organizations.
ill Enter gross salaries and wages of employees of the
recipient and payments to third party contractors directly
engaged in performing demolition or removal of
structures from developed land. All proceeds from the
sale of salvage or the removal of structures should be
credited to this account; thereby reflecting net amounts if
required by the Federal agency.
Ilk Enter those amounts associated with the actual
construction of, addition to, or restoration of a facility.
Also, include in this category, the amounts for project
improvements such as sewers, streets, landscaping, and
lighting.
111 Enter amounts for all equipment, both fixed and
movable, exclusive of equipment used for construction.
For example, permanently attached laboratory tables,
built-in audio visual systems, movable desks, chairs,
and laboratory equipment.
l l m Enter the amounts of all items not specifically mentioned
above.
fin Enter the total cumulative amount to date which should
be the sum of lines a through on.
110 Enter the total amount of program income applied to the
grant or contract agreement except Income Included on
line j. Identify on a separate sheet of paper the sources
and types of the Income,
l l p Enter the net cumulative amount to date which should be
the amount shown on line n minus the amount on line o,
/1q Enter the Federal share of the amount shown on line p.
11r Enter the amount of rehabilitation grant payments made
to individuals when program legislation provides 100
percent payment by the Federal agency.
11t Enter the total amount of Federal payments previously
requested, if this form is used for requesting
reimbursement.
11u Enter the amount now being requested for
reimbursement. This amount should be the difference
between the amounts shown on lines s and I. If different,
explain on a separate sheet.
12a To be completed by the official recipient official who is
responsible for the operation of the program, The date
should be the actual date the form is submitted to the
Federal agency.
12b To be completed by the official representative who is
certifying to the percent of project completion as
provided for in the terms of the grant or agreement.
STANDARD FORM 271 (Rpv, 1-97) Back
•
INVOICE SUMMARY
NO.2
DEPARTMENT OF TRANSPORTATION, DISTRICT IV
AITN: LAURIE MCDERMOTT, AVIATION COORDINATOR
IN ACCORDANCE W ITII CHAPTER 332.006(6), F.S., THE JOINT PARTICIPATION AGREEMENT
DATED OCTOBER 31, 2012 BETWEEN FDOT AND THE
CITY OF SEBASTIAN
1225 MAIN STREET, SEBASTIAN, FLORIDA 32958
THE AGENCY INCURRED THE INDEBTEDNESS LISTED BELOW BETWEEN THE DATE OF
SEPTEMBER 29, 2013 THROUGH MARCH 25, 2014
'('HIS INVOICE IS NOT FOR COSTS INCURRED ON A PREQUALIFIED JOINT PARTICIPATION AGREEMENT
TOTAL ESTIMATED PROJECT COSTS: S 1,200,000.00
FRONT END FUNDED PROJECT: YES ( ) NO (X)
MAXIMUM DOT PAR FICIPATION PER AGREEMENT: 50.0%
TOTAL ELIGIBLE PROJECT COST INCURRED TO DATE
FDOT PARTICIPATION IN ELIGIBLE COSTS INCURRED TO DATE
PREVIOUSLY BILLED:
THIS BILLING:
NET REQUEST FOR PAYMENT:
[PXtIPYT Y THE APORESAN LI51ING ISTRUE AM1R COPP"
Rnn1
APPROVED:
DIST. MULTI -MODAL FROG. MGR
APPROVED AS MEETING TERMS OFCONTRACT:
DISTRICT PROJECT MANAGER
DATE
S 600,000.00
S 125,266.57
E 62,633.29
$ 37,607.93
S 25,02536
S 25,025.36
IMRTIFV UHOPRPPNALTIES OF PENURY. THAI 'I MAGESCY HAS CG WTHO
THE PROVISIONS OF THIS AGREFIAEN!
BY:
LW
FPN:
DOT WPI NO.
DOT JOB NO.
CONTRACT NO.
FINANCE DIRECTO
AT_
429695-1-94-01
N/A
N/A
AQT69
INVOICE SUMMARY
NO.3
DEPARTMENT OF TRANSPORTATION, DISTRICT IV
ATTN: LAURIE McDERMOTT, AVIATION COORDINATOR
IN ACCORDANCE WITH CHAPTER 332.006(6), F.S., THE JOINT PARTICIPATION AGREEMENT
DATED OCTOBER 31, 2012 BETWEEN FDOT AND THE
CITY OF SEBASTIAN
1225 MAIN STREET, SEBASTIAN, FLORIDA 32958
THE AGENCY INCURRED THE INDEBTEDNESS LISTED BELOW BETWEEN THE DATE OF
MARCH 26, 2014 THROUGH JULY 30, 2014
THIS INVOICE IS NOT FOR COSTS INCURRED ON A PREQUALIFIED JOINT PARTICIPATION AGREEMENT
TOTAL ESTIMATED PROJECT COSTS:
FRONT END FUNDED PROJECT: YES () NO (X)
MAXIMUM DOT PARTICIPATION PER AGREEMENT: 50.0%
TOTAL ELIGIBLE PROJECT COST INCURRED TO DATE
FOOT PARTICIPATION IN ELIGIBLE COSTS INCURRED TO DATE
PREVIOUSLY BILLED:
THIS BILLING:
NET REQUEST FOR PAYMENT:
,tmnrr nurr��Am UMNO uraWe Coa ,
wm,
APPROVED:
DIST. MULTI -MODAL PROG. MGR
DATE
APPROVED AS MEETING TERMS OF CONTRACT:
DISTRICT PROJECT MANAGER
DATE
Icsnnrv,moexrv+u.nevorrFxnmv,rw,r
m mo�aMSA�
$ 1,200,000.00
$ 600,000.00
$ 156,922.45
$ 78,461.23
$ 62,633.29
$ 15,827.94
$ 15,827.94
BY: jpl
AIRPORT MANAGER
BY:
$��4
ATE
FPN:
DOT WPI NO.
DOT JOB NO.
CONTRACT NO.
429695-1-94-01
N/A
N/A
AQT69
Quarterly Report:Q1
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
The Notice to Proceed was issued to the Contractor for the Airport Drive Construction however there impacts to the existing
airporUgolf course project limits which required redesign and modification. In addition, there needs to be a supplemental JPA
approved by City on 10/8 for the approved FAA funds not listed. The storage building is behind in schedule and permits.
Proiect Continuation
Provide any additional information about future action items, challenges, or changes to this project:
City will approve the Supplemental JPA on 10/8 and issue new NTP for contractor to start on the Airport Drive Construction.
Estimate the construction to be completed within the following quarter. The City has terminated the contract with C&S
consultants on the Storage Building and will proceed with in-house engineering to re -advertise the construction project for Jan
2015.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Consultant Invoices were submitted.
Quarterly Report:Q1
Sebastian Municipal Airport
Construct Building 425720-1
Obiectives
Provide current status of project and detail progress for this time period.
Design consultant submitted 95% final plans to the City and other agencies for permits. Fire permit required the need for
additional cost for fire suppression which exceeds the project budget. City is redesigning the hanger size to be able to
construction a new hanger within budget.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
Complete the design and permitting of the new hangar to proceed into construction.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
City received the latest invoice from the design consultant in late Sept and will submit into the JACIP system this week.
NATIO NAI R
AV I AT I❑ N I N 5 U R A N 0 E
Confirmation of Insurance Coverage
City of Sebastian
1525 Kautz Road, Suite 100
West Chicago, IL 60185
(800) 327-2222 1 fax: (866) 212-1654
www.nationair.com
Thank you for allowing NationAir to continue to serve your aviation insurance needs. This will confirm that
NationAir has procured coverage per your request as summarized below. Our invoice for the renewal
premium is enclosed.
Airport Liability
Expiring Policy Number:
AP023777813-04
Policy Period:
October 1, 2014 to October 1, 2015
Insurance Company:
AIG
Annual Premium:
$2,970.00+38.61 Florida Hurricane Fund = $3,008.61
Please call our office if you have any questions or if we may be of additional service. We appreciate your
business and look forward to serving you.
Prepared by Account Executive: Joan Perry
Contact Information: jperry@nationair.com
(800) 327-2222
Page 1 of I September 26, 2014
NationAir Aviation Insurance
SEND ALL OTHER CORRESPONDENCE TO
1525 Kautz Road, Suite 100
West Chicago, IL 60185
Phone: (800) 327-2222
Fax: (866) 212-1654
Website: www.nationair.com
Joe Griffin
City of Sebastian
1255 Main Street
Sebastian, FL 32958
Invoice # 53597
Page 1 of 1
Aa count Numbrf
Data
Cl -01
9/26/2014
Belente Due By
Entered By
10/15/2014
]HINK
Ameunt Peitl
Amount Due
$3,008.61
PLEASE SEND PAYMENTS TO:
NATIONAIR
P.O. Box 843342
Kansas City, MO 64184-3342
INCLUDE THIS ACCOUNT NUMBER ON YOUR CHECK
CITYOFS-01
(^ ^ " " ^AAAA ^ A" ^ Please send above porton of invoice with payment/ A A A A A A A A A A A A A )
Airport Liability PolicyNtimbec AP023777813-04 Effective: 10/1/2014 to 10/1/2015
Item # Trans Eff Date Due Date
127495 10/1/2014 10/15/2014
127496 10/1/2014 10/15/2014
9/26/2014
Trans
Description - -
RENB
Renewal Premium - Airport Liability
FHCF
Florida Hurricane Catastrophe Fund
Total Invoice Balance:
SEND PAYMENTS TO: NATIONA/R P.O. BOX 843342 KANSAS CITY, MO 64184-3342
AND INCLUDE THIS ACCOUNT NUMBER ON YOUR CHECK CITYOFS-01
City of Sebastian
53597 Due Date: 10/15/2014
$2,970.00
$38.61
$3,008.61
-A
Page 1 of 1
Frank Watanabe
From: McDermott, Laurie <Laurie.McDermott@dot.state.fl.us>
Sent: Friday, January 02, 2015 11:22 AM
To: Fernando Blanco; Alston, Sandra; Acuna, Priscilla; Steve Rocco; Gary Sypek; Menger, Eric;
John Wiatrak; Frank Watanabe
Subject: FW: Second Quarter Reports
Hello and Happy New Year.
Just a reminder that 2ntl quarter reports are due by January 7`h on all open contracts.
Thanks for your assistance.
Sincerely,
Laurie McDermott
Aviation Coordinator/office of Modal Development
Florida Department of Transportation, District 4
3400 West Commercial Blvd
Fort Lauderdale, FL 33309
Tel: (954)777-4497
Laurie.McDermott@dot.state.fl.us
From: McDermott, Laurie
Sent: Tuesday, December 16, 2014 8:43 AM
To: Clara Bennett; Fernando Blanco; Alston, Sandra; Acuna, Priscilla; Gary Sypek; Steve Rocco; Menger, Eric;
estokus(amartin.fl.us; John Wiatrak
Subject: Second Quarter Reports
The Second quarter of fiscal year 2014/15 will end December 31, 2014.
Please be sure your IPM checklist is up to date and invoicing is current.
Second quarter reports should be submitted no later than January 7, 2014.
You will need to submit a quarterly summary in JACIP for each of your open projects.
To access the quarterly report questions:
1. Select the project from the JACIP list
2. Select the JPM Tab
3. Select the IPM Checklist Tab
1
Quarterly Report:Q1
Sebastian Municipal Airport
Acquire Equipment 434545-1
Obiectives
Provide current status of project and detail progress for this time period.
Received all of our storm water maintenance equipment
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
None
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Submitted the final invoice in Sept 2014.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
PUBLIC TRANSPORTATION
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
Number 1
73500007
PUBLIC TRANSPORTATION
W11
Page 10r0
Financial Project No.:
Fund: DPTO
FLAIR Approp.: 088719
425720-1-94-01
Function: 637
FLAIR Obj.: 750004
(item -segment -phase -sequence)
Federal No.:
Org. Code: 55042010429
Contract No.: AR824
DUNS No.: 80-939-7102
Vendor No.: VF596000427008
CFDA Number.
CSFA Number:
55.004
THIS AGREEMENT, made and entered into this day of
by and between the STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION, an agency of the State of Florida,
hereinafter referred to as the Department, and City of Sebastian
202 Airport Drive East Sebastian, FL 32958
hereinafter referred to as Agency.
WITNESSETH:
WHEREAS, the Department and the Agency heretofore on the 8 th day of November . 2013
entered into a Joint Participation Agreement; and
WHEREAS, the Agency desires to accomplish certain project items as outlined in the Attachment "A" appended
hereto; and
WHEREAS, the Department desires to participate in all eligible items for this project as outlined in Attachment
"A" for a total Department Share of $ 1.220.000.00
NOW, THEREFORE THIS INDENTURE WITNESSETH: that for and in consideration of the mutual benefits to flow
from each to the other, the parties hereto agree that the above described Joint Participation Agreement is to be amended
and supplemented as follows:
1.00 Project Description: The project description is amended
Construct Hangars
RS U30.D]
PUBLIC TRANSPORTATION
6/11
Page 2 013
2.00 Project Cost:
Paragraph 3.00 of said Agreement is • increased O decreased by $ 650.000.00
bringing the revised total cost of the project to $ 1.525.000.00
Paragraph 4.00 of said Agreement is • increased O decreased by $ 520.000.00
bringing the Department's revised total cost of the project to $ 1.220.000.00
3.00 Amended Exhibits:
Exhibit(s) B & D of said Agreement is amended by Attachment "A".
4.00 Contract Time:
Paragraph 18.00 of said Agreement 12/31/2015 .
5.00 E -Verify:
Vendors/Contractors:
1. shall utilize the U.S. Department of Homeland Security's E -Verify system to verity the employment eligibility
of all new employees hired by the Vendor/Contractor during the term of the contract; and
2. shall expressly require any subcontractors performing work or providing services pursuant to the state contract
to likewise utilize the U.S. Department of Homeland Security's E -Verify system to verify the employment eligibility
of all new employees hired by the subcontractor during the contract term.
7zsaw rR
PUSDO TRANSPORTATION
6/11
Pape 3 of 3
Financial Project No. 425720-1-94-01
Contract No. AR824
Agreement Date
Except as hereby modified, amended or changed, all other terms of said Agreement dated 1 11812 01 3
and any subsequent supplements shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused these presents to be executed, the day and year first
above written.
AGENCY
City of Sebastian
AGENCY NAME
SIGNATORY (PRINTED OR TYPED)
SIGNATURE
TITLE
FDOT
See attached Encumbrance Form for date of Funding
Approval by Comptroller
LEGAL REVIEW
DEPARTMENT OF TRANSPORTATION
Gerry O'Reilly
DEPARTMENT OF TRANSPORTATION
Director of Transportation Development
TITLE
Financial Project No. 425720-1-9401
Contract No. AR824
Agreement Date
ATTACHMENT"A"
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
This Attachment farms an integral part of that certain Supplemental Joint Participation Agreement between
the State of Florida, Department of Transportation and City of Sebastian
202 Airport Drive East Sebastian, FL 32958
dated
DESCRIPTION OF SUPPLEMENT (Include justification for cost change):
Multi -Year Funding. This supplemental adds 2nd year of funding.
As Approved
1. Project Cost $875,000.00
As Amended
$1,525,000.00
Net Change
$650,000.00
Comments:
Page 1 of 2
As Approved
As Amended
Net
It.
Fund
DPTO
DPTO
DPTO
Department:
$700,000.00
$1,220,000.00
$520,000.00
Agency:
$175,000.00
$305,000.00
$130,000.00
Federal:
$0.00
$0.00
$0.00
Total Project Cost
$875,000.00
$1,525,000.00
$650,000.00
Comments:
Page 1 of 2
ATTACHMENT"A"
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
III. MULTI-YEAR OR PREQUALIFIED PROJECT FUNDING
If a project is a multi-year or prequalified project subject to paragraphs 4.10 and 17.20 of this agreement, funds
are programmed in the Departments Work program in the following fiscal year(s):
FY
Amount
2014
$700,000.00
2015
$520,000:00
Page 2 of 2
iSupplier Portal: View Invoices
CCPART Ar'.7 Jr T'ANSPORTATION
einvoicing
UNITED STnTLg -)F AMERICA
Home Orders/Grants Invoices
create Invoices View Invoices
Simple Search
Invoice Number
Invoke Amount From
Invoice Amount To
'N Navigator v� Favorites
Grant Number/PO Number 3-12-0145-010-201
Due Date From
Due Date To
Invoice Date From
Invoice Date To
Invoice
Number
301771
113
Invoice Date
28 -Aug -2014
20 -Aug -2014
Go .clear
Grant
IPO Number (Number
SOG120145010012 011345- .
SOG1201450103-12-0145-
010-2013
Invoice
Amount
100.00
350.00
tus
APPROVED.
PENDING
PAYMENT
APPROVED.
PENDING
PAYMENT
(Descripti)n
St. johns Permit
CAD Drawings -
Michelle 5[ramberg
Home OrdeMIGmnts
Invokes Home
Logout Preferences
Pnvacy Statement
Page I of I
Home Logout Preferences
Paid
(Type (Due Date Date View
Standard 30-NOV-2014 View
Standard 30 -Nov -2014 Vg
F Ex ort
Oepyrwhl IG 20na Oracle All nar'u �eservetl.
/nA HTML/OA.isp?page=/oracle/apps/pos/account/webui/PosA... 11/20/2014 —
Access Points
Access Point
Type of Access
Pivot Gates
1 Padlock
8,7,3 Swipe +Keypad
2 Padlock
10,20 Swipe
3
Swipe & Keypad
4,21 Keypad
4
Keypad
11 Combo
GC
Padlock
21 Gates Padlock
5
Padlock
2 Walk Through at Admin - unlocked
APP 5
Padlock
6
Padlock
1. 31 Access Points
7
Swipe & Keypad
2. Com Airport - 12 yr
3. No fees except for Swipe cards
4. Swipe cards + keypads
5. Must have second badge
8 Swipe & Keypad
9 Padlock
10 Swipe
11
Combo
12 Padlock
12b Padlock
14 Padlock
15 Padlock
16 Padlock
17 Padlock
18 Padlock
19 Padlock
20 Swipe
21 Keypad
22 Padlock
23 Padlock
APP 23 Padlock
Bin Gate Padlock
APP 28 Padlock
Walk thru at lift station - padlock
OUTLAY REPORT AND REQUEST FOR REIMBURSEMENT
PAGE OF
FOR CONSTRUCTION PROGRAMS
OMB APPROVAL NO. 034e-0002
PAGES
I TYPE OF REOUEST
2 BASIS OF REQUEST
(See instructions on back)
❑ FINAL ❑ PARTIAL
I] CASH ❑ ACCRUAL
a. FEDERAL SPONSORING AGENCY AND ORGANIZATIONAL ELEMENT TO
N. FEDERAL GRANT OR OTHER
5. PARTIAL PAYMENT REDDEST NO
WHICH THIS REPORT IS SUBMITTED
IDENTIFYING NUMBER
ASSIGNED BY FEDERAL AGENCY
6. EMPLOYER IDENTIFICATION
]. RECIPIENT S ACCOUNT NUMBER
PERIOD COVERED BY THIS REQUEST
NUMBER
OR IDENTIFYING NUMBER
FROM(MOnM, M,, yelp TO FMORA, JIg YSIq
9. RECIPIENT ORGANIZATION
IT PAYEE (MFM eh KY p I* be MvII &AMANO MUN, Rem 9)
Name:
Name:
No. and Street:
No. and Street
City, State and
City. State and
ZIP Code:
ZIP Code:
11. STATUS OF FUNDS
PROGRAMS FUNCTIONS - ACTIVITIES
CLASSIFICATION
(a)
(b)
(c)
TOTAL
a. Administrative expense
S
$
S
S 0,00
0.00
D. Preliminary expense
0.00
C. Land, Structures, right-ol-Way
0.00
C. Architectural engineering basic fees
0.00
e. Other architectural engineering fee
0.00
f. Project inspection fees
0.00
. Land development
0.00
h. Relocation expense
1. Relocation payments to Individuals
0.00
and businesses
j. Demolition and removal
0.00
R. Construction and project improvement cost
0,00
I. Equipment
0.00
m. Miscellaneous cast
0.00
0. Total Cumulative t0 date(Sum of lines a thru m
0,00
0.00
0,00
0.00
0. Deductions for program Income
0.00
G. Net cumulative to date (line n minus line o)
0.00
0.00
0.00
0.00
G. Federal share to date
0.00
I. Rehabilitation grants (100% reimbursement)
0.00
s. Total Federal share (sum of lines q and r)
0.00
0.00
0.00
0,00
L Federal payments previously requested
0.00
M Amount requested lot reimbursement
$
S
S
$ 0.00
v. Percentage of physical completion of project
%
S
%
%
12. CERTIFICATION
SIGNATURE OF AUTHORIZED CERTIFYING OFFICIAL
DATE REPORT SUBMITTED
a. RECIPIENT
1 cerllly that to the best of my knawied0e antl
TYPED OR PRINTED NAME AND TITLE
TELEPHONE (Area Fade, 1um0e1
belief the billed costs or disbursements are
and e:nmmn)
in accordance with the terms of the project
and that the reimbursement represents the
SIGNATURE OF AUTHORIZED CERTIFYING OFFICIAL
DATE SIGNED
Federal share due which has not been
previously requested and that an inspection
has been performed and all work i5 in
b. REPRESENTATIVE
TYPED OR PRINTED NAME AND TITLE
TELEPHONE (Arca rude, numbe,.
accordance with the terms DI the award.
CERTIFYING TO LINE 11V
are a.MT)
AUTHORIZED FOR LOCAL REPRODUCTION ITANDAN. Foe. an run. r-vn
PREVIOUS EDITION USABLE Prescribed by OMB Circular A-102 and A-110
271-103
INSTRUCTIONS
Public reporting burden for this collection of information is estimated to average 60 minutes per response, including time for reviewing Instructions.
searching existing data sources, gathering and maintaining the data needed. and completing and reviewing the collection of information. Send comments
regarding the burden estimate or any other aspect of this collection of Information, Including suggestions for reducing this burden, to the Office of
Management and Budget. Paperwork Reduction Project (0348-0004). Washington, OC 20503.
PLEASE 00 NOT RETURN YOUR COMPLETED FORM TO THE OFFICE OF MANAGEMENT AND BUDGET.
SEND IT TO THE ADDRESS PROVIDED BY THE SPONSORING AGENCY.
Please type or print legibly. Items 3, 4, 5, 8, 9, 10, 1 is and 1 l are self explanatory; specific instructions for other items areas
follows:
I Mark the appropriate box. If the request is final, the amounts
billed should represent the final cost of the project.
2 Show whether amounts are computed on an accrued
expenditure or ash disbursement basis.
6 Enter the Employer Identification Number (EIN) assigned
by the U.S. Internal Revenue Service or FI CE (institution)
code if requested by the Federal agency.
7 This space is reserved for an account number or other
Identifying number that may be assigned by the recipient.
11 The purpose of vertical columns (a) through (c) is to
provide space for separate cost breakdowns when a large
project has been planned and budgeted by program,
function or activity. If additional columns are needed, use
as many additional forms as needed and indicate page
number in space provided in upper right; however, the
summary totals of all programs, functions, or activities
should be shown in the 'total' column on the first page.
All amounts are reported on a cumulative basis.
11a Enter amounts expended for such items as travel, legal
fees, rental of vehicles and any other administrative
expenses. Include the amount of interest expense when
authorized by program legislation. Also show the amount
of interest expense on a separate sheet.
11b Enter amounts pertaining to the work of locating and
designing, making surveys and maps, sinking test holes,
and all other work required prior to actual construction.
l lc Enter all amounts directly associated with the acquisition
of land, existing structures and related right-of-way.
lid Enter basic fees for services of architectural engineers.
118 Enter other architectural engineering services. Do not
include any amounts shown on line d.
Ili Enter inspection and audit fees of construction and related
programs.
llg Enter all amounts associated with the development of
land where the primary purpose of the grant is land
improvement. The amount pertaining to land development
normally associated with major construction should be
excluded from this category and entered on line k.
1ih Enter the dollar amounts used to provide relocation
advisory assistance and net costs of replacement housing
(last resort). Do not include amounts needed for
relocation administrative expenses; these amounts should
be included in amounts shown on line a.
Ili Enter the amount of relocation payments made by the
recipient to displaced persons, farms, business concerns,
and nonprofit organizations.
11j Enter gross salaries and wages of employees of the
recipient and payments to third party contractors directly
engaged in performing demolition or removal of
structures from developed land. All proceeds from the
sale of salvage or the removal of structures should be
credited to this account; thereby reflecting net amounts if
required by the Federal agency.
11k Enter those amounts associated with the actual
construction of, addition to, or restoration of a facility.
Also. include in this category, the amounts for project
improvements such as sewers, streets, landscaping, and
lighting.
111 Enter amounts for all equipment, both fixed and
movable, exclusive of equipment used for construction.
For example, permanently attached laboratory tables,
built-in audio visual systems, movable desks, chairs,
and laboratory equipment.
11m Enter the amounts of all items not specifically mentioned
above.
l In Enter the total cumulative amount to date which should
be the sum of lines a through m.
fill Enter the total amount of program income applied to the
grant or contract agreement except income included on
line j. Identify on a separate sheet of paper the sources
and types of the income.
11 p Enter the net cumulative amount to date which should be
the amount shown on line n minus the amount on line a.
fill Enter the Federal share of the amount shown on line p.
lit Enter the amount of rehabilitation grant payments made
to individuals when program legislation provides 100
percent payment by the Federal agency.
lit Enter the total amount of Federal payments previously
requested, if this form is used for requesting
reimbursement.
fill Enter the amount now being requested for
reimbursement. This amount should be the difference
between the amounts shown on lines s and I. If different,
explain on a separate sheet.
12a To Be completed by the official recipient official who is
responsible for the operation of the program. The date
should be the actual date the form is submitted to the
Federal agency.
12b To be completed by the official representative who is
certifying to the percent of project completion as
provided for in the terms of the grant or agreement.
BTARDMB FORM 2711Rni 7971 Balk
Project Status Summary
Airport Improvement Program
Quarter: July — September 2013
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Completed bid documents and advertised bids for construction
services. Public bid opening conducted for both roadway and
storage building improvements which were rejected by the City
Manager.
The project is 18% design/construction and 3% total construction.
Special Circumstances: New bids were published on September 29, 2013 with closing
advertisement of November 15, 2013
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Project Status Summary
Airport Improvement Program
Quarter: October — December 2013
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Closed the bid documents for second advertisement and held
public bid opening for both the roadway and storage building
improvements. City Council award contracts for both contractors
and waiting return of executed contracts
The project is 33% design/construction and 6% total construction.
Special Circumstances: None
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
Project Status Summary
Airport Improvement Program
Quarter: January — March 2014
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter;
through the quarter; Include % of project physical
end of the quarter.
progress made
completion at the
City conducted a preconstruction meeting with both contractors for
the roadway and the storage building improvements. Mancil's
Contractor from Ft Pierce was selected for the roadway and C&S of
Orlando for the storage building improvement. Both start dates is
set for June 14, 2014, pending permit from SJRWMD. City started
to clear area for the contractor to mobilize equipment and material
for the construction staging.
The project is 51% design/construction and 8% total construction.
Special Circumstances: None
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Project Status Summary
Airport Improvement Program
Quarter: April — June 2014
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Revised the roadway and storage building design plans for final
100% construction documents, received the SJWRMD permit.
Issued the Notice to proceed to both contractors to submit schedule
and mobilize equipment.
The project is 68% design/construction and 10% total construction.
Special Circumstances: Permit modifications due to revisions to the final design
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
AIRPORT CAPITAL IMPROVEMENT PLAN
FY 2015 - 2019 (including FY 2014 for Reference)
Updated: 12/22/2014
SEBASTIAN MUNICIPAL AIRPORT (X26)
Fiscal
Project Total
Eligible FDOT
Sponsor
Year Description
Cost
Eligible Federal Share
Share (5%)
Share 5%)
Discretionary or
FDOT
Carryover
Entitlements
Apportionment
Total
$0
2014
Carryover Funds into 2014
ALP Drawing Update
$0
$0
$0
$0
$0
$0
$0
Example Taxiway Construction Project (Design and Permitting)
$0
$0
$0
$0
$0
$0
$0
Electrical Vehicle Charging Stations (2)
2014 Annual Total:
$0
$0
$0
$0
$0
$0
$0
2015
Carryover Funds into 2015
$0
example Taxiway Construction Project (BidlConshoctioNlnspection)
$0
$0
$0
$0
$0
$0
s0
2015 Annual Total:
$0
50
$0
$0
$0
$0
$0
2016
Carryover Funds into 2016
SU
Airport Drive West
2016 Annual Total:
$0
$0
50
So
$0
$0
2017
Carryover Funds into 2017
5n
2017 Annual Total:
$0
So
$0
$0
$U
$o
2018
Carryover Funds into 2016
50
2018 Annual Total:
$0
$0
$0
$0
$0
$0
2019
Carryover Funds Into 2019
So
2019 Annual Total:
$0
$0
$0
$0
$0
$o
Carryover Funds into 2020
$0
2014-2019 Grand Total:
EO
$0
$0
Sol
s0
$0
$0
N.uNcc�wL.wmeoxr
�nux.rinm.
REVISIONS
TAXIWAY D
CONCEPT PLAN
xxmumu
1
( Y ba�e'1 r o y xa
!¢ 6 V
1 ypLLLpr
WMI
i
n r
N 1 ONOO
O AYN "I
fv°jdt! SSJ»b,
°� /fg,1K%P?V
'JMYYLMIiwcl
wml.,ll.wv
,wonwiv�mtwnw
41
\ ^ f A+A • T
I
14
Al
Sebastian Municipal Airport PROJECT SUMMARY HANGAR C
Sebastian, FL
SE�TI�1
.b 6
MUNICIPAL AIRPORT
Original Project Summary
Item No. Item Description
Amount
1 A/E PERMITTING SERVICES
$
15,000.00
2 A/E CONSTUCTION ADMINISTRATION
$
74,084.00
3 ENGINEERING / ARCHITECTURE (A/E) DESIGN
$
157,848.00
4 CONSTRUCTION COST ESTIMATE
$
1,289,598.00
[COSTS TO DATE]
$
1,536,530.00
Revised Project Summary
Item No. Item Description
Amount
A/E PERMITTING SERVICES
$
15,000.00
A/E CONSTUCTION ADMINISTRATION
$
74,084.00
ENGINEERING / ARCHITECTURE (A/E) DESIGN
$
105,253.02
[COSTS TO DATE]
ENGINEERING / ARCHITECTURE (A/E) DESIGN
$
33,834.00
[FINAL DOCS AND BIDDING]
ADDITIONAL DESIGN SERVICES
$
72,006.50
CONSTRUCTION COST ESTIMATE
$
1,215,091.00
$ 1,515,268.52
1of1
Sebastian Municipal Airport PRELIMINARY HANGAR C
Sebastian, FL OPINION OF PROBABLE COST
Item Description Quantity Unit Unit Price Cost
Subtotal Building Construction $ 835,462.60
Subtotal Sitework Construction $ 170,829.00
Contractor's General Conditions 1 LS 15% $ 150,940.00
Subtotal Construction: $ 1,157,231.60
Contingency 1 LS 5% $ 57,859.40
TOTAL OPINION OF PROBABLE PROJECT COST: —$ 1,215,091.00
Notes:
A/E and Testing Fees are not included.
FFE (Furniture, Equipment, etc.) - Not Included
Does not Include Alternate Restroom Buildout & Alternate Office Buildout
This Opinion of Probable cost is based on 1,937 square feet of office shell space on the east side of
the hangar.
Trees, mulch, shrubs, and other landscaping shown in the plans to be self -performed by City and
are not included.
Turf Reinforcement for Grass Parking areas is not included.
The existing sliding gate will be removed and turned over the the City. No new fence is included.
1 of 1
Sebastian Municipal Airport PRELIMINARY HANGAR C
Sebastian, FL OPINION OF PROBABLE COST (HANGAR)
Item Description Quantity Unit Unit Price Cost
02- Site Work Landscaping, Irrigation
See Sitework breakdown
03 - Concrete (Building)
Slabs and footings
04 - Masonry
See Special Construction "13"
05 - Metals
See Special Construction "13"
06 - Wood and Plastics
See Special Construction "13"
07 - Thermal and Moisture Protection
See Special Construction "13"
O8 - Doors and Windows
Doors, Frames, Hardware
Windows (No window at Hangar bay)
09 - Finishes
Epoxy Flooring
Paint
Acoustical Ceiling (Office & Finished Spaces)
Restroom Floor Tile
Carpet & Vinyl Base
10 - Specialties
Signage (Interior Building)
Toilet Partitions
Accessories
Eyewash
11 - Equipment
Miscellaneous (Compresssor)
15,754 SF $ 6.00 $ 94,524.00
15,754
SF
$
0.60
$
9,452.40
15,754
SF
$
0.40
$
6,301.60
14,014
SF
$
1.50
$
21,021.00
15,754
SF
$
1.00
$
15,754.00
1,740
SF
$
3.00
$
5,220.00
290
SF
$
7.00
$
2,030.00
1,450
SF
$
3.30
$
4,785.00
1
LS
$
800.00
$
800.00
1
LS
$
6,000.00
$
6,000.00
1
LS
$
4,000.00
$
4,000.00
1
LS
$
600.00
$
600.00
1
LS
$
19,500.00
$
19,500.00
1oft
Sebastian Municipal Airport PRELIMINARY HANGAR C
Sebastian, FL OPINION OF PROBABLE COST (HANGAR)
Item Description Quantity Unit Unit Price Cost
12 - Furnishings
(By Tenant/Owner)
13 - Special Construction
Building shell and components, Masonry,
Metals, Wds. & Plas, Therm. & Moisture Prot.,
etc.
Building erection
Hangar Door (90' wide, includes material and
installation)
14 - Conveying Systems
Not Used
15 - Fire Sprinkler Protection
Not Used (No sprinkler system)
15 - Plumbing
Plumbing pncludes rough -in for future
restrooms in east lean-to)
15 - Mechanical
Mechanical
16 - Electrical
Electrical
15,754
SF
$
11.00
$
173,294.00
15,754
SF
$
6.00
$
94,524.00
1
LS
$
92,000.00
$
92,000.00
15,754 SF $ 2.00 $ 31,508.00
1 LS $161,200.00 $ 161,200.00
15,754 SF $ 5.90 $ 92,948.60
Subtotal Building Construction: $ 835,462.60
2 of 2
Sebastian Municipal Airport PRELIMINARY HANGAR C
Sebastian, FL OPINION OF PROBABLE COST (SITEWORK)
Item
Item Description
Quantity
Unit
Unit Price
Cost
01060
Control of Erosion, Siltation, and Pollution
1
LS
$
3,000.00
$
3,000.00
5-140-1
Remove 8" PVC Watermain
5
LF
$
25.00
$
125.00
5-140-2
Remove Bollard
1
EA
$
100.00
$
100.00
5-140-3
Remove Exist. Pavement
1,585
SY
$
8.00
$
12,680.00
Remove Exist. Gate, Key Pad, and Control Box
5-140-4
1
LS
$
500.00
$
500.00
(turn over to City)
P-152
Excavation and Embankment
1
LS
$
15,000.00
$
15,000.00
P-211
Lime Rock Base Course
495
CY
$
80.00
$
39,600.00
P-401
Bituminous Surface Course
270
TON
$
105.00
$
28,350.00
P-602
Prime Coat
575
GAL
$
5.00
$
2,875.00
D-701-1
15" RCP
160
LF
$
50.00
$
8,000.00
D-701-2
6" HDPE
134
LF
$
10.00
$
1,340.00
D-701-3
8" HDPE
123
LF
$
11.00
$
1,353.00
D-701-4
10" HDPE
36
LF
$
16.00
$
576.00
D-701-5
18" HDPE
130
LF
$
22.00
$
2,860.00
D-751-1
Airfield Inlet, Type ll
1
EA
$
4,000.00
$
4,000.00
T-904
Sodding
1,850
SY
$
2.50
$
4,625.00
FDOT 425
Type "C" Inlet
4
EA
$
2,100.00
$
8,400.00
FDOT 522
Concrete Sidewalk (4" Depth)
180
SY
$
30.00
$
5,400.00
FDOT 700
Handicap Parking Sign
1
EA
$
250.00
$
250.00
FDOT 700
Relocate Sign
1
EA
$
100.00
$
100.00
FDOT 700
Stop Sign and Right Turn Sign
2
EA
$
300.00
$
600.00
FDOT 710
Reflective Pavement Marking
250
SF
$
2.00
$
500.00
Concrete Wheel Stop
23
EA
$
80.00
$
1,840.00
Gate Valve
1
EA
$
300.00
$
300.00
4" DIP Sanitary Sewer
40
LF
$
50.00
$
2,000.00
Cleanout
2
EA
$
50.00
$
100.00
Oil/WaterSeparator
1
EA
$
10,000.00
$
10,000.00
6" PVC Sanitary
205
LF
$
35.00
$
7,175.00
11/2" Schedule 80 PVC Water Service
80
LF
$
21.00
$
1,680.00
11/2" RPZ
1
EA
$
1,500.00
$
1,500.00
Irrigation System
1
LS
$
6,000.00
$
6,000.00
Subtotal Sitework Construction: $ 170,829.00
1 of 1
Airport Improvement Program
Orlando Airports District Office
Grant Quarterly Report Checklist
Airport:
Sebastian Municipal Airport X26
Sponsor:
City of Sebastian
City, State:
Sebastian, Florida
Date of Quarterly Report:
1S, 2" , 3` and 4 for 2014
Grant Number:
AIP10
Projects:
Improve Access Road — Airport Drive
Nominal Airport Submission:
_X_ Project Status Summary (one form for each project included in the grant agreement.)
Statement and Distribution of Project Costs or equivalent (cumulative)
FAA Standard Form 271 for each drawdown in the quarter
Monthly Construction Progress and Inspection Report (Construction Projects Only)
Summary/Spreadsheet of Project Change Orders, Work Authorizations/Scope Changes
Photos, if applicable (start and end of quarter)
Summary of Test Results, if applicable
Moderate Airport Submission:
All information contained under Nominal Airport Submission
Breakdown of invoices included in Statement and Distribution of Project Costs
Weekly Construction Progress and Inspection Report (in lieu of monthly)
All Change Orders, Work Authorizations/Scope Changes in addition to summary
Airport Sponsor Representative ADO Program Manager
Title
Date
Updated November 2006
L0l5 l`/
Date
Project Status Summary
Airport Improvement Program
Quarter: April — June 2014
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Revised the roadway and storage building design plans for final
100% construction documents, received the SJWRMD permit.
Issued the Notice to proceed to both contractors to submit schedule
and mobilize equipment.
The project is 68% design/construction and 10% total construction.
Special Circumstances: Permit modifications due to revisions to the final design
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Project Status Summary
Airport Improvement Program
Quarter: January — March 2014
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
City conducted a preconstruction meeting with both contractors for
the roadway and the storage building improvements. Mancil's
Contractor from Ft Pierce was selected for the roadway and C&S of
Orlando for the storage building improvement. Both start dates is
set for June 14, 2014, pending permit from SJRWMD. City started
to clear area for the contractor to mobilize equipment and material
for the construction staging.
The project is 51 % design/construction and 8% total construction.
Special Circumstances: None
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Project Status Summary
Airport Improvement Program
Quarter: July — September 2013
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Completed bid documents and advertised bids for construction
services. Public bid opening conducted for both roadway and
storage building improvements which were rejected by the City
Manager.
The project is 18% design/construction and 3% total construction.
Special Circumstances: New bids were published on September 29, 2013 with closing
advertisement of November 15, 2013
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Project Status Summary
Airport Improvement Program
Quarter: October — December 2013
Airport: Sebastian Municipal Airport x26
City, ST: Sebastian, FL
Grant Number: AIP 3-12-0145-010-2012
Project Description: Improvement Access Road
Quarterly Progress: Include status of project at the start of the quarter; progress made
through the quarter; Include % of project physical completion at the
end of the quarter.
Closed the bid documents for second advertisement and held
public bid opening for both the roadway and storage building
improvements. City Council award contracts for both contractors
and waiting return of executed contracts
The project is 33% design/construction and 6% total construction.
Special Circumstances: None
Schedule Impacts: List any specific schedule impacts, especially if they impact project
completion and final closeout with the FAA.
None.
Frank Watanabe
From: Miguel.Martinez@faa.gov
Sent: Thursday, November 06, 2014 2:47 PM
To: Frank Watanabe
Subject: Quarterly Report
Frank,
I am missing several Quarterly Reports for the two open FAA grants. Part of the City's financial obligations of accepting a
grant is to provide the FAA (the Orlando ADO) with Quarterly Report. To date, the Orlando ADO has not received the
following Quarterly Reports:
AIP 06 —1'n, 2nd 3'a and 4`h quarter for 2013 and 2014
AIP 10 —1�, 2nd 3'a and 4th quarter of 2014
Failure to comply with the quarterly report would require that the City's Risk Assessment be elevated to moderate and
require additional documentation from the Authority.
Miguel A. Martinez
Program Manager
Orlando Airports District Office
407-812-6331, extension 123
37k
2,,)1 q5 -v16 `ZO l�
Quarterly Report:Q4
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Obiectives
Provide current status of project and detail progress for this time period.
'4pr�Jo7 1311e-1
Revising final plans. Received SJRWMD permit. Notice to Proceed to both contractors. Currently on hold for permit mod from
St. Johns
ProiectContinuation
Provide any additional information about future action items, challenges, or changes to this project:
none
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
\ Quarterly Report:Q3
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
(, lllj%ur /3l/�
Conducted pre -construction meeting with both construction firms; Mancil's of Ft. Pierce and US of Orlando. Both start dates
expected in June 14. Received permits from St. Johns
Proiect Continuation
Provide any additional information about future action items, challenges, or changes to this project:
none.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
Consultant engineering company, AID, has not submitted in this quarter. No construction by the two construction companies has
been performed.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Please upload JPM documents
Quarterly Report:Q1
Sebastian Municipal Airport
\ • Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
Public Open Bid conducted but bids were rejected by City Manager
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
New bid published 29 Sep 13 with closing on 15 Nov 13
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
N/A
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Quarterly Report:Q2
(3 Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
Bids closed, City Council awarded, awaiting return of executed contracts.
Proiect Continuation
Provide any additional information about future action items, challenges, or changes to this project:
none
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
Last submittal on 9/13/13. Reimbursement on 10/16/13. Awaiting construction startup for additional invoicing.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Please upload plans and bid documents.
Quarterly Report:Q1
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
objectives
Provide current status of project and detail progress for this time period.
The Notice to Proceed was issued to the Contractor for the Airport Drive Construction however there impacts to the existing
airport/golf course project limits which required redesign and modification. In addition, there needs to be a supplemental JPA
approved by City on 10/8 for the approved FAA funds not listed. The storage building is behind in schedule and permits.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
City will approve the Supplemental JPA on 10/8 and issue new NTP for contractor to start on the Airport Drive Construction.
Estimate the construction to be completed within the following quarter. The City has terminated the contract with C&S
consultants on the Storage Building and will proceed with in-house engineering to re -advertise the construction project for Jan
2015.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? Yes
If no, please explain why no invoices have been submitted in the last 90 days:
Consultant Invoices were submitted.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Please upload project schedule
Quarterly Report:Q1
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Obiectives
Provide current status of project and detail progress for this time period.
JPA approved by Council on 10 October 2012. Sent to FDOT for execution.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
N/A
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
New Project
Comoliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
12#2
Quarterly Report:Q2
0 Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
Received executed JPA. Consulting with engineers for production plan and bid.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
Will be submitting for FAA portion of project before 1/21/13.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
New project --have received no invoices from vendors.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Quarterly Report:Q3
Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
rT11-��
Working with consulting engineer, AID, to develop plan. Engineer has done physical inspection and provided preliminary
drawings for proposal purposes.
Project Continuation
Provide any additional information about future action items, challenges, or changes to this project:
FAA participation has not been applied for at this time.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
No invoices have been submitted for payment by vendor(s)
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken:
Quarterly Report:Q4
' Sebastian Municipal Airport
Improve Access Road (Capacity) 429695-1
Objectives
Provide current status of project and detail progress for this time period.
Notice of Invitation to Bid published. Pre -Bid conference scheduled for 6 July 13. Bid close and opening scheduled for 23 July
13.
ProiectContinuation
Provide any additional information about future action items, challenges, or changes to this project:
Part of this project is FAA participation. Application for AIP funding will be made on 26 July 13. Anticipate Council approval of
construction contract eady September 13.
Invoices
Have you submitted an invoice to FDOT in the last 90 days? No
If no, please explain why no invoices have been submitted in the last 90 days:
No invoices have been submitted as of this date by consulting engineer.
Compliance Review
Project is in compliance: Yes
If no, describe corrective actions(s) to be taken: