HomeMy WebLinkAboutCSA-18 SW Management Plan Update - StonecropCITY OF SEBASTIAN, FLORIDA
WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
MBV ENGINEERING, INC.
1835 201h Street
Vero Beach, FL 32960
Work Authorization No: CSA -18 (MBV 190070)
Project Identification: Stormwater Management Plan Update - Stonecrop
IT IS AGREED to undertake the following work in accordance with the provisions of the MBV
Engineering, Inc. Master Agreement entitled Non -Exclusive Continuing Professional Services Agreement
for Engineering Dated July 12, 2017.
Description of Assignment:
As per our coordination, the City of Sebastian is looking to have the Stormwater Management Plan
updated for the Stonecrop basin area in conjunction with the FEMA grant application requirements.
Work Scope:
Task l: Preparation of an H&H (Hydrology & Hydraulics) study of approximately 120 nodes for
the Stonecrop basin, to include:
• Assistance with estimating the Finished Floor Elevations within the basin
• Pre and Post Developed length of flood duration determination
• Estimate of repair/ replacement cost for roadways per FDOT Guidelines
• Model the following storm events:
0 25 year- 24 hour and 72 hour
0 100 year - I hour, 24 hour, and 72 hour
Task 2: Preparation of a response to both the FEMA Environmental & Engineering comments
Task 3: Preparation of an aerial map showing all drainage improvement activities, including the
beginning/end coordinates in decimal degree format
Task 4: Preparation of a ground disturbance map showing the total area of ground disturbance in
square feet and vertical depth in feet. Include the coordinates in decimal degree format of
the exact location of all areas of ground disturbance and staging areas
Task 5: Contingency for additional responses
Deliverables: H & H Study, Response to FEMA comments, Aerial Map, and Ground Disturbance Map
- Response to FEMA engineering comments to be no later than 30 days upon authorization
- Response to FEMA environmental comments to be by 2/22/19.
Basis of Compensation/Period of Services:
The above referenced Professional Engineering Services for CSA 18 will be performed for a fee not to
exceed the below breakdown of fees:
Task I:
$
6,500
Task 2:
$
500
Task 3:
$
1,250
Task 4:
$
1,250
Task 5:
$
5 000
Total $14,500
AGREED:
ENGINEERING CONSULTANT:
ax"��ate: 02/19/2019
Aaron Bowles, P.E.
MBV Engineering, Inc.
Attest:
anette Williams, MMC, City Clerk
CITY OF SEBASTIAN:
,,
Date �
l Ce
urfisle
City Manager
Approved as to Form and Content for
Reliance by the City of Sebastian Only:
J .Stoke�ttorney