WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
Work Authorization No: #CSA-7
Project Identification: City of Sebastian - Roadway Improvements/Asphalt Overlay (Ocean Cove
Street, Cavern Terrace, and Schooner Lane)
Description of Assignment:
Schulke, Bittle & Stoddard, LLC will provide Inspection Services for the asphalt overlay and milling
project (Ocean Cove Street, Cavern Terrace, and Schooner Lane).
See detailed Scope of Work (Exhibit A).
Deliverable and Fee:
4.0 Construction Inspections
See detailed Fee Schedule (Exhibit B)
Period of Services: 7-day project duration.
AGREED:
Engine ing sultant::
/�✓ Data: Id h 1
Schulke. Biltld Stoddard. LLC
Atte'
J nee Hams, MC, City Clerk
T.R.` $4,583.50 (Estimated Fee)
City ebastian/:
< (/ Date:
au Carlisle, City Manager = _
Approved as to Form and Content for -
Reliance by the City of Sebastian Only:
Jim—SRfkes, ity Attorney _ _
SCOPE OF WORK— EXHIBIT A
General Descrl ttion
Schulke, Bittle &Stoddard, LLC will provide Inspection Services for the asphalt overlay and milling project
(Ocean Cove Street, Cavern Terrace, and Schooner Lane).
Construction Inspections
4.0 Construction Inspections
A. Construction Inspection (as required / requested)
a. Review project specifications and attend required pre -construction meetings (as
necessary).
b. Inspect adequacy and progress of construction in accordance with bid specifications.
Prepare inspection reports.
c. Attend / witness required tests. Review other test results.
d. Review pay requests.
e. Coordinate (as necessary) and attend on -site construction meetings, final inspections! walk
—thru(s). Prepare punch list.
Page 1 of 1
FEE SCHEDULE — EXHIBIT B
SBS will be compensated with payment from the Client the following estimated amounts:
Section Description Amount
Phase II Construction Administration
4.0 Construction Inspections T.R."
Estimate Fee: $4,583.50
Services are estimated on a per hour basis, based on four (4) days base reclamation and three (3) days paving.
• Pre -Construction Meeting
2.5 hours
• Base reclamation:
4 days x 4 hours = 16 hours
• Paving:
3 days x 9 hours = 27 hours
• Final Inspection/Punchlist:
3 hours
Total:
48.5 hours
Fee estimate: 48.5 hours x $85/hour =
$4,122.50
Mileage: 450 miles" @ $.58/mi. _
$261.00
Other reimbursement expenses =
$200.00JEstimatel
$4,583.60
•T.R.: Time Rate based on 7-day project duration
- The actual amount may vary depending on the proficiency of the contractor, actual duration of
construction, or other factors.