HomeMy WebLinkAboutCSA-9 Cemetery Road (complete)CITY OF SEBASTIAN, FLORIDA
WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
Work Authorization No: #CSA-9
Project Identification: City of Sebastian — Roadway Improvements/Asphalt Overlay (Cemetery
roadway Improvements and Improvements to other streets in the City of Sebastian)
Description of Assignment:
Schulke, Bittle & Stoddard, LLC will provide Inspection Services for the asphalt overlay, milling
and paving project(s).
See detailed Scope of Work (Exhibit A).
Deliverable and Fee:
4.0 Construction Inspections
See detailed Fee Schedule (Exhibit B)
Period of Services: Up to 8-day project duration.
AGREED: I
Engineering CopsII �ltt:
Hate: I Z
Schulke, Slide & Stoddard, LLC
Att t
anefte Williams, , ityerk
T.R.• $8,670.00 (Estimated Fee)
City of ebasti / //a'',_�
L / Date: �zwo
P Carlisle, City Manager
Approved as to Form and Conte or
Reliance by a City eb s' nly:
My Ano , fr., City may
SCOPE OF WORK —EXHIBIT A
General Descrip%on
Schulke, Bit0e 8 Stoddard, LLC will provide Inspection Services for the asphalt overlay, milling and
paving project(s).
Construction Ins ections
4.0 Construction Inspections
A. Construction Inspection (as required / requested)
a. Review project specifications and attend required pre -construction meetings (as
necessary).
b. Inspect adequacy and progress of construction in accordance with bid
specifications. Prepare inspection reports.
c. Attend / witness required tests. Review other test results.
d. Review pay requests.
e. Coordinate (as necessary) and attend on -site construction meetings, final
inspections / walk—thm(s). Prepare punch list.
Scope of Work
It is anticipated that the inspections services required will include:
a. MIII/Pave Inspections: Ranger Const. 1 day, + Precon 1 day, + 1 day,
Not to exceed 3 days
b. FDR Inspections: Asphalt Pavino Svstems 5 days, + Precon 1 day, + 1 day,
Not to exceed 7 days
c. Cemetery Road Inspections. Tim Rose Const. 2 days, + Precon 1day, + stabilized subgrade &
base rock insp. 2 days, milling +1 day, + 1day,
Not to exceed 7 days
Total up to and not to exceed 17 days
Page 1 of 1
FEE SCHEDULE —EXHIBIT B
SBS will be compensated with payment from the Client the following estimated amounts:
Section Description Amount
4.0 Construction Inspections T.R.*
Estimate Fee: $8,670.00
Services are estimated on a per day basis, based on up to 8 days.
Scope of Work
It is anticipated that the inspections services required will include:
a. Mill/Pave Inspections: Ranger Cons. 1 day, + Precon 1 day, + 1 day,
Not to exceed 3 days
b. FDR Inspections: Asphalt Paving Svstems 5 days, + Precon 1 day, + 1 day,
Not to exceed 7 days
c. Cemetery Road Inspections: Tim Rose Const. 2 days, + Precon 1day, +stabilized subgrade &
base rock insp. 2 days, milling +1 day, + 1day,
Not to exceed 7 days
Total up to and not to exceed 17 days
Fee Estimate
• Each day (average) is assumed to be 6 hours
• Daily rate computed at: 6 x $85/hr= $510.00
• Fee estimate: 17 days x $510 = $8,670.00
*T.R.: Time Rate based on 17-day project duration
- The actual amount may vary depending on the proficiency of the contractor, actual
duration of construction, or other factors.
Page 1 of 1