Loading...
HomeMy WebLinkAboutADDENDUM #2 ITB - 21-08 WITH AMENDED SOWPROCUREMENT DIVISION 1225 Main Street, Sebastian, FL 32958 ADDENDUM #1 ITB 21-08 CDBG HOUSING REHABILITATION PROJECT FOR 6 SINGLE- FAMILY HOME UNITS *This Addendum MUST be acknowledged on page 18 of the ITB Document* Date: May 12, 2021 Solicitation Due Date: Wednesday, May 19, 2021 @ 4:00 PM EST TO ALL PROSPECTIVE PROPOSERS: For the above referenced project, take note of the following revisions, additions, deletions, clarifications, and questions/answers etc. relative to the ITB, which in accordance with the Contract Documents shall become a part of and have precedence over anything shown or described otherwise. Revisions The following responses are from questions posed during the mandatory site visit held on April 29, 2021. ITB Addendum #1: As it stands there was one scope of work addendum (see the attached and descriptions below): -Line item 2a: shutter locations and count adjusted to actual affected openings. Contractor Request #1: Participating contractors made the request, in an attempt to provide the best bid and price development that they are allowed to make follow-up contact with homeowners and additional site visits to each project. It is recommended that as a best practice, this request is granted. Contact Michelle Faulkner for homeowner contact information mfaulkner@cityofsebastian.org or 772-388-8220 Questions concerning this ITB should be emailed no later than Friday, May 7, 2021. All questions and communication regarding this ITB shall be directed ONLY to the Contact Person at lfrazier@cityofsebastian.org Contact by a Bidder (or anyone representing a Bidder) regarding this ITB with the City Council or a City employee/representative other than the point of contact listed above, is grounds for disqualification. Additions A complete statewide W/MBE listing can be accessed via the following web link: https://osd.dms.myflorida.com/directories. All other documents, specifications, drawings, terms and conditions remain the same. END OF DOCUMENT 1 City of Sebastian CDBG HOUSING REHABILITATION PROGRAM WORK WRITE-UP/BID/CONTRACT FORM-AMENDED OWNER: ADDRESS: 125 Midvale Ter. Sebastian, FL 32958 PHONE #: Email: DATE: March 2021 Home Built in 1996. ➢ * Lead Base Paint Safe Construction Actions Do Not Apply: ➢ ACM Actions May Apply: ➢ Mold Actions May Apply *This unit was constructed prior to 1979: Take Notice of any material that may contain Regulated Asbestos Containing Material (RACM), Lead Based Paint (LBP) or Mold and follow all safe LBP and ACM recommended actions for safe repairs and/or disposal. If there are not attachments pertaining to RACM, LBP, or Mold it is not reasonable to assume that no actions are required. Note System Description of Work Location Price Contractor Initials A. REHABILITATION Special attention should be directed to all contractor obtained LBP/ ACM/Mold reports regarding Lead Base Paint, Asbestos, and/or Mold. Any recommendations included in the reports regarding such material shall become part of the Work. Unit N/A B. SITEWORK Rehabilitation of unit shall include as applicable: 1. Re- connects all existing TV & Phone Jacks. Install 911 addressing as required. 2. Disconnect and re-connect to community water/sewer systems if required by code or specification within this document. 3. Demolition and safe, legal, disposal of all materials, removal of all construction and replacement debris. All/Site $ : THIS PAGE MUST BE INCLUDED WITH THE BID FOR IT TO BE VALID All work to be performed in a workmanlike manner, in accordance with the Sebastian-CDBG Work Write Up Specifications, Florida Building Code, local codes, and manufacturer’s specifications. The contractor shall be responsible for the repairs and/or reinstallation of mater ials/equipment/fixtures damaged or removed due to any work item contained herein. Contractors shall properly dispose of all fixtures, materials and other items removed from the dwelling unless otherwise specified herein. Bid will be accepted on the TOTAL BID submitted, and all items must be cost itemized in the space provided or the bid will be rejected. This house may or may not require the homeowner to vacate the premises during the construction period. The period for Construction shall be 90 Calendar days (Mon-Sun) from the date of contract acceptance, execution and Established Notice to Proceed date. This document may not be altered in any manner. The scope of work set forth in this document may not be changed without the written consent of Guardian CRM, Inc. under direct authorization from the City of Sebastian and/or its official representatives. I hereby certify that I am licensed by the State of Florida, Department of Business and Professional Regulation, and that I am eligible to participate in the City of Sebastian CDBG program. I also agree that change orders above the original contract amount shall only be paid for with CDBG funds to correct documented code violations or to meet Section 8 Housing Quality Standards. Change orders must be approv ed by the homeowner or his/her representative, the contractor, and local government CDBG Program Administrator prior to any initiation of work based on that change order. Contractor’s Name (Print Name): Contractor's Signature: Contractor's Address: Contractor's Phone Number: 2 City of Sebastian CDBG: Scope of Services SCOPE OF WORK (“SOW”) (Work Listed Below) NOTICE TO BIDDING GENERAL CONTRACTORS No contractor shall, without prior written approval from the Housing Specialist or CDBG Program Administrator, deviate from any product recommendations listed within this Scope of Work (SOW). A notice of “or equal” exchange shall be provided to the Inspector within forty-eight (48) hours of the proposed “or equal” substitution. This notice shall contain: 1) The names of both the SOW recommended product and proposed substitute product specification 2) Comparable manufacturer specifications list, included but not limited to price, warranty information, consumer review reports 3) Any additional information requested by the Sebastian CDBG Program Administrator or its agents. 4) All bids to include the repair/repaint to match existing, all damaged (interior/exterior surfaces, i.e., plaster, stucco, Tile, or any other material), walls, ceilings, ECT… affected by construction. 5) The contractor will provide all material and shall be responsible for covering all homeowner belongings, including flooring that cannot be moved during rehabilitation: this is not the owner’s responsibility: Daily clean-up within and around the home is required. 6) All measurements and material will be the responsibility of the contracting firm: substituting items to upgrade cabinet heights is prohibited. 7) All change orders must comply with the project budget, included allotted contingency, and be approved by the Sebastian CDBG Program Administrator or Project Manager prior to any change order work can begin. 8) Profit and overhead shall only be included in the specified line item. Other line items shall only include material, and labor cost. 9) Where the prime contractor of record elects to pull “combo” permits, i.e. where the roof, HVAC, or other such discipline permits are attached to the primary construction permit and not pulled on an individual discipline basis, payment draws must be billed on two separate draw requests: the first half at 50% project completion and the final 50% at the final closeout draw. The final 50% must be accomplished with the final permit showing that all combo disciplines have passed final building department inspection. Failure to provide any required notification will result in a violation of the terms and conditions of the SOW and Work Rehabilitation Contract and a loss of payment on the substituted product if it is not replaced with the SOW specified product. Approval will NOT be granted under any circumstance on or after the fact basis. NOTE: Signature required for acknowledgment of Notice to Bidding General Contractors. Printed Name Signature Date 1. General Construction and Operational: 1a. Profit and Overhead: ➢ The contractor shall include all profit and overhead in this line item: Profit and overhead shall be inclusive of all costs not directly related to material and labor (i.e. travel, supervision, sub/supplier meetings, etc.) NOTE 1: The contractor shall include all profit and overhead on its specified line item under the Applicant (Owner) and Contractor Contract page. Profit and overhead shall be inclusive for all costs not causally related to material and labor (i.e., travel, supervision, sub/supplier meetings, etc.). Do not include any profit or overhead costs in each individual item. NOTE 2: The Profit and overhead can only be billed in two draw requests; the first half at 50% completion and the final 50% at the final closeout draw. 1b. Manuals and Specifications: ➢ The contractor shall supply, at the time of the final CDBG Program inspection, all manufacturer manuals and specification booklets/packets for all supplied and installed products listed within the Scope of Work. Failure to do so will result in a failed final CDBG Program Inspection. o To Include all applicable Plans, Drawings, and Permits, & approved building department docs $ N/A 1c. General Construction and Operational: ➢ The contractor shall be responsible for and provide all applications, surveys, permits, plans, engineering, or other required federal, state, and local documentation. NOTE 1: No profit and/or overhead shall be included in this line item. o To Include all applicable Plans, Fees, Engineering, Drawings, Permitting, etc., $ 3 2. Exterior Rehabilitation: Windows and Doors: 2a. Window and Door Shutters: ➢ Prepare the surface around all applicable exterior windows as listed below (Front-3 Openings; Right-3 Openings; Rear-2 Openings; Left-4 Openings) to accept new Miami Dade or Florida product approved or equal hurricane impact rated accordion, panel, or roll-down shutter units as indicated below. All permanent set components including but not limited to screws, embedded anchor bolts, threaded cones, metal shields, headers and sills (tracks) must be weatherized and/or protected against corrosions and integrity contaminations. New accordion shutter units shall be a minimum 22 gauge corrugated, galvanized aluminum, with a mill finish and include all required attachments for proper and code compliant mounting. All products must meet or exceeds wind-borne debris impacts and wind load tests of Miami-Dade Building Code standard and/or Florida Building Code Standard. Shutters shall be mounted in a manner to ensure proper connection, coverage, and protection of each window opening and be installed to meet the manufacturer’s specifications. Installation shall also include all required permits, additional anchoring, or framing to allow for complete and compliant installation. Any damage caused by the installation process should be prepared and patched to match exterior walls. (Unit size & dimensions to be determined by contracting firm). NOTE 1: Any minor repairs and/or replacements to window encasements, exterior sills, etc…shall be included in this bid. NOTE 2: Contractor shall submit Dade County or equal Florida product approval stamped by the building Department of jurisdiction, with this projects close-out package. NOTE 3: All shutter units must meet the FBC HVHZ for Indian River County and/or minimum ASTM 1986-1996. o Front Elevation Windows (2-Accordion Shutter Sets and 3 arch panels) $ o Right Elevation Windows (3- Accordion Shutter Sets) $ o Rear Elevation Windows (2-Accordiom Shutter Sets) $ o Rear Elevation Doors (1-Roll Down Shutter Sets over French Door) $ o Rear Elevation Doors (2-Roll Down Shutter Sets over Slider Doors) $ o Left Elevation Windows (4- Accordion Shutter Sets) $ 2b. Entry/Exit Doors: ➢ Remove the existing primary entry/exit doors (1 unit at the front elevation and 1 unit at the rear elevation) and install new, hurricane impact rated, energy efficient (for the southern region) door in the listed location(s). The installation shall include jambs, preparation a sufficient door buck to accommodate the new door, wood casing, and install a new white pre-hung fiberglass Hurricane Impact rated, energy efficient door. (Door size & dimensions to be determined by contracting firm); Installation to include all required permits, additional anchoring, framing, hardware, components, and tap cons (TAP CONS MUST BE WHITE) to ensure proper and complete installation to current Florida Building Code. Door installation shall include keyed (alike) entry lockset with lever handle (both sides): “Schlage”, Flair F51 and matching deadbolt or approved equal, deadbolt keyed one side to the lock set, preinstalled peephole, vinyl bubble weather-stripping, and aluminum threshold. NOTE 1: Where a landing is required according to code. In absence of a landing, Contractor shall construct a concrete landing in front of the door as required by code, (or where a landing exists, contractor shall re-construct/modify the existing landing in order to meet code). NOTE 2: Contractor shall submit Dade County or Florida Building Code hurricane impact product approval stamped by the building Department of jurisdiction, with this projects close-out package. Door assembly shall meet Dade County or Florida Building Code product approval without using interior slide bolts. o Front-Primary Entry/Exit Door (1- 1/4 Light Unit with impact sidelight) $ o Rear Entry/Exit Door (1- Six Panel Unit) $ 4 3. Interior Rehabilitation: Flooring & Doors 3a. Interior Flooring (Vinyl): ➢ Remove and properly dispose of the existing floor covering and base molding in the areas of the home listed below. Make all appropriate modifications to prepare the underlying floor (including the application of a surface prep primer) to accept new vinyl plank flooring and baseboard. Scrape and clean the floor to ensure that it is free of all debris and protrusions. Repair (with like code/compliant materials) and patch all cracks and uneven sub-floor leveling in all affected areas to ensure a smooth uniform, surface. Install new waterproof, low gloss, stain resistant, textured, straight edge, medium width, indoor vinyl plank flooring and new 3-1/4” white (pre-painted) baseboard in the areas listed below. The vinyl flooring shall be a minimum 2.0mm in thickness, with a minimum 2.8mil wear layer or equivalent in quality. If not self-adhering, where required, product should be installed with manufacturer approved mastic and/or underlayment. Vinyl planks shall be “Style Selections”, “Peel & Stick” or equal, and contain a no-wax pre-finish. Installation to include threshold strips at all exposed joints between rooms and/or at door openings. Provide shoe molding and paint to match other finishes where applicable. Owner will select “standard solid and/or wood” color and pattern from contractor’s supply samples. o Entry Foyer: (Floor Prep and Vinyl Plank Installation) $ o Living/Dining Room: (Floor Prep and Vinyl Plank Installation) $ o Master BR: (Floor Prep and Vinyl Plank Installation) $ -END SOW- 5 ------------------------------------------------------------------ EXISTING DWELLING FOOTPRINT --------------------------------------------------------------- ------------------------------------------------------------------ EXISTING DWELLING FOOTPRINT --------------------------------------------------------------- **SPECIAL NOTES** All questions regarding scope of work intent shall be directed to: Antonio Jenkins Antonio.jenkins@guardiancrm.com 863-899-6695 Any and all products or services included in this scope of work shall be installed to the manufacture’s specifications and in compliance with all applicable City Ordinances, Health Department, NEC, and/or Florida Building Codes. All NOA product numbers can be found at www.miamidade.gov/buildingcode/pc-search_app.asp. All products specified can be found at. www.homedepot.com, www.lowes.com, or other retail outlets where such products are sold: OFFICIAL USE ONLY DATE SUBMITTED: DATE ACCEPTED: BID OPENED BY: WITNESSED BY: DATE OPENED: TIME: WORK WRITE-UP PREPARED BY: Antonio Jenkins of Guardian CRM Date: March 2021 REQUIRED ADDENDUM PAGE(S) TO FOLLOW 6 Applicant (Owner) and Contractor Price Agreement This contract is solely for the benefit of the parties named below, and no enforceable right or cause of action shall accrue hereunder to or for the benefit of any entity or individual not a named party hereto. CONTRACTOR: I, (the contractor) have read in its entirety, and understood and agree with all of the terms, and conditions contained within this contract and SOW documents. Contractor’s Name (Print): Title: Contractor’s Name (Signature): Date: Company Name: Phone: Position/title/relation to Contractor (if not the Contractor: ENTER FINAL TOTAL BID IN THE PRIC BOX BELOW Total Aggregate Labor and Material Cost: ------------→$ Total Profit and Overhead: --------------------------------→ $ Grand BID Total For: 125 Midvale Ter. ----------------------→ $ OWNER: I/we, the listed owner(s)/applicant(s), have read in its entirety, and understood and agree with all of the terms, and conditions contained within the SOW documents, and intend to select this contractor to complete the work identified in this estimate. My/Our signature below reflects my understanding and acceptance of the aforementioned scope of work with a total project cost of $ : (handwritten by owner/applicant). I also understand and accept the possibility that this initial total project cost can change (increase or decrease) if unanticipated labor or materials changes are required for compliance with any applicable building codes or deemed necessary by the CDBG Program Administrator. Any additional charges (increase or decrease) must be requested by the contractor in writing, submitted to the housing team for review, and must receive written approval from the CDBG Housing Program Manager BEFORE the additional or reduced services are to be performed. 7 “ATTACHMENT A” CITY OF SEBASTIAN CDBG HOUSING REHABILATATION PROGRAM Subcontractor and Permit Listing List all subcontractors that will be used for the work completed on this property: Failure to complete this Exhibit may result in this bid being considered incomplete and ineligible for award. SUBCONTRACTING FIRM NAME SUBCONTRACTING FIRM PHONE # 1. 1. 2. 2. 3. 3. 4. 4. 5. 5. 6. 6. 7. 7. 8. 8. 9. 9. 10. 10. List all permits that will be required for the work completed on this property: Failure to complete this Exhibit may result in this bid being considered incomplete and ineligible for award. REQUIRED PERMITS PRINT NAME OF ENTITY RESPONSIBLE FOR PERMIT 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Contractor’s Name (Print Name): Contractor's Signature: Title of signatory: