HomeMy WebLinkAbout07 - Alternatives Development and CIP PrioritizationCity of Sebastian Stormwater Master Plan Update
7 Alternatives Development and CIP Prioritization
7.1 Previously Identified CIP Projects
Many Capital Improvement Program projects were identified in previous Master Plan updates and the full scope
and budget estimates for the projects were sometimes unclear. Some of the projects are currently included in the
City's Capital Improvement Program for the Stormwater Fund, and for those the scope and status of the projects
were reviewed with City staff and evaluated against current modeling results to determine if they should continue
to be included in the CIP program. Table 7-1 shows the previously identified projects that were eliminated from
the CIP program or replaced with a new or modified project scope.
Table 7-1. Previously Identified CIP Projects Eliminated or Replaced
Elkcam, George,
Repair and/or Replace Seawalls in the
Schumann
Seawall Elkcam Canal, George Lake, Schumann
Lake
Repair/Replace
Identified in 2018 SWMP, no description. Not
$16,000,000 shown in current CIP -it appears this project
was replaced with the project below.
This is to address major improvements to
Major Canal the canals. Sizable amounts are being Current CIP shows $500k/year from FY 21-25,
$2500
Improvements programmed for each year so that portions ,,000 funded by Discretionary Sales Tax. Replaced
of the work can be initiated. with CIP Project Nos. 4-10.
Schumann Pipe Identified in 2018 SWMP, Completed in 2019-
Lining Slip lining from Schumann Lake to Elkcam $200,000 2020 FY.
Drainage improvements including
driveways, swales, road crossing
Pelican Island Identified in 2018 SWMP, Completed in 2019-
replacements and repaving. Drainage $475,000
Place Drainage 2020 FY.
repairs were completed in order to extend
the longevity of the road repaving work.
Due to erosion of the side slopes, this ditch
is difficult to maintain and needs to be
improved. The system drains the entire
central section of the City and therefore is
critical to maintain flow and avoid flooding.
Stonecrop
The project has been redesigned for open
Drainage Ditch
conveyance, versus piping, which
substantially reduces the estimated costs.
A FEMA Hazard Mitigation Grant is being
pursued to provide 75% of the expected
costs. Stormwater Funds of $215,000 are
being allocated for the grant matching
amount.
Blossom Ditch
No description
Pipe
Identified in 2013 SWMP (Bevan & Laconia
culverts) @ $1 M. Shown in current CIP at $860k
FY20.
Project removed from CIP list because it is
currently being bid by the City. The project is a
replacement of the Laconia culvert only with a
$860,000 12x3' CON/SPAN bridge, with reduction of
channel cross section and concrete armoring
from Laconia to Stonecrop for stability.
Identified in 2004 SWMP as 100LF of 48" RCP
$1,000,000 @$43k. Identified in 2013 SWMP @$1M, no
description. Replaced with CIP Project No. 27.
www.arcadis.com 106
City of Sebastian Stormwater Master Plan Update
Table 7-1. Pre viousiy Identified CIP Projects Eliminated or Replaced
Identified in 2018 SWMP, Developer of adjacent
Empress Canal
property has agreed to install a CON/SPAN
No description
$250,000
bridge with the construction of the development.
Piping
Therefore, the repair was removed from the
City's CIP plan.
Shown as twin 36" culverts in 2013 MP @
Landsdowne
No description
$178,000
$100k. Identified in 2018 SWMP, no description.
Box Culvert
Project removed because modeling showed it
would not result in significant improvement.
Identified in 2013 SWMP as Rosebush Terrace
Pipe (2-48" RCP @ $100k). Identified in 2018
Rosebush Box
No description
$242,000
SWMP, no description. Project removed
Culvert
because modeling showed it would not result in
significant improvement.
This is a pinch point on a main ditch. The
existing road crossing pipes are
Identified in 2013 SWMP as 42"x72" box culvert
Tulip Box
undersized due to minimal road coverage
@$100k. Identified in 2018 SWMP, no
Culvert
over the pipes and need to be replaced. It
$232,000
description @$232k. $232,000 shown in FY22
is recommended that the replacement be
CIP. Replaced with CIP Project No. 15.
accomplished with a CON/SPAN open flow
a
design to enhance conveyance.
Albatross Box
No description
$178,000
Identified in 2018 SWMP, no description. Not in
Culvert
current CIP. Replaced with CIP Project No. 16.
This is a main ditch pinch point and it
needs to be replaced with a CON/SPAN
Identified in 2018 SWMP, no description
Bayfront Box
open flow design. This will prevent the
$178 ,000
@$178k. $178,000 shown in FY23 CIP.
Culvert
existing pipe to become plugged with
Replaced with CIP Project No. 17.
debris, which causes the existing ditch to
overflow into residential properties
Benedictine
No description
$1,515,000
Identified in 2018 SWMP, no description. Not in
Ditch Piping
current CIP. Replaced with CIP Project No. 18.
Bryant/Friar
Identified in 2018 SWMP, no description. Not in
Court Retention
No description
$315,000
current CIP. Replaced with CIP Project No. 19.
Pond
Oyster Point Installation of catch basin in front of the
Drainage Box FDOT outfall
Hardee Dam
RNo description
Retrofit Gates
Potomac Ditch
No description
Piping
Potomac Baffle
Retrofit for Filter No description
$100,000 Identified in 2018 SWMP, Project completed.
$150,000 Identified in 2018 SWMP, no description. Not in
current CIP. Replaced with CIP Project No. 20.
Identified in 2013 SWMP, as Potomac Ave
$393,000 Lateral Pipe @$200k. Completed in 2016-2017
FY.
Identified in 2018 SWMP, no description. City
$60,000 removed project from CIP list. Existing Baffle
www.arcadis.com 107
City of Sebastian Stormwater Master Plan Update
Table 7-1. Pre viousiy Identified CIP Projects Eliminated or Replaced
CIP Project Description Estimated Notes
Name Cost I
Box is functioning well and mostly in dry
conditions.
Davis Street Identified in 2018 SWMP, no description. Not in
Baffle Retrofit for No description $60,000 current CIP. Deleted per City staff. The site is
Filter currently utilizing a generation 1 Baffle Box.
Rosebush New Stormwater Pond $315,000 Identified in 2018 SWMP. Replaced with CIP
Retention Basin Project No. 22.
Indian River Realign Mulligan Pipe, Baffle Box at
Drive Drainage Southern Outfall, Baffle Box at Jackson $1,000,000 Identified in 2013 SWMP, no description. Not in
current CIP. Replaced with CIP Project No. 23.
Improvements Outfall/clear outfall area
7.2 Current and Proposed CIP Projects
The following is an updated list of proposed CIP projects identified through the modeling work in this Master Plan,
those included in prior Master Plan updates and those identified through discussions with City staff. The goal is to
produce a 10-year CIP program with the most feasible schedule and strategy to fund those improvement projects
with the highest priority and the greatest benefits to the City. The H&H Model was used to evaluate various CIP
projects and develop initial recommendations to address drainage issues and reduce surface flooding for the
25yr-24hr design storm event. See Section 3.7 for a detailed explanation of H&H modeling results. The CIP
projects were evaluated based on surface flooding reduction, open channel flooding reduction, and cost
effectiveness. Design and implementation of the CIP projects should include a review of available survey data,
system conditions, and constructability.
Table 7-2. Current and Proposed CIP Projects
i Shown in current
1 Stormwater Equipment equipment and trucks used in the operation $878 500 CIP, $309,000 from
and maintenance of the Stormwater System FY21 to 25
based on their expected useful service lives.
Stormwater Heavy
Heavy Equipment replacements for the
Shown in current
2
Equipment
Stormwater Maintenance Program. $119,000
CIP, $595,000 from
Replacements include:
FY21 to 25
Reconstruction of stormwater swales in ROW
Shown in current
3 Roadway Swale Work
areas in conjunction with road resurfacing $600,000
CIP, $60,000/year
and reconstruction projects.
Harbor Point Waterway
Dredging and disposal of 3 ft (46,900 CY) of
Future CIP, beyond
4 and Collier Waterway
sediment from approximately 10,550 LF of
$10,987,265
10-year planning
North Improvements
trapezoidal open channel (12' bottom width,
horizon
4:1 side slopes), clear & grub, regrade, and
www.arcadis.com 108
City of Sebastian Stormwater Master Plan Update
Central Collier Waterway
Improvements - North
Section
Central Collier Waterway
Improvements - South
Section
Schumann Waterway
Improvements
Table 7-2. Current and Proposed C/P Projects
sod approximately 211,000 SF of side slope
area.
Clearing and grubbing 20' either side of City
drainage ROW lines over approximately
8,550 LF of canal banks, demolition and
reconstruction of existing dock structures and
fences, abandon existing bulkheads in place,
installation of approximately 8,550 LF of vinyl
sheetpile bulkhead (20 ft panel length) w/ $27,130,362
24x24" concrete cap on water side of existing
bulkhead, dredging 3' of sediment from
approximately 4,270 LF of canal, regrading
and resodding of approximately 171,000 SF
of canal easement area (20 ft behind
bulkhead).
Clearing and grubbing 20' either side of City
drainage ROW lines over approximately
11,350 LF of canal banks , demolition of
existing dock structures and fences,
installation of temporary sheeting where
needed for stability, removal of of
approximately 5,700 LF of existing seawalls
and disposal of transite bulkhead panels,
installation of approximately 5,770 LF of vinyl
sheetpile bulkhead (20 ft panel length) w/
24x24" concrete cap, dredging of
approximately 5,770 LF of canal, regrading
and resodding of approximately 230,800 SF
of canal easement area (20 ft behind
bulkhead and slope on Stormwater Park
property).
Clearing and grubbing 20' either side of City
drainage ROW lines over approximately
12,200 LF of canal banks , demolition of
existing dock structures and fences,
installation of temporary sheeting where
needed for stability, removal of
approximately 12,200 LF of existing seawalls
and disposal of transite bulkhead panels,
installation of approximately 12,200 LF of
vinyl sheetpile bulkhead (20 ft panel length)
w/ 24x24" concrete cap, dredging of
approximately 6,100 LF of canal, regrading
and resodding of approximately 244,000 SF
$21, 585, 297
$39,156,096
Future CIP, beyond
10-year planning
horizon
Future CIP, beyond
10-year planning
horizon
Future CIP, beyond
10-year planning
horizon
www.arcadis.com 109
City of Sebastian Stormwater Master Plan Update
8 Schumann Lake
Improvements
9 Joy Haven Waterway
Improvements
Table 7-2. Current and Proposed C/P Projects
of canal easement area (20 ft behind
bulkhead).
Not included in this project is a new culvert at
Empress Avenue at the canal to allow
continuous flow between North and South
portions, which is going to be completed by a
developer as they develop the property on
the East.
Clearing and grubbing 20' either side of City
drainage ROW lines over approximately
5,300 LF of lake banks, demolition of existing
dock structures and fences, installation of
temporary sheeting where needed for
stability, removal of approximately 3,500 LF
of existing seawalls and disposal of transite
bulkhead panels, installation of approximately
5,300 LF of vinyl sheetpile bulkhead (20 ft
panel length) w/ 24x24" concrete cap, no
dredging of lake, regrading and resodding of
approximately 106,000 SF of lake easement
area (20 ft behind bulkhead).
Clearing and grubbing 20' either side of City
drainage ROW lines over approximately
7,400 LF of canal banks , demolition of
existing dock structures and fences,
installation of temporary sheeting where
needed for stability, removal of approximately
2,500 LF of existing seawalls and disposal of
transite bulkhead panels, installation of
approximately 7,400 LF of vinyl sheetpile
bulkhead (20 ft panel length) w/ 24x24"
concrete cap, dredging of approximately
3.700 LF of canal, regrading and resodding of
approximately 148,000 SF of canal easement
area (20 ft behind bulkhead).
Future CIP, beyond
$13,195,257 10-year planning
horizon
Future CIP, beyond
$23,774,172 10-year planning
horizon
Removal of approximately 14,800 LF of
existing bulkheads, installation of Future CIP, beyond
Collier Waterway South approximately 14,800 LF of vinyl sheetpile
10 $51,091,662 10-year planning
Improvements bulkhead (20 ft panel length), dredging and
horizon
vegetation removal of approximately 7,400 LF
of canal.
11 Ocean Cove Drainage Reconstruction of approximately 2,000 LF of $571,182 Identified in 2018
Repair trapezoidal ditch between Crystal Mist and SWMP, no
www.arcadis.com 110
City of Sebastian Stormwater Master Plan Update
Table 7-2. Current and Proposed CIP Projects
Carnival Terrace from Clearbrook 5t to description L$278k.
Periwinkle to stabilize side slopes and Shown at $300k in
maintain conveyance capacity. FY24 CIP
Desilt culvert, clear vegetation over 0.25 ac,
excavate 3 feet (approximately 3,200 CY)
Day Drive Retention Area and regrade approximately 0.80 ac Current CIP shows
12 Restoration (175'x425') retention pond and drainage $1,570,614 $240,000 FY21 CIP
swale to design grades to restore proper
retention volume.
Removal and disposal of approximately 100
LF of existing metal bulkhead and concrete
cap, installation of approximately 100 LF of
13 Concha Dam Repair
metal sheetpile bulkhead (20 ft panel length)
$365,199
w/ 24x24" concrete cap w/ weir, regrading
and resodding of approximately 800 SF of
canal easement area (20 ft behind bulkhead).
Currently in design.
Sliplining of existing culvert pipes rather than
14 SWMS Pipe Lining
open cut replacement to reduce cost and
$200,000
disturbance.
Existing twin 36" culverts in Stonecrop Ditch
at Tulip Dr. (just E of 798 Tulip Dr.) to be
changed to a 4' x 7' concrete box culvert to
15 Stonecrop Ditch - Tulip
improve capacity (14.1 SF flow area
$239,230
Culvert Replacement
increased to 28 SF). This will match the
culvert capacity at Albatross assuming
Project Number 16 and 17 are completed
(culverts downstream of Tulip culvert)
Existing 54" culvert in Stonecrop Ditch at
Albatross Terrace Oust W of 787 Albatross
Stonecrop Ditch -
Terrace) to be changed to a 4' x 7' concrete
16 Albatross Culvert
box culvert to improve capacity (15.9 SF flow
$174,375
Replacement
area increased to 21 SF). This will match the
culvert capacity at Bayfront Terrace assuming
Project Number 17 is completed (culvert
downstream of Albatross culvert)
Existing twin 40" culverts in Stonecrop Ditch
at Bayfront Terrace Oust W of 789 Bayfront
Stonecrop Ditch -
Terrace) to be changed to a 4' x 7' concrete
17 Bayfront Culvert
box culvert to improve capacity (17.4 SF flow
$824,663
Replacement
area increased to 28 SF) which is similar to
the proposed Laconia St CON/SPAN 12ft x
3ft bridge (30SF). This project would also
Current CIP shows
$250k FY25
www.arcadis.com 111
City of Sebastian Stormwater Master Plan Update
Table 7-2. Current and Proposed C/P Projects
include regrading and armoring of 657tt open
channel from Bayfront Terrace to Laconia St.
Increase the conveyance capacity of the
Benedictine Area Stormwater Network:
Replace existing twin 36" culverts at Barber
St crossing South of intersection with Rolling
Benedictine Area Culvert
Hill Dr, Dredging and expanding the existing
18
open channel from Barber St crossing and
$636,163
Improvements
the Rolling Hill Drive crossing, replace
existing 36" culvert at Rolling Hill Drive Oust N
of 414 Rolling Hill Dr.), replace existing 24"
culvert at Benedictine Terrace, replace
existing twin 24" culverts at Coverbrook Lane.
Construct new approximately 1.0 ac retention
pond in the property just N of 105 Friar Ct.,
Bryant/Friar Court
appears to be a Park property. Regrade
19 Retention Pond
perimeter swales if needed to drain to
$282,512
retention pond. There is some modeled
flooding in the area - minor regrading may
help to focus the stormwater in the park area.
Currently has wood panels acting as the
Hardee Dam Retrofit
gates. These have been leaking beneath the
20 Gates
dam and the dam will eventually have to be
$25,000
replaced. Per City staff, the concrete is still in
ok condition, stoplogs need replacement.
Approximately 2.3 ac vacant City -owned
21 Surrey Terrace Retention
property S of 737 Surrey Terrace available to
$779,055
Basin
create an additional retention basin to help
with flooding in this area.
Approximately 2.5 ac vacant City -owned
22 Rosebush Retention
property E of 768 Newhall Terrace available
$837,040
Basin
to create an additional retention basin to help
with flooding in this area
Remove existing outfall pipe sections in
manhole area, install new precast concrete 4'
diameter manhole, install approximately 80
23 Coolidge Outfall
LF of A2000 pipe, install inline tide valve and $73,309
Improvements
manatee guard on new outfall pipe. Grout fill
and abandon in place remaining existing
outfall pipe sections under Mulligan's building.
Blossom Ditch Drainage
24
Dredge Blossom Ditch and create positive
$1,684,839
Improvements
drainage in the ditch and in the connecting
www.arcadis.com 112
City of Sebastian Stormwater Master Plan Update
Table 7-2. Current and Proposed CIP Projects
pipes from the N alleviating flooding along
Lanco Ave and Blossom Dr. 2006
Construction Plans developed but not
constructed. Add 12'x24' NSBB to outfall for
quality.
Add a culvert crossing at Fordham St to allow
flow to travel north to twin ditches, includes
25 Drainage Improvements at Hazel and Lloyd St regrading open channels and upsizing the $755,939
downstream culverts from Fordhams St to
Twin Ditches
The stormwater pumps are not currently
26 Stormwater Park operated using the Float system and $50,000
Operation therefore do not operate during wet weather
events. Repair controls.
Modify the control structure. Currently the
Stonecrop ditch enters the retention area, at
elevations 7.38ft and 7.62ft, two 60inch
culverts. The compound weir dimensions are
27 Stonecrop Retention Area summarized below: 2.16ft wide at elevation $100,000
6.557ft and 18ft wide at elevation 9.067ft. The
weir elevations prevent free discharge from
the Stonecrop Ditch. Add inline tide valves on
the two 60" pipes under Stonecrop Dr.
Total Estimated Cost $197,686,732
7.2.1 Cost Estimate Criteria
A detailed cost estimate was prepared for each proposed CIP project, including a project location map, quantity
takeoffs, contingency allowances, and notes referencing calculation assumptions and cost sources. Copies of the
estimates are included in Appendix I.
7.3 CIP Prioritization Process/Tool
The method for prioritization of maintenance issues was presented in Section 6. CIP prioritization follows a
similar methodology but is more detailed and results in a more thorough triple bottom line (TBL) type cost -benefit
analysis that considers economic, social and environmental effects. Upon identifying a CIP need, the project
priority should be determined by the City Engineer. Issues that without capital improvement pose a safety hazard
or create a condition that prohibits the proper function of the SWMS should be prioritized over aesthetic or
preventative projects. The amount of time required to address CIP projects ranges from a few weeks to months or
even years depending on the severity, complexity, and priority of the project. In certain more complex emergency
www.arcadis.com 113
City of Sebastian Stormwater Master Plan Update
cases, temporary resolutions should be presented as a stop -gap measure to address public safety or functional
issues while a more permanent resolution is determined.
The CIP Priority scoring uses a simple calculation to weight the importance of a proposed project based on
economic, social and environmental criteria. For each of those three criteria, a criticality score and project
effectiveness score is determined through a series of scored queries and an overall percentage of total category
score is calculated to determine its priority. CIP projects having the highest overall percentages are the highest
priority projects. In the CIP Priority calculation, the score weighting was as shown in Figure 7-1.
Economic
0.28
0.32
Social
0.30
0.32
Environmental
0.42
0.36
TOTAL
1.00
1.00
Figure 7-1. CIP Priority Criteria Weighting
Once the proposed CIP projects shown in Table 7-2 were identified, scoped, and cost estimates were prepared, a
CIP Priority scorecard was prepared for each of them to determine their overall priority ranking. An example of a
project scorecard is shown in Figure 7-2. A summary of the final priority scoring is shown in Figure 7-3, and a
graph of the final Criticality vs. Effectiveness scoring is shown in Figure 7-4.
www.arcadis.com 114
City of Sebastian Stormwater Master Plan Update
City of Sebastian Capital Improvement Project Benefit Cost Analysis Scoring Template
Project No: 13 Description: Concha Dam Repair
Criticality of Issue for LOS Project Effectiveness
Criteria Score Description Contexi Score Description Context
ECONOMIC
111111M
Criticality of Projei
Issue for LOS
0 > $10,000,000
2 $5,000,000-$10,000,000 I
I 4 $3,000,000 - $5,000,000 (What is the cost (to the City) of the proposed
Project Cost 5 $1,000,000 - $3,000,000 project?
8 $500,000-$1,0001000
10 $100,000 - $500,000
12 <5100,000
0 Ve(Y Low 0 Ve(Y Law
1 4 Low (What are the economic impacts (future flooding 1 2 Low lWhat is the potential benefit ofthe proposed
Economic Impacts 8 Medium (damages, etc.} ifthe flooding orthe asset 4 Medium projectto increased opportunities for economic
10 High (condition is not addressed? 6 High (development or community enhancements?
12 Very High 8 Very High
0 Excellent 0 No
Condition of Existing 1 Good (What is the condition of existing pmate 1 Limited (Will the proposed project fix the private asset
Infrastructure Private 2 Fair infrastructure assets in the project area? 2 Partially (conditions in the project area?
3 Poor 3 Mo�}ly
4 Very Poor 4ComeLely
0 Excellent 0 No
4 Good 2 Limited
Condition of Existing iat is the condition of existing public i re proposed project fix the public asset
Infrastructure Public 8 Fair , �„_L, i the project area? 4 Partially the project area?
10 Poor 5 Mostly
Economic Subtotal 28 Very Poor Completely
to
0
0
❑
0
10
10
18
SOCIAL
0 No potential for injury f loss of life G No
2 Limited potential for injury (What is the current impact on safety from 1 2 Limited (Will the proposed project minimize the impact
Safety 4 Some potential for injury! loss of life floodingrassett condition in the project area for 4 Partially on safety in the project area for the intended
he intended level of semce? fi Mostly =vel of semce?
6 Reasonable potential for nju
iry
8 Great potential hor injury! loss of life 8 Yes
0 None 0 None
Number of Properties 1 1 to 5 IHaw many properties are currently impacted by 1 1 to 5 IHaw many properties will have postively
Impacted 2 6 to 10 floodingrasset condition in the project area for 2 6 to 10 heneflted from the project for the intended Level
I 3 11 to 15 Ithe intended Level of Service? 1 3 11 to 15 lof Service?
4 Greater than 15 4 Greater than 15
ial impact 0 No
Traffic Flow on Public 0 No potentHow is traffic affected b °...' . -:: , ... \ Will the proposed project positively affect traffic
Streets 2 Se�gpdaryYsem 1 Alternatives Exist fin the project area? 2 Y1N� and flooding conditions in the project area?
4 nmary Vs, em! No Alternative 4 es
High Hazard Road 0 a road crossing Are there any high hazard road crossings in the 0 No Will the project postively affect the roadway
Crossings in Project Area 2 Yes, one or more crossings IDroiect area? 4 Yes/NA crossings in the project area?
Proximity to Critical 0 > 2 miles 0
Facilities (hospitals, police, 4 <2 miles How close to the project area are facilities that
Are station, etc provide health, safety or emergency response? 0
-} 8 Located within project area 0
0 1% (100-year) Storm 8 1% (100-year) Storm
Degree of Flooding Public 2 4% 25- ear Storm (> what design storm frequency does flooding To what level (design storm) has the project
De g g (Public) ( y } 6') typically occur within the project area? 4 4% (25-year) Storm fixed the flooding problem?
4 10% (10 year)Storm 0 10% (10 year)Storm
0 None 0 Livable 1 occupied space
1 Landscape 1 Y yoding (What is the worst case facility flooding for the 1 Crawl s ice! basement! mechanical ,ylhat level offacility flooding is predicted
Property Damage (Private) 2 Garage !she � jyeway intended LOS? 2 anis, 1 shed 1 dJr:ay
1 }} i h d d"fl od following project implementation?
1 3 Crawl space basemen mec anical 1 1 3 ansc ape 1 yar o ing 1
4 Livable 1 occupied space 4 None
Social Subtotal 30 32
2
2
4
4
0
o
0
0
0
4
0
0
4
10
10
ENVIRONMENTAL
0 None
Erosion 1 Limited
I 2 Moderate
3 Significant
0 None
A Limited
Water Quantity Reduction
8 Moderate
12 Significant
0 None
Water Quality Improvement 4 Limited
8 Moderate
12 Significant
0 None
Habitat Improvement 2 Limited
I 4 Moderate
6 Significant
0 None
Public Health 1 Limited
2 Moderate
3 Significant
0 None
2 Limited
Aesthetic Effects
4 Moderate
Significant
Environmental Subtotal 42
0 None/NA
(What effect will the project have on reducing 1 2 Limited IHow has the project postively affected the
(erosion issues within the SWIMS? 14 Moderate (environment?
fi Significant
0 None/NA
fat effect will the project have on reducing the 2 Limited IHow has the project postively affected t
Fstormhe
water discharged to receiving (environment?
waterhodies? 4 Moderate
6 Significant
0 None/NA Haw, has the project postively affected the
. 'hat effect will the project have on improving th- environment? How much CIRL BMAP TN and
- , -'y of stormwater discharged to receiving 2 Limited
waterbodies? 4 Moderate TP reduction credit will the project he eligible
5 Significant or?
0 None/NA
(What effect will the project have on improving thel 2 Limited IHow has the project postively affected the
Ihshitat of receiving waterhodies? 14 Moderate lenvironment?
fi Significant
0 None/NA
What effect will the project have on improving
. health parameters in receiving 2 Limited IHow has the project postively affected the
waterhodies? 4 Moderate lenvironment?
fi Significant
0 None/NA
What effect will the project have on improving'
2 Limited IHow has the project postively affected the
aesthaadi of the SWIMS and receiving environment?
waterbodles7 4 Moderate
36 Significant
1
2
12
6
12
5
5
5
3
fi
4
4
39
19
TOTAL
100
100
59
57
ofTatal Categaryr Scare
59%
57%
Figure 7-2. CIP Prioritization Project Scorecard
www.arcadis.com 115
City of Sebastian Stormwater Master Plan Update
CIP
Project No.
4
Description
Harbor Point Waterway and Collier Waterway North Improvements
Critcality
Economic
18
at Issue for
Social
11
LOS Scores
Environ.
11
Totai
41
Project Effectiveness
Economic
2
Social
11
Scores
Environ.
5
Total
18
TDTAL
SCDRE
59
Score
-0.96
5
Central Collier Waterway Improvements- North Sed[on
18
11
12
41
2
11
5
18
59
-a.96
6
Central Collier Waterway Improvements- South Section
18
11
12
41
2
11
5
18
59
-0.86
7
Schumann Waterway Improvements
18
11
12
41
2
11
5
18
59
-0.96
8
Schumann Lake Improvements
18
11
12
41
2
11
5
18
59
-0.96
9
Joy Haven Waterway Improvements
18
11
12
41
2
11
5
18
59
-0.96
10
Collier Waterway South Improvements
18
11
12
41
2
11
5
18
59
-0.96
11
Ocean Cove Drainage Repair
14
20
16
50
16
23
12
51
101
0.57
12
Day Drive Re&ntion Area Restoration
16
17
16
49
16
18
14
48
97
0.43
13
Concha Dam Repair
10
10
39
59
18
10
29
57
116
1.12
15
StonecropDitch -TuIipCuIvertReplacement
16
15
4
35
20
17
6
43
78
-0.27
16
Stonecrop Ditch - Albatross Culvert Replacement
16
15
4
35
20
17
6
43
78
-0.27
17
Stonecrop Ditch - Bayfront Culvert Replacement
16
15
4
35
20
17
6
43
78
-0.27
18
Benedictine Area Culvert Improvements
16
15
4
35
20
17
6
43
78
-0.27
19
Brya nVF ri a r Co u rt Reten to n Pond
16
13
36
65
20
27
26
73
138
1.93
20
Hardy Dam Retrofrt Gaffs
24
17
31
72
22
27
18
67
139
1.96
21
Sutrey Terrace Retention Basin
0
11
19
30
8
17
16
41
71
-0.52
22
Newhall Terrace Retention Basn
0
11
19
30
8
17
71
-0.52
23
Coolidge ❑utfall Improvements
16
15
19
50
20
17
1W
0.65
24
Blossom Ditch Drainage Improvements
18
15
19
52
12
21
105
0.72
25
Drainage Improvements at Hazel and Lloyd St
18
18
21
5T
20
21
12�
116
1.12
26
Stormwater Park operation
4
2
16
22
16
4
56
-1.07
27
Stonecrop Retention Area
20
14
23
57
26
21
124
7.42
MAXfMBM
SCORE
28
30
42
100
32
32
36
100
200
Figure 7-3. CIP Prioritization Scoring Summary
www.arcadis.com 116
City of Sebastian Stormwater Master Plan Update
100%
90%
80%
70%
0
60%
0
50%
41
40%
U
U 30%
20%
10%
25
•
• • 24
12
0%
0% 10% 20% 30% 40% 50% 6 70% 80% 90% 10D%
Effectiveness (% of total scare)
Figure 7-4. CIP Prioritization Scoring — Criticality vs. Effectiveness
7.4 Recommended and Prioritized Improvements
Projects with high costs and low priority scores were shown in the 10-year CIP plan as "Future", and the CIP
planning emphasis was directed towards lower cost, higher priority projects. A copy of the proposed CIP Plan
from 2023-2033 including more than $9 million in capital projects is included in Appendix I. A detailed
discussion of the funding plan for the CIP projects and the ongoing operations and maintenance of the City's
SWMS in included in the next Section.
www.arcadis.com 117