DATE: November 16, 2023 PROPOSAL 032412
SUBMITTED TO: Sebastian Public Works, City of
STREET: 1225 Main Street
CITY, STATE & ZIP: Sebastian, FI 32958
PHONE: (772) 228-7056
FAX: (772) 228-7077
EMAIL: ppatnode@cityofsebastian.org
JOB NAME: Sebastian Elementary School Crossing
ATTENTION: Phil Patricide
We propose to furnish a crew and all necessary equipment to clean, televise, and install 54" CIPP at the above mentioned job
location. This work will be performed at our following hourly and/or unit prices:
Mobilization
Heavy Cleaning 54"
Storm Drain Video Observation 49-72"
Install 54" CIPP
Track or wheeled Excavator
Equipment Operator
Construction Foreman
Laborers
Estimated Total:
(at $300.00 Each)
1 Each
$300.00
(at $19.00 Per L.F.)
30 L.F.
$570.00
(at $20.00 Per L.F.)
30 L.F.
$600.00
(at $541.32 Per L.F.)
30 L.F.
$16,239.60
(at $50.00 Per Hour)
16 hour(s)
$800.00
(at $150.00 Per Hour)
16 hour(s)
$2,400.00
(at $55.00 Per Hour)
16 hour(s)
$880.00
(at $35.00 Per Hour)
48 hour(s)
$1,680.00
$23,469.60
The pricing on this proposal is based off of a piggyback of Shenandoah Construction's Broward College Storm Drain
Cleaning, Repairs, and Maintenance RFP-2018-167-EH
NOTE: Due to the fragile condition of the existing pipe(s), the possibility of the pipe collapsing exists during the construction phase.
If this unlikely event occurs, we will provide you with an additional estimate for a necessary point repair to complete the lining
process. Due to the poor condition of the original host pipe, residual settling may appear at the surface grade, post lining. This
condition is not covered under warrantee.
This proposal may be withdrawn if not accepted within 30 days. Payment terns net 30 days.
(If we encounter an Insurance compliance fee requirement, this fee will be invoiced in addition to the above rates.)
All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard
practices. Price above is only an estimate of foreseen conditions. Unforeseen conditions can affect the amount of time to complete
the work, therefore increasing or decreasing estimate. All agreements are contingent upon strikes, accidents or delays beyond our
control. Unless noted above engineering, permits, testing and bonds are not included in the pricing. Owner is to carry fire, tornado
and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance. Parties to this
proposal/contract expressly waive all tort claims against each other and limit their remedies to breach of contract.
SIGNATURE:
Qttr1�(;;fbll�
SHENANDOAH GENERAL CONSTRUCTION CO.
Louis Woska
TITLE DATE
Estimator 11/16/2023
ACCEPTANCE OF PROPOSAL / SIGN & RETURN
The above price specifrcatio an conditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified. _
SIGNATURE:
COMPANYNAME: City of Sebastian DATE: 12/13/2023
REPRESENTATIVE: TITLE: City Manager
Page f o/ 1
11,r�SHENANDOA i
1888 NW 22nd Street Pipe Inspection a acstorabon Specialist pompano Beach, FL, 33069
(772)202-3260 shenandoahus.com
DATE: December 04, 2023 PROPOSAL #P32559
SUBMITTED TO: Sebastian Public Works, City of
STREET: 1225 Main Street
CITY, STATE & ZIP: Sebastian, FI 32958
PHONE: (772) 228-7056
FAX: (772) 228-7077
EMAIL: ppatnode@cityofscbastian.org
JOB NAME: Capri and Schumann Dr.
ATTENTION: Phil Patnode
We propose to furnish a crew and all necessary equipment to clean, televise, and install 48" CIPP at the above mentioned job
location. This work will be performed at our following hourly and/or unit prices:
Mobilazation (at $300.00 Each) 1 Each $300.00
Medium Cleaning and Sediment Removal 48" (at $3.50 Per L.F.) 109 L.F. $381.50
Storm Drain Video Observation 0-48" (at $6.00 Per L.F.) 109 L.F. $654.00
Install 48" CIPP (at $346.55 Per L.F.) 109 L.F. $37,773.95
Estimated Total: $39,109A5
The pricing on this proposal is based off of a piggyback of Shenandoah Construction's Broward College Storm Drain
Cleaning, Repairs, and Maintenance RFP-2018-167-EH
NOTE: Due to the fragile condition of the existing pipe(s), the possibility of the pipe collapsing exists during the construction phase.
If this unlikely event occurs, we will provide you with an additional estimate for a necessary point repair to complete the lining
process. Due to the poor condition of the original host pipe, residual settling may appear at the surface grade, post lining. This
condition is not covered under warrantee.
This proposal may be withdrawn if not accepted within 30 days. Payment terms net 30 days.
(If we encounter an Insurance compliance fee requirement, this fee will be invoiced in addition to the above rates.)
All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard
practices. Price above is only an estimate of foreseen conditions. Unforeseen conditions can affect the amount of time to complete
the work, therefore increasing or decreasing estimate. All agreements are contingent upon strikes, accidents or delays beyond our
control. Unless noted above engineering, permits, testing and bonds are not included in the pricing. Owner is to carry fire, tomado
and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance. Parties to this
proposal/contract expressly waive all tort claims against each other and limit their remedies to breach of contract.
SIGNATURE: I�p
SHENANDOAH GENERAL CONSTRUCTION CO.
Louis Woska
TITLE DATE
Estimator 12/04/2023
ACCEPTANCE OF PROPOSAL/SIGN & RETURN
The above prices specification 3ndconditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified.
SIGNATURE:
COMPANYNAME: City of Sebastian DATE: 12/13/2023
REPRESENTATIVE: TITLE: City Manager
This document is the properly of Shenandoah General Construction. Il is intended only for the use of the individual a enldy to which It is addressed and may contain
elimination that Is non-public. proprietary, privileged. confidential and exempt from disclosure under applicable law or may constitute as attorney work product. If you are not
the intended recipient, you are hereby notified that any use. dissemination, distribution or copying of this communication of tins document is strictly prohibited If you have
received this tlocument In error notify us immediately by telephone (954) 075.0098 or Email help@shenandoahus.win and destroy this document immediately. if thts is an
electronic communication then delete immediately
Page 1 o/ 1
SHENANDOAH
1888 NW 22nd Street Ripe Inspection & Restoration Specialist Pompam Beach, F1, 33069
(772) 202-3260 shenandoahus.com
DATE: December 04, 2023 PROPOSAL #P32560
SUBMITTED TO: Sebastian Public Works, City of
STREET: 1225 Main Street
CITY, STATE & ZIP: Sebastian, F132958
PHONE: (772) 228-7056
FAX: (772) 228-7077
EMAIL: ppatnode@cityofsebastian.org
JOB NAME: Admiral and Schumann 48"
ATTENTION: Phil Patnode
We propose to furnish a crew and all necessary equipment to clean, televise, and install 48"
CIPP at the above mentioned job
location. This work will be performed at our following hourly and/or unit prices:
Mobilization (at $300.00 Each)
1 Each
$300.00
Medium Cleaning and Sediment Removal 48" (at $3.50 Per L.F.)
97 L.F.
$339.50
Storm Drain Video Observation 0-48" (at $6.00 Per L.F.)
97 L.F.
$582.00
Install 48" CIPP (at $346.55 Per L.F.)
97 L.F.
$33,615.35
Estimated Total:
$34,836.85
The pricing on this proposal is based off of a piggyback of Shenandoah Construction's Broward College Storm Drain
Cleaning, Repairs, and Maintenance RFP-2018-167-EH
NOTE: Due to the fragile condition of the existing pipe(s), the possibility of the pipe collapsing exists during the construction phase.
If this unlikely event occurs, we will provide you with an additional estimate for a necessary point repair to complete the lining
process. Due to the poor condition of the original host pipe, residual settling may appear at the surface grade, post lining. This
condition is not covered under warrantee.
This proposal may be withdrawn if not accepted within 30 days. Payment terms net 30 days.
(If we encounter an Insurance compliance fee requirement, this fee will be invoiced in addition to the above rates.)
All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard
practices. Price above is only an estimate of foreseen conditions. Unforeseen conditions can affect the amount of time to complete
the work, therefore increasing or decreasing estimate. All agreements are contingent upon strikes, accidents or delays beyond our
control. Unless noted above engineering, permits, testing and bonds are not included in the pricing. Owner is to carry fire, tornado
and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance. Parties to this
proposal/contract expressly waive all tort claims against each other and limit their remedies to breach of contract.
SIGNATURE: /
SHENANDOAH GENERAL CONSTRUCTION CO.
Louis Woska
TITLE DATE
Estimator 12/04/2023
ACCEPTANCE OF PROPOSAL / SIGN & RETURN
The above prices, specification conditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified. /yy
SIGNATURE: / /q
CO NAME: City of Sebastian DATE: 12/13/2023
REPRESENTATIVE: TITLE: City Manager
This document is the property of Shenandoah General Construction. It is intended only for the use of the individual or enhiy to which it is addressed and may contain
information that is non-public, proprietary, privileged. confidential and exempt from disclosure under applicable law or may constitute as attorney work product. If you are not
the intended recipient, you are hereby notified that any use, dissemination, distribution or copying of this communication of this document is strictly prohibited, If you have
received this document in error, notify us immediately by telephone (954) 075-0098 or Email: help@shenandoahus.com and destroy this document immediately, if this is an
electronic communication then delete immediately
Page f o/ 1
11"�r'SI�EN/�NDO/�I�
3888 NW 22ntl Street Pipe Inspection & aestoratlon Specialist Pompom 8meth, fl, 33069
(772) 202.3260 shenandoahus.com
DATE: December 04, 2023 PROPOSAL #P32561
SUBMITTED TO: Sebastian Public Works, City of
STREET: 1225 Main Street
CITY, STATE & ZIP: Sebastian, F) 32958
PHONE: (772) 228-7056
FAX: (772) 228-7077
EMAIL: ppatnode@cityofsebastian.org
JOB NAME: Dahl and Schumann 48"
ATTENTION: Phil Patriotic
We propose to furnish a crew and all necessary equipment to clean, televise, and install 48" CIPP at the above mentioned job
location. This work will be performed at our following hourly and/or unit prices:
Mobilization (at $300.00 Each) 1 Each $300.00
Medium Cleaning and Sediment Removal 48" (at $3.50 Per L.F.) 104 L.F. $364.00
Storer Drain Video Observation 048" (at $6.00 Per L.F.) 104 L.F. $624.00
Install 48" CIPP (at $346.55 Per L.F.) 104 L.F. $36,041.20
Estimated Total: $37,329.20
The pricing on this proposal is based off of a piggyback of Shenandoah Construction's Broward College Storm Drain
Cleaning, Repairs, and Maintenance RFP-2018-167-EH
NOTE: Due to the fragile condition of the existing pipe(s), the possibility of the pipe collapsing exists during the construction phase.
If this unlikely event occurs, we will provide you with an additional estimate for a necessary point repair to complete the lining
process. Due to the poor condition of the original host pipe, residual settling may appear at the surface grade, post lining. This
condition is not covered under warrantee.
This proposal may be withdrawn if not accepted within 30 days. Payment terms net 30 days.
(If we encounter an Insurance compliance fee requirement, this fee will be invoiced in addition to the above rates.)
All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard
practices. Price above is only an estimate of foreseen conditions. Unforeseen conditions can affect the amount of time to complete
the work, therefore increasing or decreasing estimate. All agreements are contingent upon strikes, accidents or delays beyond our
control. Unless noted above engineering, permits, testing and bonds are not included in the pricing. Owner is to carry fire, tornado
and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance. Parties to this
proposal/contract expressly waive all tort claims against each other and limit their remedies to breach of contract.
SIGNATURE:
dtfrll(j_(blt —
SHENANDOAH GENERAL
Louis Woska
CO. TITLE DATE
Estimator 12/04/2023
ACCEPTANCE OF PROPOSAL / SIGN & RETURN
The above prices specification conditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified.
SIGNATURE: i
COMPANYNAME: City of Sebastian DATE: 12/13/2023
REPRESENTATIVE: TITLE: City Manager
This document is the property of Shenandoah General Construction. It is intended only tor the use of the individual or enaly to which it is addressed and may contain
miorrna Lion that is non-public, proprietary, privileged, confidential and exempt from disclosure under applicable law or may constitute as attorney work product. If you are not
the intended recipient, you are hereby notified that any use, dissemination, distribution or copying of this communication of this document Is strictly prohibited. If you have
received this document In error, notify us immediately by telephone (954) 075-0098 or Email help@shenandoahus.com and destroy this document immediately, if this is an
electronic communication then delete Immediately
❑nn
HOME OF PELICAN ISLAND
CITY COUNCIL AGENDA TRANSMITTAL
Council Meetine Date: December 13, 2023
Aeenda Item Title: Shenandoah Slip lining at four locations along Schumann Drive
Recommendation: Staff recommends Council approve the proposals provided by Shenandoah to
complete investigation and slip lining repairs of failed culvert piping at four
locations along Schumann Drive at Sebastian Elementary School Crossing,
Capri Avenue, Admiral Circle, and Dahl Avenue for a total of $134,745.10
and authorize City Manager to execute the appropriate documents,
Backeround: Slip lining is a common practice at the City of Sebastian to repair Stormwater
drainage pipes in high impact areas, Using slip lining to repair drainage structures in place, instead of pipe
removal and replacement, prevents damage to City property and drastically shortens road closures. Per
previous City Council approval, we have been piggybacking the Broward College's Storm Drain Cleaning,
Repairs & Maintenance contract and its extensions, which include slip lining services and pricing. The current
Broward College contract extends through November 26, 2024. We are requesting City Council approval to
move forward with camera investigation and slip lining repair of 30 linear feet at Sebastian Elementary
School Crossing, 109 linear feet at Capri Avenue and Schumann Drive, 97 linear feet at Admiral Circle and
Schumann Drive, and 104 linear feet at Dahl Avenue and Schumann Drive. A drainage investigation was
completed by the City of Sebastian to plan drainage repairs along Schumann Drive prior to the upcoming
roadway rehabilitation plans. All of these repair locations were determined during the initial drainage
investigation and pricing proposals for each of the four individual locations are attached for reference.
If Aeenda Item Requires Expenditure of Funds:
Budgeted Amount: $165,000
Total Cost: $134,745.10
Funding: Stormwater Revenue Fund
Attachments:
1. Shenandoah Proposal #P32412 — Sebastian Elementary School Crossing
2. Shenandoah Proposal #P32559 —Capri Avenue and Schumann Dr.
3. Shenandoah Proposal #P32650 — Admiral Circle and Schumann Dr.
4. Shenandoah Proposal #P32561 — Dahl Avenue and Schumann Dr.