HomeMy WebLinkAbout#A2450 Certificate of CompletionCITY OF
SEBAS-T�I
HOME OF PELICAN ISLAND
CERTIFICATE OF PROJECT COMPLETION
Date Accepted: 07/22/24
Project Name & #: Reconstruct Alpha Apron # A2450
Total Project Expenditures: $ 607,443.44
Project Location: Airport
Contractor(s): See attached list
Contract Amount(s): $ 607,443.44
Pursuant to the above captioned contract and in compliance of same, we the undersigned do hereby certify
that this project is complete.
Issuance of this certificate releases the contractor from any further responsibility as stipulated in the contract
as it relates to bond performance, payment of subcontractors, release of liens, maintenance and indemnity. All
contractual obligations as to warranty, insurance, indemnification and patents, shall remain in full effect for the
contractually stipulated period of time. In no way does the issuing of this certificate release the Contractor from
all legal obligations as stipulated in Chapter 713 of the Florida Statutes.
Therefore, having reviewed the contract and inspected the work, the undersigned to hereby accept the
segment as being complete.
14 VL 11(012tl
Project Manager I Date
,v/,,•
Building Official (if applicable) Date
ld
City' Clerk Date
PROJECT ID A2450 Reconstruct Alpha Apron
FY24
DATE
CHECK #
PO #
DESCRIPTION
VENDOR
AMOUNT
TOTALS
12/08/23
109248
10585
30% Design (10/30/23 - 11/26/23)
Infrastucture Consulting & Engineering
4,804.31
4,804.31
01/09/24
109399
10585
30% & Final Design (11/27/23 - 12/31/23)
Infrastucture Consulting & Engineering
14,466.35
14,466.35
02/05/24
109588
10585
Final Design (01/01/24 - 01/28/24)
Infrastucture Consulting & Engineering
815.67
815.67
02/25/24
109725
Invitation to Bid
TC Palm
92.12
92.12
04/11/24
110094
10585
Final Design (01/29/24 - 03/31/24)
Infrastucture Consulting & Engineering
2,437.45
2,437.45
05/09/24
110269
10585
Final Design (04/01/24 - 04/28/24)
Infrastucture Consulting & Engineering
2,084.89
2,084.89
05/31/24
110568
10811
Work thru 05/31/24
Dickerson Infrastructure
513,737.76
513,737.76
06/14/24
110463
10585
Construction Engineering Services & Inspection (04/29/24 - 06/02/24)
Infrastucture Consulting & Engineering
26,617.27
26,617.27
07/17/24
110723
10811
Work thru 07/17/24
Dickerson Infrastructure
32,891.31
32,891.31
07/22/24
110740
10585
Construction Inspection & QA Testing (06/03/24 - 06/30/24)
Infrastucture Consulting & Engineering
9,496.31
9,496.31
607,443.44 607,443.44