September 20, 2024
Karen Miller
Director of Public Works/City Engineer
City of Sebastian
Subject: City of Sebastian ITB #23-024 Drainage Improvement in Stonecrop Drainage
Watershed
Regards: Scope of Work Change-004 – Tree Removal
To Karen Miller
UESI is pleased to provide you this proposal to remove the trees in accordance with the Jack’s
Complete Tree Service Tree Risk Assessment within the easements. UESI will remove the trees
and debris. This is scope of work outside the current contract.
Cost for change in scope of work to remove additional trees: $49,546.00
Scope of work:
Lot 1416 Stonecrop Street: 2-Oaks, 1-Carrotwood, 1-Oleander and stump grind 6”-8” below ground
Lot 943 Montrose Avenue: 3-Oaks and stump grind 6”-8” below ground
Lot 841 Montrose Avenue: 2-Oaks and stump grind 6”-8” below ground
Lot 801 Montrose Avenue: 1-Avacado and Sea grapes and stump grind 6”-8” below ground
Lot 871 Montrose Avenue: 3-Oaks and stump grind 6”-8” below ground
Lot 861 Montrose Avenue: Transplant 3-Palms out of easement.
*City or Owner is responsible for watering and keeping the trees alive.
*Option to remove 3-palms if preferred by City or Owner.
Lot 831 Montrose Avenue: 1-Oak and hedge and stump grind 6”-8” below ground
Lot 821 Montrose Avenue: Sea grapes and stump grind 6”-8” below ground
Lot 934 Majestic Avenue: 3-Oaks and stump grind 6”-8” below ground
Lot 892 Majestic Avenue: 1-Norfolk pine, 1-Cabbage Palm and stump grind 6”-8” below ground
Lot 862 Majestic Avenue: 2-Oaks, 1-Drake Elm and stump grind 6”-8” below ground
Additional Rates if Required:
Tree Arborist: $165.00 per hour
UESI Project Manager: $105.00 per hour
If you should have any questions, please contact us at your convenience.
Thank you,
Andrew Connelly
Vice President