24-19-ITB – Addendum 3 Page 1 of 4
ADDENDUM NO. 3
September 6, 2024
24-19-ITB - Hangar D Build Out - South Offices
The original Invitation to Bid shall remain in full force and effect, except as modified herein, which shall
take precedence over any contrary provisions in the prior documents.
SECTION I: CLARIFICATIONS
• N/A
SECTION II: QUESTIONS
1. Question: How much clearance will be provided in the Hangar Area to perform the work required
to create the opening in the wall dividing the Simulator Bay and Hangar?
Answer: The aircraft will be removed, and an open area of 20’ x 20’ will be provided with
access to the roll-up door.
2. Question: Will the area in the Hangar be free of contents and not require content manipulation and
protection by the GC during construction?
Answer: Yes.
3. Question: Will the awarded GC be responsible for removing and reinstalling the X-Bracing on the
hangar side of the wall?
Answer: Yes
4. Question: Will the Simulator be moved into the area during construction or will the awarded GC
need to return to fill in the area after all other construction has been completed?
Answer: The simulator move shall be the last phase of work, providing the opening for the
tenant to move the unit in, followed by immediate closure again.
5. Question: If the simulator will be moved into the area during construction will the tenant be
responsible for protecting the simulator until construction has been completed or will the awarded
GC be responsible to protect the simulator?
Answer: The simulator move shall be the last phase of work, providing the opening for the
tenant to move the unit in, followed by immediate closure again.
6. Question: Regarding Electrical Lighting Plan: The scope of work provided by the City conflicts
with the electrical lighting plan. Please clarify if the GC should quote per the Scope or the Plans.
Answer: Use the Scope as provided.
Finance Department
Procurement Division 1225 Main Street
Sebastian, FL 32958
(772) 388-8231
24-19-ITB – Addendum 3 Page 2 of 4
7. Question: The scope of work in the ITB for the Kitchen/Breakroom includes Sink/Water Piping
Plumbing. Will the scope be revised to note the plumbing to the Kitchen/Breakroom Sink is already
in place?
Answer: The sink is on hand and needs to be mounted on the countertop. Then plumbing
connections are required underneath and next door in the utility room. Piping between the
two is in place.
8. Question: The scope of work provided by the City requests for baseboard with quarter round,
painted; but, the plans specify 4” black rubber base. Please clarify if we are to price per the scope
or the plans.
Answer: Baseboard with quarter round, no black rubber cove base.
9. Question: If the City prefers wood baseboard, please specify size and type/style.
Answer: 6” baseboard, non-wood, with quarter round in the 2 offices.
10. Question: Existing drywall needs to be removed for framing/electrical and data inspection?
Answer: No. All existing walls are still open for inspection as needed.
11. Question: Please confirm location for Network - 2 ea. Cat 5 Connections.
Answer: This requirement has been removed from the scope of work.
12. Question: Grid Specification Needed (or We can assume 15/16 grid white)
Answer: 15/16 grid White
13. Question: What type of tile 2x2 acoustical panels?
Answer: Standard recessed acoustical panels, white
14. Question: Provide specifications for 2x2 LED ceiling lights.
Answer: LED Basket Troffer. 120-277v. White Finish. 20-25W.
15. Question: Can you provide a drawing with existing fire sprinkler heads?
Answer: The floor plan has been provided. The life safety plan will be provided to the
awarded bidder.
16. Question: For the HVAC unit already installed, it is assumed that all work is complete and the
warranty for this installation is not the responsibility of the new contractor, nor is the product
warranty. We would only be responsible for the duct work?
Answer: Correct. The contractor shall secure duct work, diffusers, and intake plenum to
finish.
Finance Department
Procurement Division 1225 Main Street
Sebastian, FL 32958
(772) 388-8231
24-19-ITB – Addendum 3 Page 3 of 4
17. Question: It is assumed that the wall base will be johnsonite 4” black.
Answer: No. Please refer to question #9.
18. Question: Where is quarter round required?
Answer: Quarter round is required in both west offices. None in the breakroom or simulator
area
19. Question: Clarification is needed, the plan shows CPT (Carpet) and scope of work 20x20 porcelain
grout.
Answer: No porcelain, Luxury Vinyl Tile (LVT) or carpet.
20. Question: Is bracing needed for existing framing?
Answer: No.
21. Question: Provide additional details for 4x4 Window Overlooking Simulator Bay.
Answer: Simple framed glass viewing window, non-opening and no obstructions
22. Question: What type of framing and area and height (exterior wall).
Answer: Same height as interior walls, framed and sheetrock
23. Question: More information is needed on this detail to create a 9x9 opening that meets fire rating.
Answer: What information or questions do you have about the opening? We need specific
questions regarding the information provided in the scope and the information provided on
the plans.
24. Question: In the case of pre existing job there's no active permit as it was done by tenant but tenant
will create it and close it so in case anything was improperly done then we will not be responsible?
Answer: Correct.
25. Question: Provide preexisting floor plan.
Answer: The Hangar D Floor Plan & Tenant Spaces Drawings have been uploaded to
VendorLink.
26. Question: We recommend 120 days for substantial.
Answer: The substantial completion and final completion dates will not be altered.
27. Question: Is a bid bond required for this project?
Answer: Yes.
Finance Department
Procurement Division 1225 Main Street
Sebastian, FL 32958
(772) 388-8231
24-19-ITB – Addendum 3 Page 4 of 4
28. Question: What is the size of the wall opening for the Simulator? Based on the dimensions, cross
members support may need to be removed and reinstalled.
Answer: 9x9.
29. Question: Height of the exterior walls in the Simulator area for insulation and drywall
Answer: see question #22.
30. Question: Will staff be working during the renovation?
Answer: No.
SECTION III: REVISIONS TO THE SCOPE OF WORK
• N/A
SECTION IV: ATTACHMENTS
• F-24-19-ITB - Addendum 1 - Hangar D Floor Plan & Tenant Spaces Drawings
o Uploaded to VendorLink
Sincerely,
Jessica Graham, CPPB
Procurement/Contracts Manager
Acknowledgment of Addendum No. 3 by Contractor
The Respondent hereby acknowledges receipt of the following Addendum:
This addendum shall be completed and signed by an authorized representative and returned with the
solicitation submittal. The Acknowledgment of the addendum receipt will become an integral part of the
solicitation document. Acknowledging receipt of this Addendum, the undersigned understands and accepts
the foregoing solicitation changes and clarifications.
All other bid terms, conditions, and specifications as originally issued remain unchanged