RIVIERA AVENUE AND GARDENIA STREET DRAINAGE IMPROVEMENTS
11.25.2024
SCOPE OF SERVICES — EXHIBIT A
The Engineer shall provide Construction Engineering and Inspection (CEI) for the
Riviera Ave. and Gardenia St. Drainage Improvements Project. The Project may include,
but is not limited to, drainage pipe installation and minor earthwork operations.
The CEI services for Riviera Ave. and Gardenia St. Drainage Improvements shall
include:
• Field observations, including photos and documentations for compliance
• Design modifications as needed (adjustments that can be made with field
changes not requiring EOR)
• Coordination and meetings, including pre -construction and progress meetings,
with the contractor, City, public, utility companies, landowners and testing
fines
• Review all Contractor's change orders
• Review contractor's pay estimates, pay requests, and schedules
• Review shop drawings
• Review of geotechnical test results provided by others
• Preparation of project progress reports as requested
• Coordination of permit conditions and compliance, including preparation of all
required reporting and documents as needed
• Provide City with copies of project records
• Respond to request for information by the contractor and public
• Project Closeout and review of as-builts by others to ensure compliance with
permitting agencies
The Engineer shall observe work performed and material used to determine if the work
has been completed in accordance with the construction contract.
Deliverables
The Engineer shall prepare and submit the following:
1. Construction Completion Package containing the following:
a. Dated final as -built schedule, time file and daily work reports.
b. Field survey/geotechnical verification data provided to Engineer by others.
c. Final as -built plans provided to Engineer by the Contractor.
d. Documentation of progress meetings, public informational meetings, and any
other pertinent project meetings with dates and notes.
e. Documentation of all field decisions which caused any deviation from the plans
and/or specifications.
f. Signed and Sealed test results by others.
g. Documentation of progress payments and final payment to the Contractor.
Docusign Envelope ID: F6777F46-22D647D9-A14C-3889C5796E66
CITY OF SEBASTIAN, FLORIDA
WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
Exhibit A
Johnson, Mirmiran & Thompson, Inc. — CSA #5 Page 3 of 3
Docusign Envelope ID: F6777F46-22D6-47D9-A14C-3889C5796E66
CITY OF SEBASTIAN, FLORIDA
WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
AGREED:
Johnson, Mirmiran & Thompson, Inc.:
FaSh�
N. q IL
IMIALS
$t V088t"iiaines, PE, Vice President
Date:1/2/2025 1 2:53:21 PM EST
Attest:
�mu,apw W.
p::8 r - Iva/...d
Jeanette Williams, MMC,
City Clerk
CITY OF SEBASTIAN:
;i,ap..a ey:
Brian rMon, City Manager
Date:1/6/2025 1 7:29:43 AM EST
Approved as to Form and Content for Reliance
by the City of Sebastian only:
�c«va4� ey:
Jenn%f ff Cockcroft, Esq.,
City Attorney
Johnson, Mirmiran & Thompson, Inc. — CSA #5 Page 2 of 3
Docusign Envelope ID: F6777F46-22D647D9-A14C-3889C5796E66
CITY OF SEBASTIAN, FLORIDA
WORK AUTHORIZATION FORM
CONSULTANT SERVICE AGREEMENT (CSA)
Johnson, Mirmiran & Thompson, Inc. (JMT)
3731 Oleander Ave, Suite 108
Fort Pierce, FL 34982
Work Authorization No: CSA - #5
Proiect Title: Riviera Ave. and Gardenia St. Drainage Improvements Project, CEI Services
IT IS AGREED to undertake the following work in accordance with the provisions of RFQ 21-01 - Johnson,
Mirmiran &Thompson, Inc. (JMT), Master Agreement entitled NON-EXCLUSIVE ENGINEERING CONSULTING
SERVICES AGREEMENT dated FEBRUARY 22, 2021.
Description of Assignment:
Johnson, Mirmiran & Thompson, Inc. (JMT) will provide Construction Engineering and Inspection (CEI) for the
Riviera Ave. and Gardenia St. Drainage Improvements Project. The Project may include, but it not limited to,
drainage pipe installation and minor earthwork operations.
1. Preliminary Planning
N/A
2. Permitting & Inspections
See detailed Scope of Work attached (Exhibit A)
3. Contract Administration
N/A
4. Vendor's Responsibility
See detailed Scope of Work attached (Exhibit A)
5. Pricing
Description Quantity Contracted TOTALS
Unit Price
Shop Drawing Reviews $1,670.00
(See Exhibit A for a detailed fee schedule)
Start-up & Close-out $6,275.00
(See Exhibit A for a detailed fee schedule)
Construction (3 weeks; 21 day construction time) $17,010.00
(See Exhibit A for a detailed fee schedule)
6. Deliverables Provided to the City (surveys, plans, etc.)
I Description Quantity
(See Exhibit A for a detailed fee schedule)
Basic of Compensation/Period of Services:
The above -referenced description for CSA #5 will be performed for a fee of $24,955.00
Johnson, Mirmiran & Thompson, Inc. — CSA #5 Page 1 of 3
Docusign Envelope ID: F6777F46-22D6A7D9-A14C-3889C5796E66
h. Copies of all RFIs and responses.
i. Copies of all executed changes to the contract.
j. Copies of the final inspection deficiency lists with dates of item resolution.
k. All other project records.
Docusign Envelope lD:F6777F46-22D647D9.A14C.3889C6796E66
CEI SERVICES FOR RIVIERA AVE. AND GARDENIA ST. DRAINAGE IMPROVEMENTS
MANHOUR ESTIMATE
Riviera Ave. and Gardenia St. Drainage Improvements- CEI Services
Manhour & Cost Estimate
JMT, Inc.
12/23/2024
Shoo Drawine Reviews
ISr. Project Engineer
I Project Manager
ISr. Inspector
Start-uo & Close-out
ISr. Project Engineer
(Project Manager
ISr. Inspector
Construction 13 weeks: 21 day construction timel
ISr. Project Engineer
(Project Manager
ISr. Inspector
Field Office & Utilities
Direct Expense
Direct Expense
Notes: Based on 3 weeks of construction time.
As-builts and geotechnical testing by others
Time & Expense Basis
Hrs/Week Total Weeks Total Hours Rate/Hr I Total
--- --- 2.00 $ 195.00 $ 390.00
-- --- B.00 $ 160.00 1 $ 1,280.00
--- --- - $ 105.00 $ -
Subtotal $ 1,670.00
Hrs/Week
Total Weeks
Total Hours
Rate/Hr
Total
2
2.50
5.00
$ 195.00
$
975.00
8
2.50
20.00 1
$ 160.00
$
3,200.001
8
2.50
20,00
$ 105.00
$
2,100.001
Subtotal
$
6,275.00
Hrs/Week
Total Weeks
Total Hours
Rate/Hr
Total
2
3.00
6.00
$ 195.00
$
1,170.00
12
3.00
36.00 1
$ 160.00
$
5,760.001
32
3.00
96.00
$ 105.00
$
10,080.001
Subtotal
$
17,010.00
Budget of $0/mo for 12 mos. $
I I II$
TOTAL = $
24,955.00
Manhour Estimate (12.23.24) - City of Sebastian.xim 1 of 1