HomeMy WebLinkAboutAgenda TransmittalITY OF SEBASTIAN
CITY COUNCIL STAFF REPORT
DATE February 12, 2025
TO Honorable Mayor and City Council
THRU Brian Benton, City Manager
FROM Jeffrey Sabo, Airport Manager
SUBJECT
Consideration of Resolution R-25-04 to accept FDOT
Public Transportation Grant Agreement (PTGA) –
Engineer & Design Terminal Apron Expansion
EXECUTIVE SUMMARY
This Public Transportation Grant Agreement (PTGA) will allow the airport to begin the design process
for enhancing and expanding the aircraft parking apron at the Sebastian Municipal Airport Terminal
Building. The current apron space and layout only allows secure parking for six (6) aircraft. With
strategic additions to the asphalt surface and a new layout, we will be able to double our available
parking to twelve (12) aircraft spaces.
This apron is a primary receiving area for transient aircraft and new arrivals and is located adjacent to
the airport fueling facility. The total project cost for this design phase is $230,000 to be funded through
two separate grants from the FAA at 95% and FDOT at 2.5%. The City’s responsibility will also be
2.5%, which is $5,750. This Resolution will accept the FDOT grant, 453357-1-94-01 of $5,750. The
FAA grant Pre-Application has been submitted and should be processed in the coming months.
RECOMMENDATION
Staff requests consideration of Resolution R-25-04 to approve the PTGA FM453357-1-94-01 reflecting
state funds for the design phase of the terminal apron expansion at the Sebastian Municipal Airport and
authorizing the City Manager to execute the appropriate documents.
ATTACHMENTS:
1. Resolution R-25-04
2. PTGA FM453357-1-94-01
FUNDING SOURCE:
Expenditure required Amount Budgeted: Funding source
$5,750 $45,000 DST
Additional Funds Needed: $ 0.00