DESIGN “GOLF APRON” PHASE 1 DESIGN, BIDDING, AND PERMITTING SERVICES SCOPE & FEE
5550 W. IDLEWILD AVENUE,
SUITE 115,
TAMPA, FL 33634
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 1 of 7
EXHIBIT “A”
SCOPE OF WORK
DESIGN GOLF APRON PHASE 1
SEBASTIAN MUNICIPAL AIRPORT
PROJECT DESCRIPTION
The City of Sebastian and the Sebastian Municipal Airport (CITY) intend to construct a new Apron
known as “Golf Apron” on the north side of the Taxiway “G” to increase airport capacity and provide additional aircraft parking. The proposed apron will support future hangar development on the northwest side of the airport. The new Golf Apron will be 115 feet wide and 705 feet long, constructed
as a flexible pavement apron. The Apron will encompass the decommissioned Runway 13-31, which is 150 feet wide. The existing runway pavement exhibits significant distress, including potholes, longitudinal cracks with raveling, fatigue cracking, depressed areas, localized rutting, and oil deposits. The surface is oxidized and heavily raveled, resulting in a rough and unsafe condition with foreign object debris (FOD) from loose aggregates. The new pavement will correct
deficiencies in the apron grade and provide a durable surface free of rutting and loose aggregate, creating designated aircraft parking positions for future hangar development on the north side of Taxiway “G.” This project will extend the useful life of the existing pavement while providing a surface that meets or exceeds FAA grading requirements. The apron/ramp grade will be sloped at a minimum of 1% for 50 feet toward Taxiway “G,” in compliance with NFPA 415. The estimated construction cost is $1,300,000.
This scope and fee for services provided by Infrastructure Consulting & Engineering (ICE) will be for Design efforts, Permitting, and Bidding Services for said project.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 2 of 7
Phase 1 – 30% Plans:
ICE proposes to perform a structural and functional evaluation of the old runway pavement to
assess the condition of the pavement and determine if it requires additional structural overlay. ICE
proposes to perform a combination of nondestructive testing (NDT) and coring for a cost-effective
and comprehensive evaluation of the pavement.
This preliminary engineering phase is intended to identify the cause of the pavement structure
deficiencies and provide different engineering & construction alternatives for the Taxiway
construction and includes various studies which generally will include Existing Pavement
Structure strength evaluation, evaluation of pavement failures, determination of rehabilitation
alternatives and cost analysis for the rehabilitation alternatives.
Preliminary Engineering activities include:
1. Perform Site Visits in order to assess existing pavement and subgrade conditions including
the identification of all surface and subsurface deficiencies contributing to the pavement’s
poor performance.
a. Ground Penetrating Radar (GPR). GPR provides continuous measurement of
pavement thickness at highway speed (ASTM D6087). The thickness of the surface
course and also be determined from the GPR data to select an appropriate milling
depth. GPR testing is proposed to perform at 6’ offset lines along the old runway
to obtain a full coverage of the pavement thickness.
b. Coring. Core samples are proposed to be extracted from the pavement at selected
areas to examine the condition of the pavement layers as well as debonding between
the layers. Core results will also be used to verify the GPR data.
c. Borings shall be to approximately 10-20’ depth. Cores shall be only to the bottom
of pavement in order to define existing pavement section, with a frequency of one
bore per 10,000 sf per FAA’s “AC 15/5320-6G, Airport Pavement Design and
Evaluation”. A report will be generated in order to analyze and describe all
materials encountered, with identification of pavement failures and pavement
recommendations.
d. Survey elevation grid will be maximum of 50’x50’, except pavement areas and at
all grade breaks and elevation changes, including top of bank and toe of slope of
both sides of all ditches and swales to be 20’x20’ or as necessary.
2. Develop an AutoCAD drawing from DTM survey for use in modeling the old Runway
(New Golf Apron) Reconstruction.
3. Obtain and review any available historical documents: construction documents, as-builts
from previous projects to determine existing pavement structure.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 3 of 7
4. Analyze the existing pavement section.
5. Evaluation of the old runway 13-31 pavement based on geotechnical investigation above.
6. Incorporate results into the Preliminary Engineering Report.
7. Complete Preliminary Engineering Report including the various study elements:
a. Project Narrative
b. Topographical survey
c. Geotechnical investigation.
d. Existing Pavement Strength Evaluation:
e. Engineering judgment for probable cause of pavement failures
f. Design alternatives for pavement rehabilitation.
g. Conduct a construction cost estimates for each rehabilitation alternative.
h. Provide recommendation for preferred rehabilitation method.
8. Conduct in-house Quality Review for acceptable design practices and constructability.
9. Attend Pre-design Conference and review findings and discuss recommendations with
airport personnel and FDOT/FAA as required.
10. Coordinate with the Airport Staff to optimize available construction monies and minimize
the impacts in day-to-day operations of the airport.
11. Develop Projected Project Budgets
Phase 1 services will involve preliminary design and the production of 30% Plans. The design
considerations shall include:
• Geotechnical Investigation,
• Field Survey,
• General Coordination with Airport Staff,
• Pavement Design/Analysis,
• Horizontal and Vertical Geometrics,
• Preliminary Cost Estimates,
• Engineer’s Report,
The Consultant will prepare a revised Construction Cost Estimate, a 30% Engineer’s Report, and
the Preliminary Plans, which will include:
Cover Sheet Project Layout Plan
Typical Sections Demolition Plan
Profile Sheets
Deliverables: Three (3) copies of the Preliminary Plans in 11”x17” format and 30% Engineer’s
Report will be submitted to the CITY for distribution to airport staff.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 4 of 7
Phase 2 – 60% Plans
The Consultant shall address any changes requested by the airport at the 30% Review Meeting in
this Phase. Upon issuance of the Notice to Proceed, the Consultant will proceed with the 60%
Plans to include the following:
• General Coordination,
• Grading,
• OE/AAA submittal (including CSPP)
• Construction Safety and Phasing Plan,
• Coordination with SJRWMD.
• Updated Cost Estimates,
• Engineer’s Report
• Marking
• Signing
The Consultant will prepare a revised Construction Cost Estimate, a 60% Engineer’s Report, and
the 60% Plans, which will include:
Cover Sheet Project Layout Plan
Typical Sections Demolition Plan
Safety Plan Staking Plan
Preliminary Grading Plans General Notes
Preliminary Cross-Sections Marking Plan
Preliminary SWPP plans
The Consultant will meet with the City to review the Plans, Specifications, and the Engineer’s
Report to verify that all concerns, issues, and potential conflicts are addressed prior to proceeding
with 90% of the Construction Documents.
Deliverables: Three (3) copies of the 60% Plans in 11”x17” format and 60% Engineer’s Report
will be submitted to the CITY for distribution to airport staff.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 5 of 7
Phase 3 – 90% Plans
The Consultant shall address any changes requested by the airport at the 60% Review Meeting in
this Phase. Upon issuance of the Notice to Proceed, the Consultant will proceed with the 90%
Plans to include the following:
• Preliminary Front-End Documents,
• Preliminary Technical Specifications,
• Final Grading Design,
• Cost Estimates,
• Engineer’s Report,
• Submittal to SJRWMD
The Consultant will prepare a revised Construction Cost Estimate, a 90% Engineer’s Report, and
the 90% Plans, which will include:
Cover Sheet Project Layout Plan
Typical Sections Demolition Plan
SWPP plans Staking Plan
Safety Plan General Notes
Final Grading and Drainage Plans Final Cross Sections
Signing and Marking Plans Construction Safety and Phasing Plan
Miscellaneous Details Marking and Signage Plans
The Consultant will meet with the CITY to review the Plans, Specifications, and the Engineer’s
report to verify that all concerns, issues, and potential conflicts are addressed prior to proceeding
with Final Construction Documents.
Deliverables: Three (3) copies of the 90% Plans in 11”x17” format, a draft set of specifications
and front end documents, and 90% Engineer’s Report will be submitted to the CITY for distribution
to airport staff. A copy will also be sent to the FAA, and FDOT for review and comment.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 6 of 7
Phase 4 – Final Contract Documents
The Consultant shall address minor changes to the plans and any comments from City Procurement
for the bidding documents, and then proceed with the 100% Plans to include the following:
• Incorporate City Comments,
• Final Plans,
• Final Technical Specifications,
• Final Quantities.
• Final Front End Bidding Documents
The Consultant will prepare a Final Construction Cost Estimate, a 100% Engineer’s Report,
Bidding Documents and the Final Plans.
Deliverables): Three (3) copies of the 100% Plans in 11”x17”format, the final Engineer’s Report
and Contract Documents will be submitted to the CITY for distribution to airport staff, A copy will
also be sent to the FAA, and FDOT for their files. Two full sized sets (22”x34”) of signed and
sealed plans will be submitted for CITY records.
Grant Services
The consultant will coordinate during the project to provide and submit design and bidding status
reports to the FDOT and perform necessary coordination with the FDOT district office. Upon
design and bidding completion, ICE will submit all required project documentation to agencies.
Phase 5 - Bidding Services
The Consultant shall perform general coordination with the City and Bidders and will:
• Prepare for and attend the Pre-Bid Conference.
• Prepare and distribute addenda as necessary.
• Attend the bid opening.
• Assist the City in tabulating and evaluating bids; and
• Assist the City with the re-bid of the project if the City rejects the bids for any reason. This
work will be performed as an additional service requiring a negotiated contract, and
• Assist in the contract.
Other Provisions
a) The CITY will pay all costs associated with any permit application and/or impact fees.
b) Any mitigation of wetlands, impacts to threatened and endangered species, or other
environmental efforts beyond the scope of the Focused EA will be performed under a
separate agreement.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Scope of Services
Sebastian Airport, Design Golf Apron Phase 1 Page 7 of 7
OUT OF SCOPE ITEMS
a) Environmental design and services.
b) FAA Categorical Exclusion.
c) Dewatering Permit.
d) Construction Administration and Inspection Services.
PROJECTED PROJECT SCHEDULE
DESIGN PHASE SERVICES
Task Duration
Phase 1 – 30% Plans 60 Days
Phase 2 – 60% Plans 30 Days
Phase 3 – 90% Plans 30 Days
Permitting 30 Days
Phase 4 – Final Contract
Documents
30 Days
TOTAL PROJECT
DESIGN DURATION
180 days *
* Contingent on owner’s review time)
FEE
Exhibit B: Please see the attached detailed fee proposal.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
PHASE 1 PHASE 2 PHASE 3 PHASE 4 PHASE 5 TOTAL
30% Plans 60% Plans 90% Plans Final Contract Documents
Bidding Services
CLASSIFICATION RATES HOURS HOURS HOURS HOURS HOURS HOURS
Principal $255.00 5 4 6 4 0 19Sr. Project Manager $220.00 28 35 29 18 13 123Project Manager $200.00 18 6 6 16 12 58Senior Engineer $200.00 57 39 36 28 12 172Engineer$170.00 41 50 66 42 6 205Sr. Designer $140.00 57 50 49 18 4 178Designer$105.00 50 82 76 30 2 240Technician$90.00 48 56 64 54 2 224Administrative Assist.$70.00 44 41 49 24 36 194
TOTAL HOURS 348 363 381 234 87 1413 TASK COST $38,455.00 $41,540.00 $43,500.00 $27,410.00 $9,750.00 $160,655.00
DIRECT EXPENSES
Reproduction $250.00 $250.00 $250.00 $250.00 $250.00 $1,250.00Postage$50.00 $55.00 $75.00 $75.00 $75.00 $330.00
TOTAL EXPENSES $300.00 $305.00 $325.00 $325.00 $325.00 $1,580.00
Survey $6,700.00 $6,700.00Geotechnical Investigation $16,200.00 $16,200.00Ground Penetrating Radar (GPR) $2,400.00 $2,400.00Environmental Review Estimate $2,000.00 $2,000.00
TOTAL SUBCONSULTANTS $27,300.00 $0.00 $0.00 $0.00 $0.00 $27,300.00
TOTAL COSTS $66,055.00 $41,845.00 $43,825.00 $27,735.00 $10,075.00 $189,535.00Method of Payment Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum
SUBCONSULTANTS
EXHIBIT "B"Manhour and Fee Estimate Design Golf Apron Phase 1
Sebastian Municipal Airport Summary
Page B-1 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Sr. Project Project Sr.Sr Administrative TotalItem/Task Description Principal Manager Manager Engineer Engineer Designer Designer Technician Assistant Hours
Project Management 2 4 6Coordination with Airport 1 2 8 11Project Kick-Off Meeting 1 2 4 7Meeting with FDOT, FAA 2 4 6Coordination with Subconsultants 2 4 4 8 18Review Past stormwater permits 4 4 8Review available as-built info 2 4 4 10Preliminary Pavement Design/ Analysis 2 4 8 14Preliminary Drainage Evaluation, Review permits 8 8Evaluation of Existing Conditions 4 4Process Survey DTM 2 2 8 8 20Preliminary Fillet Design 0Horizontal Design 4 8 16 8 36Generate Profiles 4 8 8 4 24SJRWMD Pre-Application Meeting 4 8 4 2 18Update the Construction Cost Estimate 2 2 2 6Preliminary Construction Schedule 2 4 2 8
Cover Sheet 1 1 1 3Project Layout Plan 1 2 2 2 7Construction Safety and Phasing Notes 1 4 2 2 9General Notes 1 1 1 1 4Boring and Coring Plan 1 1 1 1 4Boring and Coring Logs 1 2 2 2 7Project Key Map 1 1 1 1 4Typical Sections 1 2 4 8 8 23Exist. Condition Plans 4 4 8 8 24Profile Sheets 4 4 8 8 2430% Engineer's report 2 4 8 14Quality Control Review 1 4 4 9Plot 30% 11"x17 plans (1 Copy)4 8 12
Total Hours:5 28 18 57 41 57 50 48 44 348
Prepare 30% Plans
MANHOUR AND FEE ESTIMATE
Phase 1 - 30% Design Plans
EXHIBIT "B"
Design Golf Apron Phase 1Sebastian Municipal Airport
Page B-2 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Sr. Project Project Sr.Sr Administrative TotalItem/Task Description Principal Manager Manager Engineer Engineer Designer Designer Technician Assistant Hours
Project Management 1 8 8 17Coordination with Airport 1 8 8 17Coordination with Subconsultants 1 2 4 7Prepare for Review Meeting, Attendance, Minutes 4 4 2 10
Pavement Design/ Analysis 2 4 8 14Drainage Evaluation, and Design 8 8Fillet Design 0Horizontal Design 8 8 16 16 48Generate 3D Profiles 8 8 8 8 32Coordination with SJRWMD 4 8 8 2 22Update the Construction Cost Estimate 2 2 2 6Preliminary Schedule 1 1 1 3
Construction Safety and Phasing Plans 1 4 2 2 9Staking and Demolition Plan 4 4 16 16 40Preliminary Grading Plan 4 4 8 8 24Preliminary SWPP Plans 1 2 4 8 8 23Drainage Details 4 4 8 8 24Preliminary Cross Sections 4 4 8 8 2460% Engineer's report 2 4 8 14Quality Control Review 1 4 4 9Plot 60% 11"x17 plans (1 Copy)4 8 12
Total Hours:4 35 6 39 50 50 82 56 41 363
Prepare 60% Plans
60% Design
MANHOUR AND FEE ESTIMATE
EXHIBIT "B"
Design Golf Apron Phase 1Sebastian Municipal Airport
Phase 2 - 60% Design Plans
Page B-3 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Sr. Project Project Sr.Sr Administrative TotalItem/Task Description Principal Manager Manager Engineer Engineer Designer Designer Technician Assistant Hours
Project Management 1 8 8 17Coordination with Airport 1 8 8 17Coordination with FDOT, and FAA 1 2 4 7Prepare for Review Meeting, Attendance, Minutes 2 4 2 8Preliminary Front End Documents 1 4 8 4 17Preliminary Technical Specifications 1 8 8 4 21
Finalize Pavement Design/ Analysis 2 4 4 10Finalize Drainage Evaluation, and Design 4 4Finalize Fillet Design 2 2 4Finalize Horizontal Design 4 4 8 8 24Generate 3D Cross Sections 4 4 8 4 20Prepare and Submit SJRWMD Permit Application 2 8 8 2 20Update the Construction Cost Estimate 2 2 4Final Schedule 1 1 1 3
Leveling Plans 4 4 8 8 24Grading and Drainage Plan 4 4 8 8 24SWPP Plans, Details and Notes 1 2 4 4 4 15Profile Sheets 4 4 8 8 24Drainage Details 4 4 8 8 24Marking Plans and Details 4 4 8 8 24Guide Sign Layout and Details 2 2 4 4 12Cross Sections 1 1 4 4 10Construction Details 1 4 4 4 1390% Engineer's report 2 4 8 14Quality Control Review 1 4 4 9Plot 90% 11"x17 plans (1 Copy)4 8 12
Total Hours:6 29 6 36 66 49 76 64 49 381
MANHOUR AND FEE ESTIMATE
Prepare 90% Plans
90% Design
EXHIBIT "B"
Design Golf Apron Phase 1Sebastian Municipal Airport
Phase 2 - 90% Design Plans
Page B-4 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Sr. Project Project Senior Administrative TotalItem/Task Description Principal Manager Manager Engineer Engineer Sr. Designer Designer Technician Assistant Hours
Project Management 1 1Coordination with Airport 1 1Prepare for Review Meeting, Attendance, Minutes 1 4 2 7Finalize Plans 8 12 12 24 40 96Calculate Final Quantities & Eng. Est. of Probable Cost 2 2 2 2 8Prepare and Submit OE/AAA 2 4 4 4 14Address comments 0Finalize Technical Specifications 8 10 4 22Finalize Front End Docs 4 4 4 12 24Assemble Bid Schedule 2 2 4Plot full size and 11"x17" Plans 4 4 8 16Prepare Final Engineer's Report 8 8 2 4 22Quality Review and Control 1 4 4 8 2 19
Total Hours:4 18 16 28 42 18 30 54 24 234
Phase 4 - Final Contract Documents
MANHOUR AND FEE ESTIMATE
EXHIBIT "B"
Design Golf Apron Phase 1Sebastian Municipal Airport
Page B-5 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Sr. Project Project Senior Administrative Item/Task Description Principal Manager Manager Engineer Engineer Sr. Designer Designer Technician Assistant Totals
General Coordination with City 2 2 2 2 4 12Prepare Pre-Bid Agenda 2 2 2 6Attend Pre-Bid Conference 2 2 4Prepare Minutes to Pre-Bid 1 2 4 7Answers to Bidders/Issue Addenda 2 2 2 2 2 2 2 8 22Review Bids for Responsiveness 2 2 2 2 8 16Certified Bid Tabs 2 2 2 8 14General Coordination with Low Bidder 2 2 2 6
Total hours:0 13 12 12 6 4 2 2 36 87
MANHOUR AND FEE ESTIMATE
Design Golf Apron Phase 1
Phase 5 - Bidding Services
EXHIBIT "B"
Sebastian Municipal Airport
Page B-6 of B-6
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Do
c
u
s
i
g
n
E
n
v
e
l
o
p
e
I
D
:
5
9
A
B
5
3
4
0
-
B
C
A
F
-
4
7
3
3
-
B
C
7
D
-
A
3
7
A
4
5
0
C
7
5
A
A
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
℄ EXIST. RW 13-31
NEW T/W GOLF
NEW TW 'G' 35'
1.0%
FUTURE APRON 'G' 115'
MIN. 0.5%
TW 'G' OFA 62'
TAXIWAY "G" TYPICAL SECTION
53'
TRANSIENT AIRCRAFT PARKING
17.5'
FUTURE BOX HANGARS
FUTURE APRON
RECONSTRUCTION
17.5'
Sebastian Municipal Airport
TAXIWAY 'G' RECONSTRUCT
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Item No.Spec. No.Item Description Quantity Unit Unit Price Amount
1 1530 Barricades 1 LS $25,000.00 $25,000.00
2 1720 Project Record Documents 1 LS $5,000.00 $5,000.00
3 2000 Construction Layout and As-built Survey 2 LS $20,000.00 $40,000.00
4 C-100 Contractor Quality Control Program (CQCP)1 LS $35,000.00 $35,000.00
5 C-102-1 Installation and removal of silt fence 750 LF $10.00 $7,500.00
6 C-102-2 Temp. Check Dam 3 EA $800.00 $2,400.00
7 C-105 Mobilization (10% Max.)1 LS $104,000.00 $104,000.00
8 1720 Project Record Documents 1 LS $8,000.00 $8,000.00
9 S-140-1 Bituminous Surface Removal (Up to 2") 9,010 SY $4.00 $36,040.00
10 S-140-1 Exist. Base Removal (Up to 19")9,010 SY $7.00 $63,070.00
10 P-152-1 Unclassified Excavation 1 LS $25,000.00 $25,000.00
11 P-152-2 Embankment 5,000 CY $15.00 $75,000.00
12 P-152-3 Clearing and Grubbing 1 LS $6,000.00 $6,000.00
13 P-160 12" Stabilized Subgrade 9,060 SY $15.00 $135,900.00
14 P-219 Recycled Concrete Aggregate Base Course 9,060 SY $18.00 $163,080.00
15 FDOT-334 Superpave Asphalt Concrete SP-12.5, 3" 1,550 TON $150.00 $232,500.00
16 FDOT-300 Bituminous Prime Coat 1,360 GAL $6.00 $8,160.00
17 FDOT-301 Emulsified Asphalt Tack Coat 1,360 GAL $6.00 $8,160.00
18 P-620-1 Reflective Pavement Marking 1 LS $8,000.00 $8,000.00
19 P-620-2 Non Reflective Pavement Marking 1 LS $4,000.00 $4,000.00
20 Aircraft Tie Down (Including Galvanized STEEL Anchor and Concrete Collar 1 LS $8,000.00 $8,000.00
21 D-701 Drainage 1 LS $30,000.00 $30,000.00
22 Apron Guidance Signs 1 LS $8,000.00 $8,000.00
23 FDOT-570 Performance Turf 1.00 AC $5,000.00 $5,000.00
24 T-904 Sodding 1.00 AC $6,000.00 $6,000.00
25 T-905 Topsoil Placement 200 CY $20.00 $4,000.00
$1,052,810.00
10% Construction Preliminary Estimate Uncertainty $105,281.00
ENG CONSTUCTION ADMIN. & INSPECTION (13%)$136,865.30
ADMIN. FEE $3,500.00
IFE $0.00
Total CONSTRUCTION FEE=$1,298,456.30
ENGINEERING DESIGN FEE Total DESIGN FEE=$240,000.00
Total PROJECT COST FEE=$1,538,456.30
Golf Apron for FY 2027
Sitework
Engineer's Opinion of Probable Construction Cost
DATE: February 3, 2026
Pavement Reconstruction
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Oakhurst Professional Park + 1309 S.E. 25th Loop + Suite 103 + Ocala, Florida 34471
PHONE (352) 622-3133 + FAX (352) 369-3771 + rmbarrineau.com
January 26, 2026
Hamed Jafarian, PE
Infrastructure Consulting & Engineering
5550 W. Idlewild Ave., Suite 115
Tampa, FL 33634
RE: Proposal for Topographic Surveying Services at Sebastian Municipal Airport,
Golf Apron Phase 1, City of Sebastian, FL
Dear Hamed:
Thank you for the Request for Proposal. R.M. Barrineau and Associates, Inc has
prepared the following Scope of Surveying Services and timeline for the referenced
project.
Scope of Services: Fee: $ 6,700.00
Topographic Surveying Services:
The services will be completed in accordance with the Standards of Practice for
Professional Surveyors and Mappers, as set forth in the Florida Administrative Code and
City of Sebastian Land Development Code Standards.
1. Elevation grid maximum of 50’x50’, except pavement areas and at all grade
breaks and elevation changes, including top of bank and toe of slope of both
sides of all ditches and swales to be 20’x20’ or as necessary.
2. All above-ground site features with descriptions including but not limited to
pavement edges (PC, PT, and approx. midpoint on curves), driveways,
sidewalks, walls, fences, signs (include sign message), buildings, pavement
markings, and any other visible physical improvement.
3. All underground site features and utilities with descriptions including but not
limited to water, sewer, storm sewer, power, communications/cable, and gas.
Obtain utility locate from Sunshine State One Call and survey painted locate
lines. Obtain data from any valve, clean out, manhole, junction box, meter, etc.
encountered on site. Include pipe inverts /conduit size and type for all
underground utilities or drainage. Include upstream and downstream locations
and inverts of storm or sanitary sewer pipes coming into or out of the site,
Reginald M. Barrineau, P.S.M., Founded 1988
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Page 2, Sebastion Golf Apron Ph 1
regardless of location.
4. Sufficient Control points. (Min. 3) within the Site Limits.
5. NAD 83 State Plane, Florida East Zone (1990 adjustment) for Horizontal
control datum.
6. NAVD 88 for vertical control datum.
7. Provide deliverables:
a. In AutoCAD 2020 format complete with contours, breaklines,
features, callouts, spot elevations, symbols, and control points.
b. Signed and sealed hard copy matching the provided cad file.
c. ASCII point file in .txt or .csv format including Northing, Easting,
Elevation, and Description. Include a text or pdf file with a list of the
meaning of all abbreviations used.
Schedule for Surveying Services:
Estimated timeline for Survey to is four weeks from notice to proceed.
Terms of this proposal are valid for 30 days from date of proposal. If you have any
questions regarding the proposal, please do not hesitate to contact our office. If the
terms are acceptable, please email authorization to proceed and we will schedule the
project. An invoice will be submitted upon completion of the project, with payment due in
30 days. Thank you for the opportunity to submit a proposal for this project.
Sincerely,
Diane Barrineau
Diane Barrineau, CFO
R.M. Barrineau and Associates, Inc.
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098
Document ID: F3C3E0BEEF4CD26B431CD04D6F075098