Schumann Drive Irri.qation System
As referenced in the attached Notice of Award/Notice to Proceed, please be
advised that the Schumann Drive Irrigation System Installation Program will
officially begin Monday July 22"d, pursuant to the Agreement with Irrigation
Consultants Unlimited, Inc. authorized during your June 26th regular
meeting. This arrangement will also incorporate additional plantings to
accommodate and beautify Schumann Drive medians and the thoroughfare
itself. Work is anticipated to take approximately five weeks. By contract
however, Irrigation Consultants Unlimited, Inc. has six weeks to complete
the job.
Runway 4-22 Li,qhtin.q Installation
As referenced in the attached second Notice to Proceed, please be advised
that the Sebastian Municipal Airport (SMA) Runway 4-22 Edge Lighting
Program will begin Tuesday July 23rd. This project will take a considerable
amount of time to implement, approximately five months or so. As such,
Runway 4-22 will cease operations for brief periods of time during
construction. In addition, all SMA runways may have to be closed for a few
hours to accommodate specific improvement activities between the Runway
13-31 and 4-22 intersection. Airport Director Jason Milewski will maintain
communication with all tenants and airport users for the duration of the
project, so as to provide continuous updates accordingly.
Lund Property on Louisiana Avenue-
You will recall a presentation during your last meeting by Louisiana Avenue
resident Mark Lund relative to his request to have the City of Sebastian
City Council Information Letter
July '19, 2002
Page 2
waive a four-year-old $7,500 lien levied against his single-family residence
located at 1053 Louisiana Avenue. My office has recently learned that the
house is for sale. As such, in addition to his unwillingness to work with the
Code Enforcement Division to address additional violations that may exist at
and around his property, I cannot recommend working with his family to
forgive the lien. As I am sure that you are aware, liens and other
assessments are typically required to be satisfied prior and/or during such
real estate transactions. Accordingly, the City of Sebastian should not be
subjected to a contrary practice.
Parks Improvement Public Workshop
Various staff members, including myself will likely participate in tomorrow's
Parks and Recreation Advisory Committee Workshop. This arrangement
will be extremely helpful in that specific plans can be formally considered by
administration in compiling cost figures and overall scope of development
for future parks. Such dynamics are necessary to incorporate respective
final recommendations into the City of Sebastian's Capital Improvement
Program and Fiscal Year 2002/2003 Recommended Budget. As such, you
will notice a Parks and Recreation Advisory Committee report regarding the
July 20th workshop listed in your July 24th meeting agenda. Hopefully, both
meetings will foster solid productivity.
Enclosure(s):
Notice to Proceed -Schumann Drive Irrigation System
Notice to Proceed - Runway 4-22 Edge Lighting
My Documents/InfoLetter141
HCh~I~ OF PELIC. AN I~LAND
NOTICE OF AWARD
NOTICE TO PROCEED
Schumann Drive Irrigation
DATE: July 17, 2002
TO:
Ruben Koch, President
Irrigation Consultants Unlimited, Inc.
d/b/a Ra nforest Irrigation
125 43rd Avenue
Vero Beach, Florida 32968
You are hereby notified that the City of Sebastian City Council awarded the Schumann Ddve
rri,qation Proiect to your firm on June 26, 2002 as had been conveyed to you verbally on prior
occasion.
Further, you are hereby notified to commence work on July 22, 2002 (as agreed verbally)
pertaining to the signed Agreement dated July 17, 2002, in the amount of $48,468.52. Your signed
proposal warrants completion time of not to exceed 6 weeks from the commencement date stated
herein. Therefore, your attention is called to the Liquidated Damages clause in the amount of
$150.00 per day for each day the project completion date is late. The completion time shall be
extended by the City contingent on the City providing power as required by the Contractor.
The Project Manager is Mr. Chris McCarthy, Parks & Maintenance Supervisor. All substantial
communication pertaining to this project should be directed to him.
Congratulations and we look forward to working with you on this project.
Paul Wagner, ~;ral Services Administrator
HOOF. O~ ~I~IC,6~ LSLAND
NOTICE TO PROCEED
Runway 4-22 Ed.qe Lighting
DATE: July 17, 2002
TO:
Brenda P. Green, President
Jaco Airfield Construction, Inc.
1071 Greensboro Road, N.E.
Eatonton, Ga. 31024
You are hereby notified to commence work on July 23, 2002 as agreed in
the Pre-Construction Meeting held July 16, 2002, pertaining to the signed
Agreement dated June 29, 2002, in the amount of $236,886.44. The agreement
warrants completion time of 150 consecutive calendar days from the
commencement date stated herein. Therefore, your attention is called to the
Liquidated Damages clause in the amount of $250.00 per day for each day the
project completion date is late.
The Project Manager is Mr. Jason Milewski, Airport Director. All substantial
communication pertaining to this project should be directed to him.
We look forward to working with you on this project.