HomeMy WebLinkAboutChapter 6 - Airport Alternatives
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
AIRPORT ALTERNATIVES
"'''.
:5J,J}?'.c5"JJAl'i
~>~.-... ..~.
""-----: .' ~~
HOME or PWC.AN l'iLAND
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~~
.. -- (:" - - .
-~'''''.'' ---"
HOME Of PWCAN ISlAND
Chapter Six - Airport Alternatives
INTRODUCTION
Once the facilities required for the planning period have been identified, the next step in the master planning
process is to evaluate the various ways those facilities can be provided. The possible combinations of alternatives
are countless, so some intuitive judgment must be used to identify those alternatives, which have the greatest
potential for implementation. Three major elements must be considered in the development alternatives at
Sebastian Municipal Airport. These include alternatives for the airfield, general aviation facilities, and
navigational aids. In addition, the utilization of the remaining airport property to provide revenue support for the
airport and benefit the economic development and well-being of the Sebastian area must be considered after the
development alternatives are defined.
Each element inter-relates and affects the development potential of the others. Therefore, all areas must be
examined both individually and then coordinated as a whole to ensure the final plan is functional and efficient, as
well as cost effective. When analyzing alternatives for development, consideration must first be given to a "do
nothing" or "no build" alternative. These alternatives are not without major impacts and costs to the public; they
are addressed in the following sections of this chapter. The alternatives considered are compared using
environmental, economic, and aviation factors to determine which of the alternatives will best fulfill the local
aviation needs. With this information, as well as the input and direction of the Technical Review Committee, a
final airport concept can evolve for refinement into a realistic development plan.
General
In analyzing and comparing the benefits of various development alternatives, It IS Important to consider the
consequences of no future development at Sebastian Municipal. The "do-nothing" alternative essentially
considers keeping the airport in its present condition and not doing any improvements to the existing facilities.
The primary result of this alternative would be the inability of the airport to safely accommodate the existing
demand, much less the projected.
It should be pointed out here that any development proposed in the master plan evolves from an analysis of
projected needs over a set period of time. Even though the needs were determined by reliable methods, it cannot
be assumed that future events will not change these needs. The master plan attempts to develop a viable scheme
for meeting the needs brought about by projected demands for the next 20 years. No scheme should be adopted
that would assume expansion beyond the 20-year period or that would require expensive commitments prior to
the certainty of need. However, the plan should allow for flexibility to expand beyond the plan, should the need
arise. In addition, no plan of action should be developed that is not consistent with the goals and objectives of the
City, which has a vested interest in the results of any development or lack thereof. Sebastian Municipal should be
developed so that the facilities accommodate the demand and minimize any operational constraints. While these
objectives may not be all inclusive, they should provide a point of reference in the alternatives evaluation process.
In the preceding chapter, both airside and landside facility requirements were identified for the 20-year planning
period. While the previous sections have identified and quantified facility needs, they have not addressed the
options for providing these requirements, nor have they explored issues of operational efficiency and community
acceptance of meeting the identified needs of the airport over the planning period. This chapter reviews each of
the identified needs and discusses the pros and cons of various options designed to address the facility
requirements previously discussed.
2002
6-1
I
I
I
I
I
I
I
I
! I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST!AN
~
~...s::.~
HOME Of PUK:AN lSlAND
The facility requirements indicated the need for various airfield improvements, including pavement
rehabilitations. Without improvements and rehabilitation of existing pavements, areas will fall into disrepair.
This would seriously affect the capability of the airfield to continue serving users and the community. Expanding
facilities at the airport is also necessary over the next 20-years. To ignore this would restrict the growth of
aviation in the local area and region. This would, in turn, reflect on commerce and economic growth in the
regIOn.
Thus, the "do-nothing" alternative is inconsistent with the long-term goals of the City of Sebastian. In addition,
the airport has made assurances to the Federal Aviation Administration (FAA) in accepting past federal grants for
airport improvement projects that the facility will be operated at all times in a safe and serviceable condition. It
would represent an irresponsible action affecting the long-term viability of the airport and the airport's service
area. Therefore, the "do-nothing" alternative is not considered prudent or feasible.
The ultimate goal of the master planning process is to provide the City of Sebastian with an assessment of the
adequacy and capabilities of the airport as well as the identification of the best options available for addressing
future development needs at the facility. To accomplish this goal it is necessary to identify and evaluate
alternatives for meeting the needs identified in the previous chapters and ultimately provide the City with a
planning framework on which to base future airport development decisions.
Airport Considerations
The ultimate objective is to develop balanced airside and landside facilities to serve all segments of the forecast
aviation demand. Prior to defining and evaluating specific airport alternatives, development objectives to guide
the evaluation should be identified. The City of Sebastian wants to market, develop, and operate the airport so as
to better the economic base of the surrounding area. The successful realization of this role can be facilitated if the
City focuses on the following objectives:
+
+
+
Obtain the maximum service level of the airfield to the community.
Operate the airport as an attractive, easy-to-use, safe, and environmentally compatible facility.
Market and develop the airport facilities and available land as unique business opportunities.
In addressing these objectives, development of facilities should be undertaken in such a manner as to minimize
existing and potential operational constraints. Flexibility in airport development is essential to assure adequate
capacity should market conditions change unexpectedly.
In approaching the analysis of alternatives to meet identified airport facility needs, it is necessary to keep in mind
a number of factors, or considerations that impact and influence future development at Sebastian Municipal.
These considerations form a basis for the initial identification of options as well as providing a set of issues that
need to be kept in mind throughout the review and selection of alternatives. It should be noted that the goal of the
Master Plan is to mitigate to the maximum extent possible all of the factors that adversely impact the airport's
ability to meet demand or to comply with airport standards. While this goal is attainable, it must often be
weighed against the financial, social, and political costs of doing so. As a result, it is possible that the result of the
alternatives analysis may be to find that not all of the identified facility requirements at the airport can be fully
addressed and some must be left unfulfilled or only partially mitigated. A number of factors must be considered
in the alternatives analysis, and some of the more significant of these that impact or influence the alternatives are
listed below.
+
Only a few parcels, some impacted by environmental conditions remam for future aviation related
development at the airport.
2002
6-2
I
I
I
I
I
I
I
I
I
I
'I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~'
. .._'.'..... '" --.
-..,.- '~"'-', --
HOME Of PWCAN IStAND
+ The Sebastian Municipal Golf Course takes up a significant portion of the developable land to the south
and east of the airfield.
+ No property acquisitions can be made to the existing airport property boundary that would enhance the
aviation or non-aviation related development.
+ Any development in the infield portions of the existing airfield configuration will generate significant
difficulties with respect to airside and landside access for all tenants.
+ The City of Sebastian is on the verge of exhausting all available commercial and industrial land within the
City limits (outside of the airport property line).
The preceding considerations have been factored into the identification of potential alternatives to address the
facility needs identified. These issues should also be kept in mind when reviewing the following sections due to
the impact they may have on the options that have been identified. These concerns are very real, and if money
were not a concern, they could certainly be mitigated; however, funding is a considerable factor in any analysis of
options and, as such, many of the alternatives are designed to mitigate issues without having to undertake the
extensive relocation or reconfiguration of the entire airport property. The following sections outline options that
were identified, and discuss the positive and negative features of each.
AIRFIELD ALTERNATIVES
Airfield facilities are, by their nature, the focal point of the airport complex. Because of their primary role and the
fact that physically, they dominate airport land use, airfield facility needs can be the most critical factor in the
identification of viable airport development alternatives. In particular, the runway system requires the greatest
commitment of land area and has the greatest effect on the alternatives evaluation.
Previously, the demand/capacity analysis showed that the airport, even without improvements, would not
experience any problems related to either airfield capacity or delay during the planning period. However, two
factors of the airfield system were identified in the facility requirements chapter as being deficient for the
planning period. These include the existing pavement conditions and the ultimate configuration of taxiways for
airfield access. The following sections will analyze alternatives, which provide options to improve these
conditions.
Runway Alternatives
The alternative to re-open Runway 9-27 and close Runway 13-31 was selected in the 1993 Master Plan as a result
of numerous public sessions focused on achieving compatibility between the airport and community. Selection of
this option incorporated a dual runway system with Runway 9-27 as the primary and Runway 4-22 as the
crosswind. It was determined that Runway 4-22 provided better wind coverage than Runway 13-31, and offered
less impact on the residents from overflights. In addition to its inclusion in the 1993 Master Plan, an
Environmental Assessment for the re-opening of Runway 9-27 was also approved as part of the study.
Unfortunately, eight years later, this alternative has never been realized. The primary reason Runway 9-27 has
not re-opened was due to the costs required under the previous analysis. Nonetheless, the option of re-opening 9-
27 is still appealing, not only for the reasons included in the previous master plan, but also due to many other
advantages that can be realized for the airport and community as a whole. The interest now is to re-evaluate the
option of opening Runway 9-27, with respect to the existing configuration. The most important element of this
re-evaluation is to determine if the re-opening is still possible, primarily with respect to the available funding.
During this re-evaluation, a significant cost saving measure was realized with respect to the airport configuration.
A crosswind runway is recommended at an airport when a runway orientation cannot provide 95 percent wind
2002
6-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTIAN
~~
HOME Of PUICAN ISlAND
coverage for any aircraft forecasted to use the airport on a regular basis. This 95 percent coverage is based on a
crosswind that does not exceed 10.5-knots for aircraft with Airport Reference Codes (ARC) of A-I and B-I. A 13-
knot crosswind component is used for the ARCs A-II and B-II. The current (Twin Otter) and future (King Air
200) critical aircraft for Sebastian Municipal share an ARC of B-II. Based on the wind rose data, Runway 4-22
currently provides 97.2 percent coverage for a 13-knot wind. Likewise, Runway 13-31 or the alignment for
Runway 9-27 could also provide coverage over 95 percent for the 13-knot wind. However, as documented in the
facility requirements, the need for a crosswind runway is required for aircraft with ARCs of A-lor B-1, since none
of the three alignments can provide this individually. As such, any runway used to provide the 95 percent
crosswind coverage would only be required to meet the design standards of ARC B-I.
Under the previous master plan, once re-opened, Runway 9-27 would serve as the primary and Runway 4-22 as
the crosswind. However, due to the reconstruction of Runway 4-22 in 1997 to a length of 4,024 feet, as well as
the more recent improvements to lighting, and the fact that it provides the necessary crosswind coverage for the
airport's critical aircraft, this runway is now considered the primary. Under the 10.5-knot wind analysis, the two
runways provide nearly identical coverage with Runway 4-22 and Runway 9-27 providing 91.1 percent and 92.0
percent respectively. Therefore, the following alternatives analysis will re-evaluate the re-opening of Runway 9-
27 or the preservation of Runway 13-31 as the crosswind runway. In doing so, this evaluation will incorporate the
design standards for ARC B-1 versus B-II, on the crosswind runway.
Nearly all of the aircraft with an ARC of A-lor B-1 are categorized as small airplanes (less than 12,500 pounds)
with less than 10 passenger seats. A runway length of 3,080 feet will accommodate 95 percent of the small
airplanes with less than 10 passenger seats. This calculation, which is based on the FAA's Airport Design
software, is reflected in Table 5-3 of the preceding chapter. However, the FAA Airports District Office (ADO) in
Orlando recommended using a length of 3,200 feet. The ADO made this recommendation to provide a crosswind
runway with 80 percent of the length of the primary runway (which is 4,024 feet). Therefore, 3,200 feet will be
used in alternatives analyses. A width of 60 feet is required for visual and not lower than % of a mile visibility
runways, serving aircraft with an ARC ofB-I. However, because the airport serves B-II aircraft and both Runway
13-31 and the pavement for Runway 9-27 are 150 feet wide, a runway width of 75 will be analyzed in all of the
crosswind runway alternatives. In addition to enhancing the safety of the facility, this will preserve the option to
utilize this runway for Design Group II aircraft in the future (under visual and not lower than % mile visibility
conditions). The following sections address three crosswind alternatives for Sebastian Municipal.
Alternative A - Re-opening of Runway 9-27
This alternative is nearly identical to the selected alternative of the 1993 Master Plan. The primary
difference being that under this version, Runway 9-27 would serve as the crosswind runway for the
airfield, thus would only need to provide an overall length of 3,200 feet. As described in the previous
section, the width of this runway would be 75 feet wide. The runway has been aligned along the
centerline of the existing ISO-foot wide pavement, to balance the clearance between existing airport
structures and the transitional surfaces associated with the runway. It is recommended that the removal of
any runway pavement coincide with the construction of a parallel taxiway so that credit can be received
against this addition of pavement. This alternative is depicted on Exhibit 6-1.
2002
6-4
I.
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST!AN
~.,
-.p ~~. ,
-,- '- .-....;
HOME Of PtUCAN ISlAND
I
I
Because of the small aircraft designation (less than 12,SOO pounds), Runway 9-27 will only require a 20: I
approach slope surface for either visual or non-precision instrument approaches. Thus, the Runway 9
threshold has been configured so that the approach slope surface will provide more than the required IS
feet of vertical clearance over public roads specified in Federal Aviation Regulation (FAR) Part 77. This
ensures that the alignment of Airport Drive West is not affected by this alternative. On the opposite end,
the runway length of 3,200 feet places the approach surface for Runway 27 in a position that allows for
more than IS feet of clearance within the existing airport property line. This preserves the ability to allow
future access into the currently vacant area located between the approach ends of Runway 22 and Runway
27.
I
I
I
I
The following sections address both positive and negative considerations for this alternative. These pros
and cons are summarized in Table 6-1.
Positive Considerations
I
I
As detailed in the previous master plan, one of the more significant advantages associated with
the re-opening of Runway 9-27 will be the ability to serve aviation operations while creating less
of an impact to the adjacent residential communities. In addition, the re-opening of Runway 9-27
will create an airfield configuration that will open up nearly three times the developable area to
the north (143 acres versus 48 acres).
I
I
Currently the City of Sebastian is approaching a point where no more land within the City limits
(outside of the airport property) is available for industrial development. Under this alternative,
the airfield will provide approximately an additional 100 acres ofland that would be developable
as aviation and non-aviation industrial/commercial land. It is felt that this significant increase
will ultimately outweigh the additional costs associated with re-opening Runway 9-27 through the
community benefits it will provide. These benefits are primarily expected to result from the form
of additional jobs and tax base.
I
I
I
I
With respect to pavement conditions, the condition of the Runway 9-27 alignment is nearly the
exact same as that of Runway 13-31. The U.S. Navy constructed all four ofthe original runways
at Sebastian in 1943 to a length of 4,000 feet and a width of ISO feet. It has been estimated that
the pavement structure for each contains a one and a half inch asphalt surface with eight inches of
base. Since that time, there have been no significant improvements to the pavement of Runway
13-31 or the Runway 9-27 alignment. Therefore, the pavement of the old Runway 9-27
alignment will not require any more or less reconstruction than that of Runway 13-31. In fact, the
reconstruction of Runway 9-27 can occur without the need to shut down Runway 13-31.
I
An additional benefit to the Runway 9-27 and Runway 4-22 configuration is that this layout will
significantly simplify the taxiway system for the airfield. Currently a majority of the airfield
development is between the approach end of Runway 13 and the alignment of Runway 9-27. A
full-length parallel taxiway on the north side of Runway 9-27 would allow unimpeded aircraft
movements to the ends of Runway 9, 22, and 27. Access to Runway 4 would still require taxiing
aircraft to cross the Runway 9 threshold. If Runway 13-31 remains open, only half of the runway
ends can be accessed without crossing a runway. Similarly, two parallel taxiways to Runway 13-
31 would have to be constructed in order to serve aviation related development on both sides of
the runway, and yet crossing runways would still be required half ofthe time.
I
I
I
2002
6-6
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEB~T!AN
~
~~
HOME Of mlCAN ISlAND
I
Negative Considerations
I
Obviously, the re-opening of Runway 9-27 will require the relocation of the facilities located at
each end. On the Runway 9 end, there is a building (approximately 10,000 square feet) occupied
by Velocity Inc. and Golden Horn Aviation. This building is located on the south portion of the
leasehold held by Velocity. A relocation of this facility, which would also include four acres of
Velocity's leasehold, is depicted on Exhibit 6-1. The relocation of this building incorporated
input from Velocity so that it would not interfere with their future plans. On the Runway 27 end,
the entire JS Aviation leasehold (approximately two acres) will also need to be relocated. This
would include the relocation of approximately 40,000 square feet of aircraft parking ramp, the
3,700 square foot building, the fuel farm, parking lot, and a shade hangar.
! I
I
I
I
Because of the location of the approach surface to Runway 27, it will also be required for the
entire II th hole and at least the tee-box of the I ih hole at the Sebastian Municipal Golf Course to
be relocated. Similarly, there will be a requirement to remove trees at both ends of the runway
that would penetrate the approach slope. Additionally, for the approach to Runway 9, two of the
power poles located along the right-of-way for Roseland Road will have to either be lowered or
removed and the utility placed underground.
I
I
TABLE 6-1
COMPARISON OF ISSUES - RUNWAY ALTERNATIVE A
Pros Cons
Less impact to residential communities. Requires relocation of two tenants.
Triples land available for development. Requires changes to City golf course.
Same pavement condition as Runway 13-31. Requires tree removal.
Does not require dual parallel taxiways. Requires changes to two power poles.
Source: THE LP A GROUP INCORPORATED, 2001.
I
I
Estimated Costs
I
I
I
I
The cost estimate for this alternative is based on data reviewed for current or recent similar
projects. The details of the alternative development were consolidated into several general cost
categories. Unit costs were determined for each category and then applied to the unit
requirements for the alternative. Table 6-2 summarizes the development categories and cost
estimates for the alternative.
I
I
I
I
2002
6-7
I
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTIJ\N
~._'
~- ,"-"" -. ----.
- .~... .'-'.
HOME. Of PWCAN ISLAND
TABLE 6-2
COST ESTIMATE SUMMARY - RUNWAY ALTERNATIVE A
Item Amount Unit Cost Total Cost
Asphalt Pavement Removal 22,000 SY $5.00 $110,000.00
Asphalt Pavement Reclamation 26,000 SY $3.00 $78,000.00
Unclassified Excavation 5,000 SY $8.00 $40,000.00
Proof rolling 26,000 SY $1.00 $26,000.00
Limerock Base Course (3 ") 2,300 CY $30.00 $69,000.00
Bituminous Surface Course (3") 4,500 tons $45.00 $202,500.00
Bituminous Prime Coat 6,800 gallons $2.00 $13,600.00
Reflectorized Pavement Marking 5,000 SF $1.00 $5,000.00
Drainage Lump Sum $15,000.00 $15,000.00
Grassing 8 acres $2,000.00 $16,000.00
Sodding 7,000 SY $3.00 $21,000.00
Topsoil Placement 3,800 CY $5.00 $19,000.00
Mobilization $43,057.00
Contingencies (14% of Construction Costs) $86,114.00
Engineering (Design, Bidding, Construction, Inspection) $148,854.00
Relocation of Velocity Leasehold and Building $225,000.00
Relocation of JS Aviation Leasehold and Facilities $300,000.00
Golf Course Renovations (111ll & I r hole) $250,000.00
Lower or remove two utility poles (approach to Runway 9) $75,000.00
Tree clearing for both approaches (approximately 17 acres) $25,000.00
TOTAL $1,768,125.00
Source: THE LPA GROUP INCORPORATED, 2001.
Alternative B - Rehabilitate Existing Runway 13-31
Currently Runway 13-3 I is 4,021 feet long at a width of ISO feet. While it has been shown that this full-
length is not required, this alternative looks to preserve the existing pavement available at the airport.
This alternative does however recommend the removal of half of the runway pavement, thereby providing
an overall width of 75 feet. Exhibit 6-2 provides a depiction of this runway alternative. Essentially, this
alternative makes no changes to the airfield configuration, with the exception of the eventual pavement
removal. Again it is recommended that the removal of any runway pavement coincide with the
construction of a parallel taxiway so that credit can be received against this addition of pavement.
The following sections address both positive and negative considerations for this alternative. These pros
and cons are summarized in Table 6-3.
2002
6-8
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlB~T~
~....~~-,
~~~
HOMI Of rtL.KAN tslAND
I
Positive Considerations
I
This alternative can be considered a no-build option for the runway system. It obviously benefits
from the fact that the airport is currently operating under this configuration, which more than
adequately provides the necessary wind coverage. The costs associated with reconstructing the
existing pavement structure are similar to the unit costs that would be born for any other
pavement at the airport (with the exception of Runway 4-22). An additional advantage to this
alternative exists with the fact that no tenants will have to be relocated.
I
I
Negative Considerations
I
Foremost, a significant negative aspect to this alternative is that preserving the existing Runway
13-31 configuration does not address any of the issues or concerns that were discussed in the
previous master plan. By maintaining the current airport configuration, aircraft will continue to
over fly some of the more densely populated neighborhoods surrounding the airport. Not only
would this ignore the community concerns, it would negate the validity of the previous master
plan, including the environmental assessment element of that study.
I
I.
I
A serious impact associated with this alternative is that it severely limits the amount of
developable land available at the airport. Eventually this would restrict the amount of aviation
and non-aviation revenue that could be generated on the airfield. On the operational side, parallel
taxiways on the north and south side of Runway 13-31 would eventually be required to provide
airfield access to the developable areas. These parallel taxiways are the only way to minimize the
number of runway crossings. In addition, the development of the infield areas would require
landside access to disrupt the north-south taxiway (at a minimum), the east-west taxiway, or both,
resulting in significant taxi distances for most airport users.
I
'I
I
I
TABLE 6-3
COMPARISON OF ISSUES - RUNWAY AL TERNA TIVE B
Pros Cons
Maintains existing airfield configuration. Still impacts residential communities.
Provides more than adequate wind coverage Limits the amount of developable land.
Does not impact existing tenants. Eventually requires additional taxiways.
Does not disrupt airfield development. Ultimately increases taxi distances.
Source: THE LPA GROUP INCORPORATED, 2001
I
Estimated Costs
I
The cost estimate for this alternative is based on data reviewed for current or recent similar
projects. The details of the alternative development were consolidated into several general cost
categories. Unit costs were determined for each category and then applied to the unit
requirements for the alternative. Table 6-4 summarizes the development categories and the cost
estimates for the alternative.
I
I
I
2002
I
6-10
I
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~~
.r> ~ _
",~~ --
HOME Of PWCAN &AND
TABLE 6-4
COST ESTIMATE SUMMARY - RUNWAY ALTERNATIVE B
Item Amount Unit Cost Total Cost
Asphalt Pavement Removal 34,000 SY $5.00 $170,000.00
Asphalt Pavement Reclamation 34,000 SY $3.00 $102,000.00
Unclassified Excavation 5,000 SY $8.00 $40,000.00
Proof rolling 34,000 SY $1.00 $34,000.00
Limerock Base Course (3") 2,800 CY $30.00 $84,000.00
Bituminous Surface Course (3 ") 5,500 tons $45.00 $247,500.00
Bituminous Prime Coat 10,000 gallons $2.00 $20,000.00
Reflectorized Pavement Marking 5,000 SF $1.00 $5,000.00
Drainage Lump Sum $15,000.00 $15,000.00
Grassing 8 acres $2,000.00 $16,000.00
Sodding 7,000 SY $3.00 $21,000.00
Topsoil Placement 3,800 CY $5.00 $19,000.00
Mobilization $54, 145.00
Contingencies (14% of Construction Costs) $108,290.00
Engineering (Design, Bidding, Construction, Inspection) $187,187.00
TOTAL $1,123,122.00
Source: THE LPA GROUP INCORPORATED, 2001.
Alternative C - Modify and Rehabilitate Runway 13-31
Under this alternative, the length of Runway 13-31 would be reduced from the current 4,021 feet to 3,200
feet, while the width would remain the same as the other alternatives, at 75 feet. This reduced length
would begin at the same threshold as the current Runway 13 end and would extend to a point just beyond
the intersection with Runway 4-22. This layout is depicted in Exhibit 6-3.
As with Alternative B, this option preserves the existing airfield configuration and pavement. In addition
to removing half of the runway pavement, for an overall width of 75 feet, it is recommended that the
remaining runway length (921 feet) ultimately be removed. With the exception of runway length, this
alternative does not change the airfield. To obtain credit for the pavement removal, it is recommended
that any pavement removal occur with the construction of either one or both parallel taxiways.
The following sections address both positive and negative considerations for this alternative. These pros
and cons are summarized in Table 6-5.
2002
6-11
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~.,
___ ,r- ".;:' _'_'
- .~'.'~ -
-.- .'
ttOMl Of PUJCAN ISLAND
I
Positive Considerations
I
All of the benefits associated with Alternative B are retained with this option. However, due to
the decreased runway length, this alternative has additional advantages. The most obvious of
which is the reduced costs to reconstruct the runway pavement, which is reflected in the
construction estimate. Also, the ability to remove more pavement for potential credit is a positive
aspect to this alternative. The description for this alternative recommended the removal of the
unused portion of the runway, when needed to obtain credit for the construction of any new
impervious surface, such as the parallel taxiways. When this occurs, the taxiway connecting the
leasehold of JS Aviation to the end of Runway 31 will no longer be required. Similarly, the
partial parallel taxiway between Runway 4-22 and Runway 31 will not be needed.
I
I
I
I
It should be noted that while a parallel taxiway is shown on both sides of the Runway 13-3 I , the
current partial parallel is to a width of 50 feet and with a centerline separation of 400 feet. The
future parallel taxiways will only need to have a centerline separation of 240 feet and a width of
35 feet. This smaller separation becomes particularly important for this option since it provides
an additional 160 feet of developable land in the infield areas.
I
I
A more significant benefit related to the reduced runway length of this option relates to the
impacts it has on the surrounding community. By moving the threshold of Runway 31
approximately 921 feet toward Runway 4-22, the traffic using this runway will also move. This
lessens the impact that overflights to Runway 13-3 I have on the communities located to the east
and southeast of the airport. This occurs because most aircraft would make their base leg turn
(perpendicular to the final approach) earlier. While this will not eliminate community
overflights, it should reduce the number and lessen the impact due to the higher altitude these
aircraft will be on final approach.
I
I
NeKative Considerations
I
While the overflight impact to surrounding communities would be reduced under this option, it
still does not completely satisfy the issues or concerns that were discussed in the previous master
plan. Thus, as with Alternative B, this configuration tends to disregard the community concerns,
which as stated previously, ultimately contradicts the validity and effort of the previous master
plan.
I
I
Other negative characteristics associated with the shortened Runway 13-31 are the same as with
Alternative B. This layout poses a severe limitation on the amount of land that is available on
airport property for development, both aviation and non-aviation related. Although the overall
lengths are decreased, this option will also ultimately require parallel taxiways on both sides of
the runway to provide the safest access to and from future aviation related areas. Finally, this
option still creates the problem associated with developing the infield areas with respect to
landside access and taxi distances.
I
I
I
I
2002
I
6-13
I-
I
I
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTL\N
~.,
__ .r-" .
----:-....,~ -..;; .-,
HOME. Of PWC.AN I::Sl.AND
TABLE 6-5
COMPARISON OF ISSUES-RUNWAY ALTERNATIVE C
Pros Cons
Slightly reduces impact to community. Still negates benefits of previous study.
Maintains existing airfield configuration. Limits the amount of developable land.
Provides the required wind coverage. Eventually requires additional taxiways.
Does not impact existing tenants. Ultimately increases taxi distances.
Source: THE LPA GROUP INCORPORATED, 2001.
Estimated Costs
The cost estimate for this alternative is based on data reviewed for current or recent similar
projects. The details of the alternative development were consolidated into several general cost
categories. Unit costs were determined for each category and then applied to the unit
requirements for the alternative. Table 6-6 summarizes the development categories and the cost
estimates for the alternative.
TABLE 6-6
COST ESTIMATE SUMMARY - RUNWAY ALTERNATIVE C
Item Amount Unit Cost Total Cost
Asphalt Pavement Removal 22,000 SY $5.00 $110,000.00
Asphalt Pavement Reclamation 26,000 SY $3.00 $78,000.00
Unclassified Excavation 5,000 SY $8.00 $40,000.00
Proofrolling 26,000 SY $1.00 $26,000.00
Limerock Base Course (3 ") 2,300 CY $30.00 $69,000.00
Bituminous Surface Course (3") 4,500 tons $45.00 $202,500.00
Bituminous Prime Coat 6,800 gallons $2.00 $13,600.00
Reflectorized Pavement Marking 5,000 SF $1.00 $5,000.00
Drainage Lump Sum $15,000.00 $15,000.00
Grassing 8 acres $2,000.00 $16,000.00
Sodding 7,000 SY $3.00 $21,000.00
Topsoil Placement 3,800 CY $5.00 $19,000.00
Mobilization $43,057.00
Contingencies (14% of Construction Costs) $86,114.00
Engineering (Design, Bidding, Construction, Inspection) $148,854.00
TOTAL $893,125.00
Source: THE LP A GROUP INCORPORATED, 2001.
Selection of the Preferred Runway Alternative
Typically at an airport like Sebastian Municipal, the most advantageous alternative would be the one that satisfies
all of the requirements for the least cost. However, this does not necessarily translate into the most desirable or
preferred alternative for the airport or community as a whole. Both ofthe alternatives, which utilize the existing
Runway 13-31 alignment, would certainly be more cost-effective and pose less of an overall impact. However,
by selecting either of the Runway 13-31 alternatives, it seems that nearly all of the effort that was put into the
previous master plan, including the public participation, would be ignored. The re-opening of Runway 9-27 is a
very good option for the airport and community. Unfortunately, it is also the most expensive option.
2002
6-14
1;-
, I
I
I
I
I
I
I
I
I
I
I
I
I
i
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTIAN
~.'
~~~
HOME Of PWCAN ISLAND
Nonetheless, since the previous study, many things have changed affecting the development of the airport,
possibly the most significant being the passage of the AIR-21legislation (reference financial feasibility text).
A detailed Environmental Assessment (EA), which was conducted as part of the previous master plan, supported
the re-opening of Runway 9-27 and closing of Runway 13-31. This EA was approved in a letter from the FAA
dated March 9, 1994. Because a significant amount of time has passed since this assessment was conducted, and
since this preferred alternative has a different runway length, the EA will need to be re-evaluated. Conversations
with the FAA Airports District Office (ADO) in Orlando confirmed the fact that this process will simply require a
detailed letter addressing each and every section of the previous EA. This letter will need to document whether or
not there have been any changes that would impact the findings of the previous study. Based on the work
conducted to date for this study, it is not anticipated that there have been any significant changes that would
prevent the FAA from revalidating the EA to re-open Runway 9-27.
With respect to the additional cost of the recommended alternative, it is the opinion of this consultant that the
long-term benefits associated with this option far outweighs the additional expense. One cannot quantify in
dollars the benefit associated when the community overflights are reduced and the related quality of life is
enhanced. Conversely, it is easy to understand that three times the developable area on an airport will eventually
produce more revenue for the airport and the City in the long run. As such, Alternative A has been selected as the
preferred runway alternative for this study. Therefore, this runway configuration will be utilized throughout the
rest of this alternatives analysis.
Taxiway Alternatives
Upon first examining a layout of Sebastian Municipal, one of the most notable deficiencies is the lack of taxiways
to efficiently serve users of the airfield. Therefore, an important consideration when examining airfield
alternatives is to properly plan for taxiways to serve not only existing activity, but also that which may develop in
the future. Likewise, while airfield access is possible through use of the existing pavement, the ultimate goal
should be to provide a parallel taxiway for each runway and the necessary connectors to efficiently link aircraft
facilities to the runway system.
Many of the taxiway characteristics are predetermined by FAA standards relative to the Airport Reference Code.
The FAA requires a taxiway width of 25 feet for Design Group I aircraft and 35 feet for Design Group II.
However, all of the taxiways at Sebastian Municipal will need to be 35 feet wide and constructed to pavement
standards, which are capable of handling the future critical aircraft (King Air 200). Likewise, any future parallel
taxiways need to have a runway centerline to taxiway centerline separation of at least 240 feet. This will preserve
the option of providing non-precision approaches (with not lower than % of a mile approach visibility minimums)
to each runway end. The following sections discuss the opportunities that are available for taxiway development.
Parallel Taxiway to Runway 4-22
Currently, access to both ends of Runway 4-22 is sufficiently served by the existing taxiways. However,
once Runway 9-27 is re-opened, the access from the west side of the airport to Runway 22 will become
difficult. This access will require a portion of the abandoned Runway 13-31 alignment to be used if back
taxiing is to be avoided. But, depending on how fast the airport develops, this route may not be available;
as it would ultimately be broken up by the landside access necessary to access facilities on the north side
of Runway 9-27. This problem would be solved if a full-length parallel taxiway were developed on the
north side of Runway 9-27, as discussed in the following section.
2002
6 -15
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTIAN
~
~~~
HOMI Of PnICAN ISLAND
I
I
For Runway 4-22, a full-length parallel taxiway will not be crucial until the South Infield area is
developed. At that time, the existing north-south taxiway will be severed in order to provide landside
access into the South Infield area. Until then, access to Runway 4 can be achieved through the use of the
north-south taxiway. For access to Runway 22, either the abandoned Runway 13-31 alignment can be
utilized or a future parallel on the north side of Runway 9-27 can be used for access to the existing partial
parallel to Runway 22.
I
I
Parallel Taxiway to Runway 9-27
I
Once Runway 9-27 is re-opened, the most important taxiway development will be the construction of a
full-length parallel to this runway. As stated previously, although Runway 9-27 is a Design Group I
runway, the full-length parallel taxiway will need to be constructed to accommodate Design Group II
aircraft. Therefore, it should be constructed to a width of 35 feet and at a centerline separation of 240
feet.
I
As described in the discussion related to the parallel taxiway to Runway 4-22, the need for a full-length
parallel to Runway 9-27 will greatly depend on how fast the airfield is developed. In the meantime,
although not the most direct route, aircraft will be able to utilize the Runway 13-31 pavement to gain
access to the Runway 22 and 27 ends. Nonetheless, a full-length parallel taxiway to Runway 9-27 should
be constructed as soon as it is feasibly possible.
I
I
While it is possible to provide airfield access no matter which side of Runway 9-27 the parallel taxiway is
on, the recommendation is to construct it on the north side. By building this taxiway to the north, most
aircraft only have to cross a runway when taxiing to the Runway 4 end. In addition, nearly all of the
existing airfield development is located on the north side of Runway 9-27, and a majority of the future
aviation related development would also occur to the north. Therefore, it would not make sense to
construct the parallel taxiway on the south side of the runway. Ultimately a partial parallel may be
required on the south side, but this would depend solely on the location and configuration of any facilities
constructed to the southeast or in the South Infield area.
I
I
I
North-South Taxiway
I
I
Of the active taxiways serving the airport, the north-south taxiway is the most utilized. Currently this
taxiway runs along the old Runway 18-36 alignment, which like all of the other runways, was constructed
to a width of ISO feet. Because most of the airport facilities have been constructed along the west side of
this pavement, and subsequently park aircraft along both sides, this pavement acts more as a taxilane and
ramp than that of a taxiway. There are times when the parking of aircraft along this taxiway are such that
the required object free area is encroached, and other times when taxiing aircraft have to actually weave
through parked aircraft.
I
I
The only true alternative for this taxiway is to provide a 35-foot wide alignment that can maintain an
adequate object free area. Because all of the existing hangars are located along the west side of the 150-
foot pavement, the most parking and maneuvering space (into and out of hangars) would be realized if the
easternmost 35 feet were utilized. While this would create the most space in front of the existing
facilities, it would eliminate the single row of aircraft tiedowns. As such, the designation of this taxiway
alignment would need to coincide with the construction of additional ramp space to replace the dislocated
tiedowns.
I
I
2002
6 -16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlB~T!AN
~..p~_.,.
~~
ttOMt Of PWCAN rstAND
Once Runway 9-27 is open, the north side of this taxiway will no longer run between active runway ends.
Therefore, when designing the additional tiedown space, the north half of the north-south taxiway is truly
better described as a taxilane. Therefore, the Design Group II standards of 115 feet for a taxilane object
free area were employed. The taxi lane designation however will end at the intersection of the north-south
taxiway and the future north parallel to Runway 9-27. Conversely, the south half of the north-south
taxiway will need to maintain the full 131-foot taxiway object free area, as it will still connect the
approach ends of Runway 4 and 9. As with the north half, the south half should also be constructed on
the east side of the 150-foot wide pavement. In addition to providing more space for future aviation
related development off of Airport Drive West, it also maintains a uniform intersection with the approach
end of Runway 9.
GENERAL AVIATION ALTERNATIVES
The analysis of general aviation alternatives focuses on future Fixed Base Operator (FBO) development. It is
envisioned that this complex will serve many functions, which shall include a general aviation terminal,
administration building, and hangar development. However, before options for future FBO development can be
explored, the needs of the existing tenants must be considered first.
Relocation of Existing Tenants
As mentioned previously, the re-opening of Runway 9-27 will require two existing airport tenants to relocate.
Likewise, the future development of the airfield will also have an effect on the operations that are conducted by
Skydive Sebastian. The subsequent sections address some of the issues related to these tenants and the relocation
of their operations.
South Portion of Velocity Leasehold
On the west side of the airport, a 10,000 square foot building occupied by Golden Horn Aviation and
Velocity will need to be relocated, as well as the south portion (four acres) of the land leased by Velocity.
Discussions between the City and this tenant have resulted in a mutually agreed upon site, located across
the north-south taxiway. This site, depicted on Exhibit 6-4, reserves an equal area to that displaced, just
east of the north portion of Velocity's leasehold.
While an initial estimate has been made for the cost to relocate the 10,000 square foot building, details of
the exact transaction will change as future conversations and negotiations between the airport and
Velocity evolve. Although it is easy enough to reserve an equal amount of land and construct a similar
facility, at some point a compromise will have to be made with respect to short and long-term access to
the new site.
JS Aviation Leasehold
At the time of this writing, only preliminary discussions have been held between the City and the tenant
(JS Aviation) regarding need to be relocated. JS Aviation has a leasehold of approximately two acres and
their facilities include an aircraft parking ramp, an enclosed hangar building, a fuel farm, an automobile
parking lot, and a shade hangar. Until input can be obtained from JS Aviation, no sites have been
analyzed for this relocation. The facilities that will need to be relocated are depicted on Exhibit 6-4.
2002
6-17
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEB~T~
~
~~
HOME Of PWCAN ISlAND
Skydive Sebastian Landing Zone
Currently, Skydive Sebastian utilizes the North Infield area as a landing zone for its sky diving
operations. At present, there is no lease between the City and Skydive Sebastian for the exclusive use of
this area. As such, when the north side of the airport eventually develops, these operations will have to
occur elsewhere on the airfield. Two alternative sites are depicted on Exhibit 6-4.
According to information provided by Skydive Sebastian, the minimum of a 300-foot radius is required
for landing skydivers. One 300-foot radius landing zone is depicted in the northwest corner of the airport
property. This site, while close to the existing Sky dive Sebastian leasehold, should only be considered for
a single-term lease. Ultimately, this area will become part of the industrial/commercial parcels developed
by the City. A second landing area is depicted for Skydive Sebastian in the South Infield area. This area
is similar to the space currently used. As such, a problem with this site is that, much like the existing
landing area, jumpers must cross an active taxiway to return to Skydive Sebastian's facilities. Even
worse, in the future, if these jumpers are not properly escorted, they may also cross an active runway
(once Runway 9-27 is re-opened).
While the South Infield area is immediately available, the site in the northeast corner will obviously rely
on the closing of Runway 13-31. However, the existing landing zone in the North Infield area should not
be developed (other than the relocation of Velocity) until after the closure of Runway 13-31. In the
meantime, the City and Skydive Sebastian need to continue conversations to determine which option will
be pursued.
FBO Alternatives
The following sections present an overview of three FBO development alternatives. Cost estimates for the
various FBO alternatives have not been developed, as it is assumed that most of the FBO and/or conventional
hangar development costs will be born by the developer of the facility and not by the City. Likewise, all three of
the alternatives have the same number, type, and size of facilities in each layout, which are based on the findings
of the facility requirements. Also, it was assumed that the costs associated with the administration building
portion of the development would be the same for the City, no matter which location is selected. Therefore, the
sites were evaluated using a matrix with a variety of selection criteria.
Alternative A - North of Runway 9-27
Alternative A attempts to achieve the most centralized airfield location, with respect to the ultimate
runway configuration. A site such as this will provide the most visibility and shortest taxi times to each
runway end. This concept places the main FBO terminal in the middle of the development, serving to
separate the two different functions ofthe layout. Alternative A is depicted on Exhibit 6-5.
To the east of the FBO building is the operational side of the complex, while the west provides t-hangars
and tiedown space for private aircraft storage. Essentially, this design enables the FBO facility to
segregate the different needs of itinerant and local operations. Arrangement of the buildings are such that
none of the required standards, including object free areas, building restriction lines, and the runway
visibility zone, are violated.
Layout of the apron provides adequate spacing so that a 25-foot apron edge taxilane will maintain the
proper Design Group II centerline separation from the full-length parallel taxiways to both Runway 4-22
2002
6 -19
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~-'
~ - ."-..,,
- -~''''">__ "'i--
HOME Of PUlCAN ISlAND
I
I
and Runway 9-27. While this configuration could temporarily tie into the existing partial parallel taxiway
to Runway 4-22, it would require the reconfiguration of the fuel farm installation.
Alternative B - South Infield Area
I
Applying the concept of providing a centralized airfield location on the southwest side of the runway
intersection results in the FBO complex shown as Alternative B. However, because the runways form an
acute angle, the facility cannot be placed as close to the runway intersection. In fact, the layout for
Alternative B (shown on Exhibit 6-5) is primarily driven by the limitations of the building restriction
lines off both runways.
I
I
Because the proposed FBO clearspan hangar is assumed to be taller than the terminal building, it needs to
be further away from the runway centerlines. This limits the ability of the layout to segregate local from
itinerant needs. As with Alternative A, this option could place the FBO terminal in-between the clearspan
hangar and t-hangar facilities, but this would place the t-hangars closest to the runway intersection and in
effect, coffin corner the other FBO facilities towards the approach to Runway 4.
I
I
Layout of the aircraft parking apron provides the capability to support aircraft operations. The set back
from the parallel taxiway to Runway 4-22 is such that an apron edge taxilane could be used to provide
flexibility in the ramp layout. However, because of the proximity of the taxilanes to and from the t-
hangars, aircraft movements in, out, and around the area just in front of the clearspan hangar could be
constrained.
I
I
Alternative C - Southeast Side of Airport
I
The FBO complex depicted on Exhibit 6-5 for Alternative C is exactly the same as Alternative A, only
on the other side of the runway intersection. Although the thought behind these two layouts are similar,
there are still some significant differences that should be noted.
I
Of the three alternatives, this is the only one located on the east side of the airport. Because of the airport
configuration, this option relies on landside access off of Airport Drive East. This means that all of the
vehicular traffic using these facilities will use Main Street to get to U.S. I or County Road 512 (Fellsmere
Road). However, such a facility is not expected to generate a lot of traffic, especially when compared to
the daily traffic that is generated by the City's Municipal Golf Course.
I
I
I
With respect to airfield access, Alternative C is significantly different since it is not located on the sides
of the runway that have the full-length parallel taxiways. Thus, connector taxiways must run from the
FBO apron area, to and across both runways to provide complete airfield access. Beyond the additional
costs, this requires all aircraft going into and out of this area to cross an active runway.
I
I
I
2002
I
6-20
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBASTIAN
~~
. -. ...~ ~~. .,
--'"'-~-........ -
HOME Of PUlCAN rslAND
Evaluation of FBO Alternatives
While only a single FBO alternative will be recommended to serve as the framework for future development, all
or part of each layout could eventually be developed. Therefore, the concepts are evaluated within this section to
reveal the positive and negative aspects of each in comparison against the others. Thus the alternatives were
evaluated within the following categories: flexibility, phasing/construction, environmental effects, operational
effectiveness, and safety considerations.
Flexibility - pertains to the total growth potential of each alternative site and the process inherent to
achieving that growth. The evaluation criteria associated with this category include the ability to respond
to uncertain demand levels, the balance of support functions, and the ability to satisfy changing tenant
demands.
Phasing/Construction - pertains to designated land uses and associated impacts to on-airport operations
and the level of difficulty involved in implementing the proposed land uses. The evaluation criteria
associated with this category include the ability to phase construction, the impact on existing facilities,
and the ability to incrementally expand site development.
Environmental Effects - performs a general assessment to determine the degree proposed land uses would
potentially impact various components of the surrounding environment.
Operational Effectiveness - compares the overall efficiency levels and usage of existing or proposed
infrastructure associated with the general aviation area. The evaluation criteria associated with this
category includes the compatibility with the long-range airfield, roadway access to development area, the
competitive environment, and assures the highest and best use.
Safety Considerations - measures each component for compliance with FAA standards that have a direct
effect on the daily operations and safety at the airport facility. Evaluation factors include the overall
compatibility with the areas of aircraft operation, FAR Part 77 surfaces, airfield design standards, and
airport security.
Table 6-7 presents an evaluation matrix that addresses the aforementioned criteria. This matrix summarizes the
analyses of the development concepts, also presented in the following paragraphs.
Flexibility
Ability to Respond to Uncertain Growth - The ability to respond to uncertain demand levels determines
each concept's ability to accommodate demand in excess or lower than anticipated. Alternative A
provides the best alternative to accommodate future demand due to the available space on this side of the
runway intersection. Alternative Band C both suffer from being limited in the ability to expand. Of the
two, Alternative C is constrained by the imaginary surfaces of the airfield and the proximity of the City
golf course. Alternative B is also constrained by the airfield's imaginary surfaces, but could expand to
the west. However, such an expansion would confine the FBO complex to one corner of the airport.
Balance of Support Functions - This factor evaluates the siting of support functions such as fueling,
airport maintenance, and like facilities. The ideal is to locate these facilities with access and to centrally
orientate them to serve proposed aviation related development. Of the three concepts, Alternatives A and
C were deemed to provide adequate locations for the siting of support facilities. Conversely, Alternative
B was not as desirable, as maintenance, fueling, and other operations will appear to conflict.
2002
6-22
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
S[BAST~
~~
. _~'-. -r ". '-' -- ,__
--,- -., -
HOME Of PU.ICAN ISlAND
I
I
Ability to Satisfy Changing Tenant Demands - This factor evaluates the ability to accommodate changing
needs of FBO operations and other private and corporate tenants. While not required during the 20-year
planning period, Alternative A offers the most opportunity to develop additional land abutting the site.
Thus, Alternative A possess greater ability to satisfy changing tenant demands when compared to
Alternative B which can only expand into an isolated area and Alternative C which is simply limited for
space.
I
I
Phasing/Construction
I
Ability to Phase Construction - This factor examines the impact of construction on airport operations,
potential relocations, and other airport related activity. Phasing of any development must be considered
in light of operations taking place at the time of construction. Only Alternatives A and B will impact the
airfield operations during construction. Both do so by interrupting taxiway access to a runway end.
Alternative C poses no phasing or construction related impacts. This analysis assumes that Runway 13-
31 is closed, and Runway 9-27 is re-opened, before any of the alternatives are implemented.
I
I
Impact to Existing Facilities - This factor evaluates the impact to existing airport facilities the new
development may affect, including its operation or function, or require its relocation. To fully implement
the layout associated with Alternative A, the partial parallel taxiway to Runway 4-22 will have to be
considered. As stated previously, either Alternative A's layout will need to be modified, or the portion of
the new parallel taxiway between the approach end of Runway 22 and Runway 9-27 will need to be
constructed. In order to provide landside access to Alternative B, the existing north-south taxiway will be
split between the approach ends of Runway 4 and 9. Again, assuming that Runway 13-3 I is closed, and
Runway 9-27 re-opened, Alternative C does not pose any impact to the existing airfield facilities.
I
I
I
Ability to Incrementally Expand - This factor evaluates the ability for the site build-out to be conducted in
phases and its impact on operations. There would be no additional impact if each of the three alternatives
were to develop to their full potential.
I
Environmental Effects
I
Analyzing each of the three FBO alternatives, no differences regarding environmental effects were
evident. Based on the information available, none of the three options will impact wetlands, endangered
species, historic sites, compatible land uses, or any other environmental elements.
I
Operational Effectiveness
I
Compatibility with Long Range Airfield - This factor evaluates potential operational problems that may
exist over the long-term development of the airfield. By assuring airfield components meet the needs of
activity generators, the efficiency of the airport is maintained. Ultimately, only Alternative A would not
have an impact on the long range airfield operation. As previously mentioned, Alternative B will
discontinue the ability of aircraft from the northwest side of the airport to directly access the approach end
of Runway 4. To a much lesser extent, aircraft taxiing to and from the site of Alternative C will always
have to cross active runways.
I
I
Roadway Access to Potential Development Areas - This factor addresses the ability of the eXIstmg
roadway network to accommodate the proposed alternative. While all of the concepts require the
I
2002
6-23
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~~
__ ",.r- -.;,:: _
-~"v_" --~
HOME Of P'WC.AN ISLAND
construction of new roadways for access, they do so to different extents. Alternative A will require the
longest access road, Alternative C the second longest, and Alternative B the shortest of all three.
Competitive Environment - This factor addresses the siting of the FBO terminal and operations, and the
ability of the site to maintain equal competition between the operations. There is an inherent belief that
transient traffic uses the first FBO facility that they identify when taxiing. As such, Alternative A
provides the most competitive site, with Alternative C following next, and Alternative B as the least
competitive.
Safety Considerations
Compatibility with areas of aircraft operation and Part FAR 77 Surfaces - This factor examines the
ultimate impact to airfield compatibility, with a keen interest in preserving and enhancing safety and
impacting navigable airspace. All three of the alternatives have been designed such that they are
compatible with the standards of these criteria.
Airport Security - This factor evaluates each concept's potential to preserve or enhance safety and
security on the airfield. With their proposed layouts, all three concepts will maintain a high level of
safety and security on the airfield.
Recommended FBO Development Alternative
The recommended FBO alternative for Sebastian Municipal is based on the qualitative assessment summarized in
Table 6-7. The evaluation scores afford a measurable assessment of the three options with respect to the criteria
described previously.
Alternatives A and C were considered comparable in many of the categories; however, the differences between
the flexibility and operational effectiveness made Alternative A more advantageous. Overall, Alternative B had
too many deficiencies, especially those related to the interruption of the north-south taxiway, for it to be
considered. Therefore, the recommended FBO development site is Alternative A.
2002
6-24
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SEBAST!AN
~'~
.- ."~ -..;: ---.
. ----,- _. '" .-
ttOMI Of PWCAN IS1.ANO
TABLE 6-7
FBO ALTERNATIVES EVALUATION MATRIX
Evaluation Factors Alternative Alternative Alternative
A B C
Flexibility
Ability to Respond to Uncertain Demand Levels 4 2 I
Balance of Support Functions 4 2 4
Ability to Satisfy Changing Tenant Demands 4 3 2
Subtotal 12 7 7
Phasing/Construction
Ability to Phase Construction 2 2 4
Impact to Existing Facilities 2 2 4
Ability to Incrementally Expand 3 3 3
Subtotal 7 7 11
Environmental Effects
Environmental 3 3 3
Subtotal 3 3 3
Operational Effectiveness
Compatibility with Long Range Airfield 5 I 2
Roadway Access to Potential Development Areas 3 5 4
Competitive Environment 5 3 4
Subtotal 13 9 10
Safety Considerations
Compatibility wi Operations and Part 77 Surfaces 3 3 3
Airport Security 4 4 4
Subtotal 7 7 7
Evaluation Score 42 33 38
Source: THE LPA GROUP INCORPORATED, 2001.
Legend: 1 - Poor
2 - Fair
3 - Satisfactory
4 - Very Good
5 - Excellent
NAVIGATIONAL AIDS ALTERNATIVES
Analyses were conducted to determine the viability of establishing non-precision approaches to the ends of
Runway 4-22 and Runway 9-27. Any non-precision approach for Sebastian Municipal would use Global
Positioning Satellite (GPS) technology. The FAA guidelines and criteria for approaches using this equipment are
contained in Order 8260.38A, "Civil Utilization of Global Positioning System." For this analysis, it was assumed
that the actual cost (or better, time and effort) associated with establishing a non-precision GPS approach at
Sebastian, was the same, no matter which runway end. Therefore, potential approaches were primarily evaluated
based on their impact to the community and their potential with respect to obstructions.
For Runway 4-22, a non-precision instrument approach would require a 34: I approach slope surface. Both ends
of this runway would require tree trimming and/or removal to accommodate an unobstructed non-precision
approach surface. In addition, the approach to Runway 4 would also require four of the power poles located along
the right-of-way for Roseland Road to either be lowered or removed and the utility to be placed underground.
2002
6-25
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBAST~
~.r',.----.
~~
HOMI Of PWCAN I:S1.AND
While this is not impossible, it does make the establishment of an approach to Runway 4 a bit more difficult and
expensive. The obstructions to both ends of Runway 4-22 are addressed in the Airport Layout Plan (ALP) chapter
and depicted on sheet four of the ALP set.
Because Runway 9-27 has been designed for small airplanes (less than 12,500 pounds) with less than 10
passenger seats, it is considered a utility runway, as defined in FAR Part 77. This designation allows Runway 9-
27 to have a non-precision instrument approach with only a 20: I approach slope surface. Nonetheless, as with the
primary runway, both ends of Runway 9-27 would require a number of trees to either be lowered or removed
altogether. Additionally, for the approach to Runway 9, two ofthe power poles located along the right-of-way for
Roseland Road will have to either be lowered or removed and the utility placed underground to provide an
unobstructed 20: 1 approach slope surface. However, these poles will be mitigated as part of the re-opening of
Runway 9-27. Obstructions to the ends of Runway 9-27 are addressed in the ALP chapter and depicted on sheet
five of the ALP set.
Sebastian Municipal's proximity to the Atlantic Ocean provides the most significant impact as to which runway
end would provide the most desirable non-precision approach. The prevailing winds tend to come from an
easterly orientation, favoring the approaches to Runway 4 and 9. Similarly, due to the location of the airfield,
with respect to the Atlantic coastline, it is assumed that most aircraft would arrive from the north, west, or south.
Thus, any approaches on this side of the airport would be more desirable (such as Runway 4 and Runway 9) as
pilots prefer a more direct route into an airport. Approaches made in from the east side of the airport (to Runway
22 or 27) would most likely necessitate arrival procedures that would take any traffic from the north, west, or
south out over the Indian River or possibly the ocean, before turning in-bound for the final approach.
With respect to overflights, approaches to both Runway 4 and Runway 9 would provide the least amount of
impact to the surrounding community. Similarly, an approach to Runway 22 would have little impact, but suffers
from the drawbacks associated with routing traffic over communities when serving aircraft that approach the
airport from the north, west, or south. Nonetheless, the first non-precision instrument approach should be
established for Runway 4-22 since it is the primary runway, capable of handling the most demanding aircraft
(ARC B-II) expected to use the airport. An approach to the crosswind runway should only be considered after at
least one approach has been established to the primary runway. Thus it is recommended that the first non-
precision instrument approach be established to Runway 4. Next, either an approach to Runway 22 or Runway 9
could be established, and finally, an approach to Runway 27 should be considered last.
ECONOMIC DEVELOPMENT AL TERNA TIVES
The land at an airport that is not needed for the ultimate airfield facilities should be used for economic
development opportunities. Those areas that are adjacent and/or have the ability to access the runway and
taxiway system should be reserved for aviation related expansion, while the rest can be used for compatible non-
aviation related facilities. Primarily, this section identifies and evaluates the opportunities that are possible given
the previous alternative analyses. The development of realistic economic opportunities will require close
coordination with the staff from the City of Sebastian to ensure that efforts by the City, as well as those suggested
in this study, are coordinated.
For discussion purposes, the airport was previously divided into four quadrants and the two infield areas. These
areas were based on the Runway 4-22 and Runway 13-31 configuration. Despite the fact that Runway 13-31 will
be closing, these six areas remain relatively the same, with the exception that the North Infield area would be part
of the North Quadrant, once Runway 9-27 is re-opened. Other variations are addressed in the following sections
concerning the viability of supporting future economic development options within these areas.
2002
6-26
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
S[BAST~
~.~~.-,..
~~
HOMI OF PWCAN ISLAND
North Quadrant
Currently there is no landside access to the north side of the airport. Any future access should come off of Airport
Drive West, to prevent any additional curb cuts on Roseland Road. Therefore, while this area provides the most
land available for future development, both aviation and non-aviation related, it will require improvements for
access and utilities. Nonetheless, given the other areas on the airport, the North Quadrant will be the area for
most of the airport's future economic development.
South Quadrant
Previously this portion of the airport was unavailable for development, however, this will change when the South
Quadrant's boundaries are defined as the area between the approach ends of Runway 4 and Runway 27. As
depicted on Exhibit 6-1, ultimately this area will create an additional 17 acres of developable land. Due to the
proximity of this land to the airfield, only aviation related facilities should be considered in the future for the
South Quadrant.
When this area is developed, landside access could utilize the taxiway pavement that currently connects the
approach end of Runway 31 with the pavement of the Runway 9-27 alignment, as it will no longer be needed
when Runway 13-3 I closes. This taxiway pavement would tie into Airport Drive East, which is also how utilities
would be routed to serve this quadrant.
East Quadrant
Under the new runway configuration, this quadrant will decrease in size as it will now only cover the area
between the approach ends of Runway 22 and 27. A future aviation or even non-aviation tenant could develop in
this area, however due to its remote location and the costs for access and utilities, the area would better serve as a
location for airfield related facilities, such as a maintenance building and/or electrical vault.
West Quadrant
Parcels on the west side of the airport provide the most immediate capability to accommodate future development
opportunities. The ability to quickly provide access and utilities to the undeveloped parcels in this area make it
the most desirable with respect to short-term development. While there are only a limited number of parcels
remaining that would have access to the airs ide, a good amount of space exists for non-aviation related uses.
Future development must ensure that the approach, transitional, and other surfaces related to Runway 9-27 must
not be encroached. Any development that penetrates the required surfaces and/or design standards could have
severe implications on the viability of this runway.
South Infield
Because it lies within the confines of the two runways and an important taxiway, the South Infield area should be
reserved only for development when the other areas of the airport approach saturation. As mentioned in the FBO
alternatives, land access into this area would sever the north-south taxiway and drastically increase taxi times for
nearly all of the airfield users. Therefore, this area should remain undeveloped for as long as possible.
2002
6-27
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SEBASTIAN MUNICIPAL AIRPORT
Master Plan Update
(]!'f(J
SlBASY!AN
~-'
-. .,-......." -,
. -" ~_...... --
HOMt Of PWCAN ISLAND
SUMMARY OF AIRPORT ALTERNATIVES
The preceding sections have identified and analyzed a number of planning alternatives for future development at
the Sebastian Municipal Airport. The alternatives presented focused on meeting future facility needs at the airport
while maintaining operational efficiency and safety standards. The positive and negative aspects of each
alternative were presented and discussed to provide an indication of differentials between various options.
In summary, despite the additional costs, the option to re-open Runway 9-27 and subsequently close Runway 13-
31 was selected as the most advantageous. As a result, all of the preceding sections of this analysis were based on
the new configuration of the airfield. With the new configuration of the airfield, the analysis related to the
taxiway system was simplified. The resulting layout preserved the existing north-south taxiway and
recommended a full-length parallel on the north side of Runway 9-27 and a full-length parallel on the west side of
Runway 4-22.
The analysis of the FBO alternatives indicates that Alternative A is the most effective at meeting the future needs
of the airport while also providing the best operational environment. Both of the other FBO alternatives involved
some type of compromise in effectively serving the airport's needs, and were not considered optimal for the
overall airfield development. Future non-precision approaches could be accommodated on each of the four
runway ends; however, it was determined that approaches to serve aircraft arriving from the west side (Runway 4
and Runway 9) should be the first approaches established. Finally, it was determined that future economic
development, both aviation and non-aviation related, should occur on the west side of the airport and then to the
north. Developable land on the south and east side of the airport should be reserved for more specialized uses,
while the land in the South Infield area should not be developed until it is absolutely needed.
After discussions with the Technical Review Committee, FDOT, FAA, Airport Management, and City staff, as
well as any feedback from the public presentation, these selected alternatives will be consolidated. This task,
which is addressed in the following chapter, may result in the revision of options or the combination of individual
alternatives into a single alternative for implementation. Once combined, the consolidated alternatives will be
utilized in the layout plans for the airport.
2002
6-28