HOME OF PELICAN ISLAND CITY COUNCIL AGENDA TRANSMITTAL FORM
Council Meeting Date: 13 August 2014
Agenda Item Title: Engineering services Schulke Bittle & Stoddard (Schulke)
Recommendation: Approve work scope & fees for supplemental engineering
from Schulke for $12,500 on Fish House Refurbishment
at the Sebastian Working Waterfront.
Background: On 26 February 2014, Council approved a contract with
Schulke for engineering services on the Fish House
project with a fee of $54,500. Presently, the project
requires additional engineering to the preliminary plans
per comments received from Florida Department of
Environmental Protection (FDEP) as well as some
changes needed for the Fisherman's handing museum
site work. In addition, permitting with the US Army Corp
is required for this project which was not part of the
original scope of work.
If Agenda Item Reguires Expenditure of Funds-
Add-on Cost: $12,500
Total Cost: $54,500 +$12,500 = $67,000
Amount Budgeted in Current FY: $482,350
If Cost Requires Appropriation: nla
Amount of Appropriation Required: nla
Fund to Be Utilized for Appropriation: Fish House Pr je t: D T & F.I.N.D. grant
Administrative Services Department Review: -
Attachments: Schulke Work Scope and Fee schedule
City Manager Authoriz tiom
K
Date: 06 August 2014
JOSEPH W. SCHULKE, P.E.
JODAR B. BITTLE, P.E.
WILLIAM P. STODDARD. Ph.D., RE
July 11, 2014
SCHULKE, BITTLE & STODDARD, L.L.C.
CIVIL & STRUCTURAL ENGINEERING • LAND PLANNING • ENVIRONMENTAL PERMITTING
Frank Watanabe, P.E.
Community Development Director /City Engineer
City of Sebastian
1225 Main Street
Sebastian, FL 32958
Re: Fisherman's Landing
Dear Mr. Watanabe:
Please accept this as my formal request for an approval of Amendment No. I to Work
Authorization No. 01 between the City of Sebastian and Schulke, Bittle & Stoddard, LLC. The
amendment is necessary to provide additional services as requested by the City for the
Fisherman's Landing project, including:
Site Plan 1 Uplands development area:
• Provide design of sign - provide location on site plan, and structural design of the sign -
which will identify the project as a recipient of state grant funds - via the Stan Mayfield
Working Waterfront ".
• Provide grade level "board walk" from the restaurant to the proposed north access pier,
and several benches and an info kiosk or display area.
Fisherman's Landing marina:
• Relocate the Aquaculture area from the west side of the fish house to the south side of
the southern pier.
• Revise submerged land lease area to include the new aquaculture area.
• Prepare ERP permit applications to FDEP and ACOE for the relocation of aquaculture
site.
• Prepare Biologists assessment and seagrass survey of the marina basin and new
aquaculture area.
• Survey - additional bathymetric survey of aquaculture area.
Contract administration:
• Provide assistance to the city engineer - preparation of bid docs. (see attached example
table of contents). The Bid docs are anticipated to be as follows:
o Division 0 - (Front end docs) - Bidding requirements, contract form and
requirements - prepared by city. SBS will review and offer recommended
changes
Division 1 -- "General Requirements" - prepared by SBS - to be added to City's
front end - prepared In letter size format
o Division 2 -16 - Construction specifications - prepared by SBS - due to simple
nature of this project, specifications anticipated to be provided on plan sheets
(not letter size format)
1717 INDIAN RIVER BLVD., SUITE 201 -, VERO BEACH, FLORIDA 32960
TEL 772 / 770-9622 FAX 772 / 770 -9496 EMAIL infoOsbsengineersxom
Page Z of Z
Attached please find a revised Exhibit B — Fees, which includes the original contract amount,
additional fees, and total fees. I have also attached a sample Bid docs table of contents for your
information. Please do not hesitate to contact me should you have any questions.
Sincerely
JosepVW %S&Mulke. P.E.
cc: Joe Griffin
Cynthia Watson, Environmental Specialist
4! EN RE ?RCi A,t,.H APE 4NG GARDEN
S 10
TABLE OF CON ENTS
Division 0
Bidding Requirements and Contract Requirements and Forms
00010
Invitation to Bid
00020
Advertisement for Bid
00100
Instruction to Bidders
013300
1. Definition of Terms
015000
2. Questions; Addenda
017700
3. Bend RequiFernente_
4. Preparation of Bids
017839
5. Qualifications of Bidders
Division 2
6. Submittal, Receipt, and Opening of Bids
Division 3
7. Consideration of Bids and Award of Contract
Division 4
8. Acceptance of Offer
Division 5
9. TFeF161 , Safety (if appli-al-ble),
10. Conflict of Interest
Division 6
11. Insurance
12. Permits and Licenses
D hli [Rt't. 0-411
,1,3,
14. Public Disclosure Statements
00300
Bid Form
00401
List of Subcontractors
00420
Bidder Questionnaire
A101 (Pgs. 1 -10)
Standard Form of Agreement Between Owner and Contractor
A202 (Pgs. 1 -42)
General Conditions of the Contract for Construction
Division 1
General Requirements
011000
Summary of Work
012600
Contract Modification Procedures
012900
Payment Procedures
013300
Submittal Procedures
015000
Temporary Facilities and Controls
017700
CioseoutProcedures
017839
Project Record Documents
Division 2
Site Construction (See Civil drawings and Landscape Architect's drawings)
Division 3
Concrete (See Civil, Structural, Architectural, and Landscape Architect's drawings)
Division 4
Masonry (See Architectural and Structural drawings)
Division 5
Metals (See Architectural, Structural and Landscape Architect's drawings)
Division 6
Wood and Plastics (See Architectural and Landscape Architect's drawings)
Division 7
Thermal and Moisture Protection (See Architectural drawings)
Division 8
Doors and Windows (See Architectural drawings)
Division 9
Finishes (See Architectural and Landscape Architect's drawings)
Division 10
Specialties (See Architectural and Landscape Architect's drawings)
Division 11
Equipment (See Architectural and Landscape Architect's drawings)
Division 12
Furnishings (See Architectural and Landscape Architect's drawings)
Division 13
Special Construction (See Architectural and Landscape Architect's drawings)
Division 14
Conveying Systems - N.A.
Division 15
Mechanical (See Architectural drawings)
Division 16
Electrical (See Architectural drawings)
SEBASTIAN WORKING WATERFRONT
EXHIBIT 'B' — FEES
Original
Amendment
New
Contract
No.1
Amount
1.0
Preliminary Engineering:
N/A
N/A
NIA
2.0/3.0
Final Design and Permitting:
A. Project management / coordination
$ 4,500.00
$ 1,000.00
$ 5,500.00
B. Architectural design
$16,500.00
$ 1,000.00
$17,500.00
C. Civil engineering
e Upland site Plan:
$ 3,500.00
$ 500.00
$ 4,000.00
c Over water permitting /
wetlands:
$ 5,500.00
$ 2,500.00
$ 8,000.00
D. Environmental consultation (if
needed):
$ 4,500.00
$ 2,000.00
$ 6,500.00
E, Survey:
$ 4,500.00
$ 1,000.00
$ 5,500.00
4.0
Contract Administration & Inspections:
_ A. Assistance during contract
procurement
$ 4,500.00
- - - - --
$ 4,500.00
A -1. Assistance with Bid Doc
preparation
N/A
$ 2,000.00
$ 2,000.00
B. Inspections, assistance with
contract administration
$ 4,500.00
$ 1,000.00
$ 5,500.00
Total Professional Fees:
$48,000.00
$11,000.00
$59,000.00
Reimbursables:
$ 6,500.00
$ 1,500.00
$ 8,000.00
Total.
$54,500.00
$12,500.00
$67,000.00