HomeMy WebLinkAbout2006 - ExtensionFlorida Department of Transportation
JEB BUSH OFFICE OF MODAL DEVELOPMENT
GOVrRNOR 3400 West Commercial Boulevard
Fort Lauderdale, FL 33309 -3421
Phone: (954) 777 -4490 Fax: (954) 677 -7892
June 27, 2006
Mr. Jason Milewski
Airport Manager
City of Sebastian
1225 Main Street
Sebastian, FL 32958
Dear Mr. Milewski:
Subject: Fin. Proj. No.: 412399 -1 -9401
Description: Construct Fuel Farm
DENVER J. STUTLER, JR.
SECRETARY
Enclosed are two (2) fully executed Supplemental Joint Participation Agreements for the
subject project. Please keep this office advised of the progress on this project as required
by the JPA.
In accordance with Paragraph 18.00, as amended, the expiration date of the agreement is
October 31, 2006. At expiration, any unused funds will be unencumbered and the
contract will be canceled. In addition, paragraph 18.10 requires final invoicing within 120
days after the contract expiration date.
Should you have any questions regarding this Agreement, please call (954) 777 - 4499..
Sincerely,
Lauren A. Rand
Multimodal Coordinator
Office of Modal Development
cc: Nancy Ziegler, District Modal Development Administrator
Larry Merritt, Multimodal Programs Manager
Rebecca R. Mainardi, Aviation & Rail Section Leader
File RECEIVED
JJL 2 06
OMDSEBASTLkN
www.dot.state.fl.us OFFICE OF MODAL DEVELOPMENT MUNICIPAL AIRPORT
-off -io
Florida Department of Transportation
('11ARI.1E CRUST OFFICI: OF MODAL DEVELOPMENT ST @P1IANIE C. KOPEI,01'S )S
(:01 ERNOR 3400 West Con nacial Boulevard irC'RETAR1
Furl Lauderdale. Florida 33309- ?421
Telephone: (954)777 -149 I F'a\: f954)677-7R1)2
June 12, 2007
Mr. Joe Griffin
Airport Director
City of Sebastian
202 Airport Drive East
Sebastian, FL 32958
Dear Mr. Griffin:
SUBJECT: JPA Time Extension
Enclosed is an executed Joint Participation Agreement time extension for the following project:
Fin. Proj. No_ Descrsption
412399- 1 -94 -01 Construct Fuel Farm
Expiration
8/30/2007
If any additional information is required, please feel free to call me at {407} 617 -8087.
Sincerely,
Daniel T. Afghani
District 4 Aviation Consultant
Office of Modal Development
cc: Nancy Ziegler, Modal Development Administrator
Rebecca R. Mainardi, Aviation & Rail Section Leader
File
wn w .dot.statc.11.us
i
RECEIVED
SEBASTIAN
MUMCIPAL AIRPORT
Florida Department of Transportation
011. \RLIE CRrsr 01=17101: 01: MODAL Dl:V I-OPH-'NT STEPHANIE C. KOPELOV808
GOVERNOR 3-100 West Conunercial l3oul�:ilard SECRETARY
Fort Lauderdale, Florida 33309 -3421
Telephone: (954)777-- 14901,av (95.41677 -7892
MEMORANDUM
DATE: May 23, 2007
TO: Joe Griffin
Airport Director
Sebastian Municipal Airport
FROM: Rebecca Mainardi
Aviation & Rail Section Leader
Office of Modal Development
SUBJECT: EXTENSION OF TIME - Joint Participation Agreement
Fin. Proj. No.: 412399- 1 -94 -01 Contract No.: ANU33
The time allotted for the completion of services on subject agreement dated January 1. 2005 and any
supp[ementals thereto will expire on May 31, 2007 .
Project Description: Construct Fuel Farm
In accordance with Section 18.00 of the Joint Participation Agreement, you may request a time extension.
For your convenience, you may complete, sign, date, and return this form to me.
It is requested that the Joint Participation Agreement for the project be extended until -90 4 ,1y 0 ,% for
the following reason(s): (Use attachment if necessary) [= Lrq % t-' e' J, IIA,'s rX L,f/ t. cr✓
[!/.1 c'c1 xa- /) dc.2; Ii'1ZL"`�- 4'l' ee/,. 7;2,-)41 ! f
` ` < tZ
"P -4C l�, �7 / g % l
Agency: City of Sebastian
APPROVED:
District Project Manager
APPROVED:
0 Q-0-A
Director Tr sportati n DevelopmenV District 4
nnAV .dot.state.fl.us
Date:
Title:
Date: -a7
Date: ` �( --b`?
Florida Department of 'transportation
JEB BUSH OFFICE OF MODAL DEVELOPMENT
GOVERNOR 3400 West Commercial Boulevard
Fort Lauderdale, FL 33309 -3421
Phone: (954) 777 -4490 Fax: (954) 677 -7892
June 27, 2006
Mr. Jason Milewski
Airport Manager
City of Sebastian
1225 Main Street
Sebastian, FL 32958
Dear Mr. Milewski:
Subject: Fin. Proj. No.: 412399- 1 -94 -01
Description: Construct Fuel Farm
DENVER J. STUTLER, JR.
SECRETARY
Enclosed are two (2) fully executed Supplemental Joint Participation Agreements for the
subject project. Please keep this office advised of the progress on this project as required
by the JPA.
In accordance with Paragraph 18.00, as amended, the expiration date of the agreement is
October 31, 2006. At expiration, any unused funds will be unencumbered and the
contract will be canceled. In addition, paragraph 18.10 requires final invoicing within 120
days after the contract expiration date.
Should you have any questions regarding this Agreement, please call (954) 777 -4499.
Sincerely,
Lauren A. Rand
Multimodal Coordinator
Office of Modal Development
cc: Nancy Ziegler, District Modal Development Administrator
Larry Merritt, Multirrmodal Programs Manager
Rebecca R. Mainardi, Aviation & Rail Section Leader
File RECEIVED
Li,i 6�6
www.dot.staw.fl.us �+} }�, I I
OMD SEBASTUN
Y ww.dot.s �aw.fl.us OFFICE OF NODAL DEVELOPMENT mMCIPAL AIRPORT
STATE OF FLORfOA DEPARTMENT OF TRANSPORTATION 725430.07
PUBLIC TRANSPORTATION PUBLICTRANSPORTAPON
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT 071M
Number 1 Pool 4f s
Financial Project No.: Fund: DS FLAIR Approp.: 088719
41239919401 537 FLAIR Obj.: 750004
(Jem- segment- phas&4NLenee) Function: Org. Code: 55042010428
Contract No.: ANU33 Federal No.: Vendor No.: VF596000427008
Catalog of Federal Domestic Assistance Number. Catalog of State Financial Assistance Number: 55004
THIS AGREEMENT, made and entered Into this day of JUN 2 6 @06
by and between the STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION, an agency of the State of Florida,
hereinafter referred to as the Department, and City of Sebastian
hereinafter referred to as Agency.
WITNESSETH;
WHEREAS, the Department and the Agency heretofore on the 4th day of January 2005
entered Into a Joint Participation Agreement; and
WHEREAS, the Agency desires to accomplish certain project items as outlined in the Attachment "A" appended
hereto; and
WHEREAS, the Department desires to participate In all eligible items for this project as outlined in Attachment
"A" for a total Department Share of $260,000.00
NOW, THEREFORE THIS INDENTURE= WITNESSETH: that for and in consideration of the mutual benefits to flow
from each to the other, the parties hereto agree that the above described Joint Participation Agreement Is to be amended
and supplemented as follows;
1.00 Project Description: The project description is amended
N/A
I I
725.03007
PUBLIC TRANSPORTATK)N
07M
Paos 2 of 5
2,00 Project Cost:
Paragraph 3.00 of said Agreement is increased by $ 125,000,00
bringing the revised total cost of the project to $ 325,000.00
Paragraph 4.00 of said Agreement is increased by $ 100,000.00
bringing the Department's revised total cost of the project to $ 260,000.00
3.00 Amended Exhibits:
Exhibit(s) B of said Agreement is amended by Attachment "A ".
4.00 Contract Time:
Paragraph 18.00 of said Agreement Not Applicable
725-,a3"7
PU BLC TRA45PCR'iAT1 DN
47M
Pace 3 cf 5
Financial Project No, 41239919401
Contract No. ANU33
Agreement Date 21-IN I
Except as hereby modified, amended or changed, all other terms of said Agreement dated ,January 4th, 2005
and any subm quent supplements shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused these presents to be executed, the day and year first
above written.
AGENCY
City of Sebastian
AGENCYNAME
Al Dinner
f;TbZoiI
See atta ed Encumbrance Form ffordate of
Fun pproval by Comptroller
/ l
f (PRINTED OR TYPED) LEGAL rEW
DEPARTMENT of RTBGN
SIGNATURE
DEPARTMENT OF TRANSPO A
City Manager
TITLE
ATTEST:
i
Sally A. M io, MMC - City Clerk
Approved as to form and legality for
ref' nce by the City of Sebastian only:
T P (� S � .
Rich Stringer, City ttorney
Director of Transportation Development
TITLE
725 -030-07
PUBLIC TRANSPORTATION
07N2
Pape 4 M 5
Financial Project No. 41239919401
Contract No. ANU33
Agreement Date UUN 2 inn;
ATTACHMENT "A"
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
This Attachment forms an integral part of that certain Supplemental Joint Participation Agreement between
the State of Florida, Department of Transportation and City of Sebastian
dated
DESCRIPTION OF SUPPLEMENT (Include justification for cost change):
Funds added due to increases in construction costs and design changes.
I. Project Cost: As Approved As Amended Net Change
$200,000.00 $325,000.00 $125,000.00
Total Project Cost $200,000.00 $325,000.00 $125,000.00
I. Fund Participation:
As Approved
As Amended
Net Change
Department:
$160,000.00
$260,000,00
$100,000.00
Agency:
$40,000.00
$65,000.00
$25,000.00
Other:
$0.00
Total Project Cost
$200,000,00
$325,000.00
$125,000.00
Comments:
CITY OF SEBASTIAN
AGENDA TRANSMITTAL
Subject:
Agenda No. , "'s ,
y
Supplemental Funding for Aviation Fuel
Farm and Corporate Park Drive
Department Origin:
Airert- I
Department Head:
Finance Director:
App mittal by:
City Attorney:
City Clerk:
anager
Date Sub mitted:
6 -6 -06
For Agenda of:
6-14-06
Exhibits: (4) — Supplemental Joint Participation
Agreements from FDOT, Resolutions R- 06 -10, R-
06-11
EXPENDITURE
AMOUNT
APPROPRIATION
FUNDING SOURCE:
REQUIRED:
BUDGETED:
REQUIRED:
Airport Enterprise
$ n/a
$ n/a
$ n/a
Fund
SUMMARY
In accordance with our Joint Automated Capital Improvement Program (JACIP) through the Florida
Department of Transportation (FDOT), airport and FDOT staff have been working together to
address recent funding issues relating to two specific projects underway at Sebastian Municipal
Airport. These projects include the aviation fuel farm, whereby Council has authorized staff to solicit
bids to install a city -run aviation fuel facility; and the construction of Corporate Park Drive, which
will become the main access road into what is now the north infield area. Our goal was to solve the
issues relating to these projects without requesting to expend an added single dollar from the City of
Sebastian and /or the Airport Enterprise Fund.
Through some creative discussions with FDOT, we decided that we could transfer funds from a
future, budgeted project that isn't absolutely necessary to these two, current projects. To clarify, we
had funding ($250,000) in place to purchase additional land, in the event it was necessary. At the
present time, staff sees no need for the airport to purchase any adjacent land. Therefore, we intend to
reallocate that budgeted money to these other projects. It's important to note that this action results in
absolutely no additional cost to the City and/or the Airport. In short, we are recommending
reallocating this $250,000, to supplement the Fuel Facility ($125,000) and the construction of
Corporate Park Drive ($125,000).
W'e'll first address Lhe issues relating to the aviation fuel facility. As you're aware, staff issued a
formal Request for Proposals (RFP) for a company to install and activate an aviation fuel tank at the
airport. Thou: h we had several potential vendors attend the pre -bid meeting, not a single copmany
bid on she +roject. Through some value - engineering and some other project deletions, we
subseauently re -bid the work and received one bid. As suspected (as has been very typical with
consu-u.-iion projects in Florida, post - hurricanes), the bid was higher than the budgeted amount.
Essentially. we needed an additional $125,000 to install the tank. In addition, we had to delete the
wash rack from the project, as that would have required even more money to construct. By
reallocating the above - listed funds, this project can be accomplished without any added money from
the CiB- or the Airport Enterprise Fund.
For Corporate Park Drive, geotechnical borings indicated a much higher water table than expected.
Basically, this means that the scope of this project needs to be expanded to include some significant
drainage improvements, directly relating to the size of the retention pond needed. Though this project
is still in the planning and design phase, it is apparent that the extensive drainage work necessary will
increase the construction budget. As with the fuel tanks, staff began seeking ways to meet this
anticipated expense without expending any further funds from the City, by reallocating funds as
listed above.
To summarize, staff is requesting to cancel the project entitled "Acquire Land" for $250,000 and
reallocate those funds to the projects entitled "Construct Fuel Farm" ($125,000) and "Construct
Access Road" ($125,000). As mentioned, this recommendation results in no added cost to the City
and/or the Airport. Additionally, it is important to note that this recommendation does not include
any expenditure requests. This is simply to accept the Supplemental Grant Agreements from FDQT.
Recommendations regarding the expenditure of these funds will come before you in the future for
your consideration.
RECOMMENDATION
Move to approve Resolutions R -06 -10 and R -06 -11 authorizing staff to execute Supplemental Joint
Participation Agreements entitled "Install Aviation Fuel Farm" and "Construct Access Road" for
$125,000 each.
STATE OF FLOWDA DEPARTMENT OF TRANSPORTATION
PUBLIC TRANSPORTATION
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
Number 1
725430 -07
PUBLIC TRANSPORTA71ON
07102
Papa 1 of 5
Financial Project No.: Fund: DS FLAIR Approp.: 086719
41239919401 637 FLAIR Obj.: 750004
(item - segment- phase - sequence) Function: Org. Code: 55042010428
Contract No.: ANU33 Federal No.: Vendor No.: VF596000427008
Catalog of Federal Domestic Assistance Number: Catalog of State Financial Assistance Number: 55004
THIS AGREEMENT, made and entered into this day of
by and between the STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION, an agency of the State of Florida,
hereinafter referred to as the Department, and City of Sebastian
hereinafter referred to as Agency.
WITNESSETH:
WHEREAS, the Department and the Agency heretofore on the 4th day of January 2005
entered into a Joint Participation Agreement; and
WHEREAS, the Agency desires to accomplish certain project items as outlined in the Attachment "A" appended
hereto; and
WHEREAS, the Department desires to participate in all eligible items for this project as outlined in Attachment
"A" for a total Department Share of $260,000.00
NOW, THEREFORE THIS INDENTURE WITNESSETH: that for and in consideration of the mutual benefits to flow
from each to the other, the parties hereto agree that the above described Joint Participation Agreement is to be amended
and supplemented as follows:
1.00 Project Description: The project description is amended
N/A
2.00 Project Cost:
Paragraph 3.00 of said Agreement is increased by $ 126,000.00
bringing the revised total cost of the project to $ 325,000.00
Paragraph 4.00 of said Agreement is increased by $ 100,000.00
bringing the Department's revised total cost of the project to $ 260,000.00
3.00 Amended Exhibits:
Exhibit(s) B
4.00 Contract Time:
Paragraph 18.00 of said Agreement Not Applicable
725 -OW -07
PU9LIC TRANSPORTA70N
07102
Page 2 of 5
of said Agreement is amended by Attachment "A ".
7254mol
PUBLIC, TRANSPORTATION
071172
Page 3 of b
Financial Project No. 412399194011
Contract No. ANU33
Agreement Date
Except as hereby modified, amended or changed, all other terms of said Agreement dated January 4th, 2005
and any subsequent supplements shall remain In full force and effect.
IN WITNESS WHEREOF, the parites hereto have caused these presents to be executed, the day and year first
above written.
AGENCY
City of Sebastian
AGENCY NAME
Al Minner
S TORY (PRINTED OR T(PED)
SIGNATURE
City Manager
TITLE
ATTEST:
Sally A. MVio, MMC - City Clerk
Approved as to form and legality for
reliance by the City of Sebastian only:
t
Rich Stringer, City ttorney
FDOT
See attached Encumbrance Form for date of
Funding Approval by Comptroller
LEGAL REVIEW
DEPARTMENT OF TRANSPORTATION
DEPARTMENT OF TRANSPORTATION
Director of Transportation Development
TITLE
Financial Project No.
Contract No. ANU33
Agreement Date
ATTACHMENT "A"
SUPPLEMENTAL JOINT PARTICIPATION AGREEMENT
725 - 030 -o7
PUBLIC TRANSPORTATION
(77M
Pape 4 of 5
41239919401
This Attachment forms an integral part of that certain Supplemental Joint Participation Agreement between
the State of Florida, Department of Transportation and City of Sebastian
dated
DESCRIPTION OF SUPPLEMENT (Include justification for cost change):
Funds added due to increases in construction costs and design changes.
I. Project Cost: As Approved As Amended Net Change
$200,000.00 $325,000.00 $125,000.00
Total Project Cost $200,000.00 $325,000.00 $125,000.00
I. Fund Participation:
As Approved
As Amended
Net Change
Department:
$160,000.00
$250,000.00
$100,000.00
Agency:
$40,000.00
$65,000.00
$25,000.00
Other:
$0.00
Total Project Cost
$200,000.00
$325,000.00
$125,000.00
Comments,