HomeMy WebLinkAbout2014 09 26 Cost EstimatePRELIMINARY CONSTRUCTION COST ESTIMATES
Road Name: Grade Crossing Barber St 99th St Schumann Dr
Dixie St. and Main St
Date 9/26/14
Proiect No. Road No.:
Prepared by: FTW
Pro'ect Location: City of Sebastian
Checked by: CRW
Grade crossing improvements at five street crossings
Revised date:
Pro'ect Site: Five Grade Crossings at Barber St 99th St Schuman Dr Old Dixie and Main St
Preliminary Estimate
DESCRIPTION
QUANTITY UNITS
UNIT COST
AMOUNT
Traffic Control MOT
1
LS
$ 2,500.00
$ 2,500.00
Erosion Control and BMP's
1
LS
$ 5,000.00
$ 5,000.00
Redo driveway concrete
1
LS
$ 2,000.00
$ 2,000.00
Install 4' sidewalk
200
LF
$ 32.00
6,400.00
Install strping and pavement legends
1
LS
400.00
400.00
Install new railroad crossing gates Barber SO
2
EA
$ 75 000.00
$ 150 000.00
Install new railroad crossing gates 99th SO
2
EA
75 000.00
$ 150 000.00
Install new railroad crossing gates Schumann Dr
2
EA
75 000.00
150 000.00
Install new railraod crossing gates Old Dixie Hwy)
2
EA
75 000.00
150 000.00
Install new railroad crossing gates Main St
2
EA
$ 75 000.00
$ 150 000.00
New pavement legends and stir in
1
LS
$ 4,000.00
$ 4,000.00
Install sod and grass
1
LS
$ 2,000.00
$ 2,000.00
OTHER COSTS
SUBTOTAL
$ 766,300.00
Preliminary Enaineering
OTHER COSTS CEI Services
12 000.00
Construction Engineering
CONTINGENCIES
@ 10%
$ 76,630.00
at 12.5% Contract Cost
RW Acquisition
TOTAL
854 930.00
ROUNDED TOTAL
855 000.00
Cost for three city
crossing
513 000.00
TOTAL LOCAL COST FOR CROSSINGS
110% Local share cost
$ 50,000.00